Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Kasyali Khobra MR Work Completed
Project: UDRP-RB UID: 2276 Sanction Cost: 424.47  lakh Length: 8.000 KM.
District: Pauri Block: Yamkeshwar Constituency: Yamkeshwar Circle:
DEA: DEA Pauri DSC: Egis International DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 80        Package Name:  UDRP/PWD/06/71/RD/069        Tender Date: 28-01-2015        Current Status: Agreement signed        Achieved on Date: 16-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/06/71/RD/069      Contractor Name: Balwinder Singh and Co.
Start Date:  22-06-2015      Intended Completion Date:  31-10-2018      Original End Date:  21-09-2016
Total Bond Cost: 64590492.74 (645.9 lakh)        Variation Cost: -3468998.15 (-34.69 lakh)    Hence Total Bond Cost is   61121494.59 (611.21 lakh) 
Sub Project Cost: 471.79  lakh        Variation Cost of Sub Project: -8931169.08  (-89.31 lakh)       Total Sub Project Cost:   382.48 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 10366695 for 321 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.76 KM19.6701-07-201510-09-20151.76 KM1.76 KM5.1419.67
2.R/Wall, B/ Wall Type Protection works950.00 m93.7101-07-201531-03-2017950.00 m950.00 m24.593.71
3.GSB/RBI/G-17.03 KM49.0005-07-201522-03-20177.03 KM7.03 KM12.8149.00
4.G-27.66 KM35.5401-08-201525-05-20177.66 KM7.66 KM9.2935.54
5.G-37.63 KM37.7901-03-201628-03-20177.63 KM7.63 KM9.8837.79
6.PC/CC i/c Prime Coat, Tack Coat7.63 KM75.0201-04-201731-05-20187.63 KM7.63 KM19.6175.02
7.Cause Way2.00 No4.6201-03-201625-06-20172.00 No2.00 No1.214.62
8.Culverts/Scupper 20.00 No33.6601-08-201510-03-201720.00 No20.00 No8.833.66
9.longitudinal Drain4970.00 m7.0601-03-201631-05-20174970.00 m4970.00 m1.857.06
10.Crash Barrier100.00 m2.2501-09-201831-01-2019100.00 m100.00 m0.592.25
11.Parapet72.00 No1.4601-02-201731-01-201972.00 No72.00 No0.381.46
12.Road Furniture107.00 No1.8901-03-201731-01-2019107.00 No107.00 No0.51.89
13.Other Allied Works & Finishing Work 1.00 Job20.8201-07-201531-01-20191.00 Job1.00 Job5.4420.82
Total Amount: 382.49 100   382.49
Remarks: No Remarks       Work Program Made On: 07-10-2015        Updation of work program on: 08-04-2019       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-September-201573.47  lakh
2.31-December-201535.31  lakh
3.31-January-201623.57  lakh
4.04-May-201621.94  lakh
5.05-May-20169.78  lakh
6.21-June-201624.98  lakh
7.31-December-201614.96  lakh
8.27-March-201717.22  lakh
9.30-June-201743.42  lakh
10.29-May-201840.01  lakh
11.14-August-201843.18  lakh
12.28-February-201938.79  lakh
13.09-July-20193.97  lakh
Total 390.6  lakh
% Payment102.12 %
Advance Amount:  79.88  lakh        Recovered Amount:  79.88  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 420   No. of Test Done : 441    No. of Test Passed : 422   No. of Test Failed : 19   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 86.63
Number of Notice(s) issued: 3

Mobile Pic Upload

Number of Pics Available on Web Repository: 62
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.18-08-2018Ch. 6/7SRMD Slip and road is closeAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
2.18-08-2018Ch 4/10SRMD slipAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
3.18-08-2018Ch 4/10SRMD R/Wall damageAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
4.18-08-2018Ch 2/28SRMD R/Wall damageAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
5.08-05-2018Site labBitumin extraction testAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
6.04-05-2018Ch 1/6P.C work is in progressAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
7.04-05-2018Ch 1/5Prime coated surfaceAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
8.04-05-2018Ch 1/12Compacted PC surafceAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
9.23-04-2018Ch 0/35Laying of PCAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
10.23-04-2018Ch 0/35Checking tempeature of PC before layingAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
11.23-04-2018Ch 0/38Prime coated surfaceAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
12.15-12-2017Km 4Visit by S.E (PIU) sirAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
13.15-12-2017Km 8S.E sir (PIU) visitAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
14.14-11-2017Ch 7+600Chief Sir annoying because of slow and poor quality of workAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
15.14-11-2017Ch 0/0Chief and S.E Sir visitAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
16.09-11-2017Ch 0/8Comment of S.E sir on site order book page 1Ankur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
17.09-11-2017Ch 0/8Comment by S.E sir on site order book final page 3Ankur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
18.09-11-2017Ch 0/8Comment of S.E sir on site order book page 2Ankur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
19.08-11-2017Ch 2/29R/wall rejected because no slop and RR (1:5) for band is just pested from outsideAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
20.06-11-2017Ch 7/12Parapet checked by S.E Sir found stone boulder and rejectedAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic