Kasyali Khobra MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
2276 |
Sanction Cost: |
424.47 lakh |
Length:
|
8.000 KM. |
District: |
Pauri |
Block: |
Yamkeshwar |
Constituency: |
Yamkeshwar |
Circle: |
|
DEA: |
DEA Pauri |
DSC: |
Egis International |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 80
Package Name: 
UDRP/PWD/06/71/RD/069
Tender Date: 28-01-2015
Current Status: Agreement signed
Achieved on Date: 16-06-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/06/71/RD/069
Contractor Name: Balwinder Singh and Co.
|
Start Date: 22-06-2015
Intended Completion Date: 31-10-2018
Original End Date: 21-09-2016 |
Total Bond Cost: 64590492.74 (645.9 lakh)
Variation Cost: -3468998.15 (-34.69 lakh) Hence Total Bond Cost is 61121494.59 (611.21 lakh)
|
Sub Project Cost: 471.79 lakh
Variation Cost of Sub Project: -8931169.08 (-89.31 lakh)
Total Sub Project Cost:
382.48 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 10366695 for 321 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.76 KM | 19.67 | 01-07-2015 | 10-09-2015 | 1.76 KM | 1.76 KM | 5.14 | 19.67 | 2. | R/Wall, B/ Wall Type Protection works | 950.00 m | 93.71 | 01-07-2015 | 31-03-2017 | 950.00 m | 950.00 m | 24.5 | 93.71 | 3. | GSB/RBI/G-1 | 7.03 KM | 49.00 | 05-07-2015 | 22-03-2017 | 7.03 KM | 7.03 KM | 12.81 | 49.00 | 4. | G-2 | 7.66 KM | 35.54 | 01-08-2015 | 25-05-2017 | 7.66 KM | 7.66 KM | 9.29 | 35.54 | 5. | G-3 | 7.63 KM | 37.79 | 01-03-2016 | 28-03-2017 | 7.63 KM | 7.63 KM | 9.88 | 37.79 | 6. | PC/CC i/c Prime Coat, Tack Coat | 7.63 KM | 75.02 | 01-04-2017 | 31-05-2018 | 7.63 KM | 7.63 KM | 19.61 | 75.02 | 7. | Cause Way | 2.00 No | 4.62 | 01-03-2016 | 25-06-2017 | 2.00 No | 2.00 No | 1.21 | 4.62 | 8. | Culverts/Scupper | 20.00 No | 33.66 | 01-08-2015 | 10-03-2017 | 20.00 No | 20.00 No | 8.8 | 33.66 | 9. | longitudinal Drain | 4970.00 m | 7.06 | 01-03-2016 | 31-05-2017 | 4970.00 m | 4970.00 m | 1.85 | 7.06 | 10. | Crash Barrier | 100.00 m | 2.25 | 01-09-2018 | 31-01-2019 | 100.00 m | 100.00 m | 0.59 | 2.25 | 11. | Parapet | 72.00 No | 1.46 | 01-02-2017 | 31-01-2019 | 72.00 No | 72.00 No | 0.38 | 1.46 | 12. | Road Furniture | 107.00 No | 1.89 | 01-03-2017 | 31-01-2019 | 107.00 No | 107.00 No | 0.5 | 1.89 | 13. | Other Allied Works & Finishing Work | 1.00 Job | 20.82 | 01-07-2015 | 31-01-2019 | 1.00 Job | 1.00 Job | 5.44 | 20.82 |
Total Amount: |
382.49 |
|
100 |
382.49 |
|
Remarks:
No Remarks
Work Program Made On:
07-10-2015 } ?>
Updation of work program on:
08-04-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-September-2015 | 73.47 lakh | 2. | 31-December-2015 | 35.31 lakh | 3. | 31-January-2016 | 23.57 lakh | 4. | 04-May-2016 | 21.94 lakh | 5. | 05-May-2016 | 9.78 lakh | 6. | 21-June-2016 | 24.98 lakh | 7. | 31-December-2016 | 14.96 lakh | 8. | 27-March-2017 | 17.22 lakh | 9. | 30-June-2017 | 43.42 lakh | 10. | 29-May-2018 | 40.01 lakh | 11. | 14-August-2018 | 43.18 lakh | 12. | 28-February-2019 | 38.79 lakh | 13. | 09-July-2019 | 3.97 lakh |
Total |
390.6 lakh |
% Payment | 102.12 % |
|
Advance Amount: 79.88 lakh
Recovered Amount: 79.88 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 420 No. of Test Done : 441 No. of Test Passed : 422 No. of Test Failed : 19 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 86.63 |
Number of Notice(s) issued: 3 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 62 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 18-08-2018 | Ch. 6/7 | SRMD Slip and road is close | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
2. | 18-08-2018 | Ch 4/10 | SRMD slip | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
3. | 18-08-2018 | Ch 4/10 | SRMD R/Wall damage | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
4. | 18-08-2018 | Ch 2/28 | SRMD R/Wall damage | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
5. | 08-05-2018 | Site lab | Bitumin extraction test | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
6. | 04-05-2018 | Ch 1/6 | P.C work is in progress | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
7. | 04-05-2018 | Ch 1/5 | Prime coated surface | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
8. | 04-05-2018 | Ch 1/12 | Compacted PC surafce | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
9. | 23-04-2018 | Ch 0/35 | Laying of PC | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
10. | 23-04-2018 | Ch 0/35 | Checking tempeature of PC before laying | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
11. | 23-04-2018 | Ch 0/38 | Prime coated surface | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
12. | 15-12-2017 | Km 4 | Visit by S.E (PIU) sir | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
13. | 15-12-2017 | Km 8 | S.E sir (PIU) visit | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
14. | 14-11-2017 | Ch 7+600 | Chief Sir annoying because of slow and poor quality of work | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
15. | 14-11-2017 | Ch 0/0 | Chief and S.E Sir visit | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
16. | 09-11-2017 | Ch 0/8 | Comment of S.E sir on site order book page 1 | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
17. | 09-11-2017 | Ch 0/8 | Comment by S.E sir on site order book final page 3 | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
18. | 09-11-2017 | Ch 0/8 | Comment of S.E sir on site order book page 2 | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
19. | 08-11-2017 | Ch 2/29 | R/wall rejected because no slop and RR (1:5) for band is just pested from outside | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
20. | 06-11-2017 | Ch 7/12 | Parapet checked by S.E Sir found stone boulder and rejected | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
|
|