Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Nathukhal Pokhrikhet MR Work Completed
Project: UDRP-RB UID: 2275 Sanction Cost: 282.13  lakh Length: 7.000 KM.
District: Pauri Block: Dogadda Constituency: Yamkeshwar Circle:
DEA: DEA Pauri DSC: Egis International DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 80        Package Name:  UDRP/PWD/06/71/RD/069        Tender Date: 28-01-2015        Current Status: Agreement signed        Achieved on Date: 16-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/06/71/RD/069      Contractor Name: Balwinder Singh and Co.
Start Date:  22-06-2015      Intended Completion Date:  31-10-2018      Original End Date:  21-09-2016
Total Bond Cost: 64590492.74 (645.9 lakh)        Variation Cost: -3468998.15 (-34.69 lakh)    Hence Total Bond Cost is   61121494.59 (611.21 lakh) 
Sub Project Cost: 174.11  lakh        Variation Cost of Sub Project: 5462170.93  (54.62 lakh)       Total Sub Project Cost:   228.73 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 10366695 for 321 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence2.66 KM20.3101-10-201728-10-20172.66 KM2.66 KM9.120.31
2.R/Wall, B/ Wall Type Protection works691.00 m77.6601-07-201528-10-2017691.00 m691.00 m34.7977.66
3.GSB/RBI/G-10.30 KM0.6601-11-201622-05-20170.30 KM0.30 KM0.30.66
4.G-20.30 KM1.2715-11-201625-05-20170.30 KM0.30 KM0.571.27
5.G-33.20 KM5.6801-03-201728-05-20173.20 KM3.20 KM2.555.68
6.PC/CC i/c Prime Coat, Tack Coat7.00 KM62.7601-04-201729-06-20187.00 KM7.00 KM28.1162.76
7.Cause Way0.00 No0.0001-01-201828-02-20180.00 No0.00 No00.00
8.Culverts/Scupper 20.00 No35.6201-08-201531-03-201720.00 No20.00 No15.9535.62
9.longitudinal Drain6080.00 m5.5301-08-201531-05-20176080.00 m6080.00 m2.485.53
10.Crash Barrier108.00 m2.3815-08-201831-01-2019108.00 m108.00 m1.062.38
11.Parapet71.00 No1.5410-08-201831-01-201971.00 No71.00 No0.691.54
12.Road Furniture103.00 No2.1801-06-201631-10-2018103.00 No103.00 No0.982.18
13.Other Allied Works & Finishing Work 1.00 Job7.6701-07-201531-01-20191.00 Job1.00 Job3.447.67
Total Amount: 223.26 100   223.26
Remarks: No Remarks       Work Program Made On: 05-10-2015        Updation of work program on: 29-03-2019       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-September-201530.42  lakh
2.31-December-201519.02  lakh
3.05-May-201634.95  lakh
4.21-June-20162.91  lakh
5.31-December-20165.35  lakh
6.27-March-201715.92  lakh
7.30-June-201712.78  lakh
8.29-May-201811.95  lakh
9.14-August-201852.31  lakh
10.28-February-201933.54  lakh
11.30-April-20197.90  lakh
12.18-June-20190.17  lakh
13.09-July-20195.48  lakh
Total 232.7  lakh
% Payment101.74 %
Advance Amount:  79.88  lakh        Recovered Amount:  79.88  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 420   No. of Test Done : 441    No. of Test Passed : 422   No. of Test Failed : 19   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
Number of Notice(s) issued: 1

Mobile Pic Upload

Number of Pics Available on Web Repository: 16
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.18-08-2018Ch 7+290SRMD R/wall damageAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
2.18-08-2018Ch 10/27SRMD R/wall damageAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
3.18-08-2018Ch 10/34SRMD SlipAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
4.18-08-2018Ch 13/4SRMD SlipAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
5.19-05-201811+150Rolling of PC in progressManoj BhattREDSC2 R&B WB Pauri See Pic
6.08-05-2018Ch. 8/25Laying and compaction of PCAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
7.08-05-2018Ch. 8/25Checking tempeature of PC during layingAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
8.15-12-2017Km 14S.E sir (PIU) visitAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
9.14-11-2017Ch km 14Chief Sir visit- No labour/machineries found at site, work was stopped at this site from last two yearsAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
10.06-11-2017Ch KM 14S.E Visit at nathukhal-pokharikhet motor roadAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
11.10-05-20177+675Pc work is in progress and compection of pcAnkit RanaSite SupervisorDSC2 R&B WB Pauri See Pic
12.09-05-20177.670Laying of type-C seal coat compacted by static Rolar.Vikas BadoniSite SupervisorDSC2 R&B WB Tehri See Pic
13.09-05-20177.675Laying of PC compacted by static Rolar.Vikas BadoniSite SupervisorDSC2 R&B WB Tehri See Pic
14.05-01-2016Km 10ScupperPran Veer SinghAAEUDRP R&B Pauri See Pic
15.05-01-2016Km 11Scupper, r wallPran Veer SinghAAEUDRP R&B Pauri See Pic
16.05-01-2016Km 12R wallPran Veer SinghAAEUDRP R&B Pauri See Pic