Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

RamkundGhat to GIC Devprayag Link MR Work Completed
Project: UDRP-RB UID: 2274 Sanction Cost: 87.49  lakh Length: 0.600 KM.
District: Pauri Block: Kot Constituency: Pauri Circle:
DEA: DEA Pauri DSC: Egis International DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 77        Package Name:  UDRP/PWD/06/69/RD/066a        Tender Date: 28-01-2015        Current Status: Agreement signed        Achieved on Date: 31-07-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/06/69/RD/066a      Contractor Name: Bharat Singh Rawat
Start Date:  07-08-2015      Intended Completion Date:  31-01-2017      Original End Date:  06-11-2016
Total Bond Cost: 7790651.52 (77.91 lakh)        Variation Cost: -532531.61 (-5.33 lakh)    Hence Total Bond Cost is   7258119.91 (72.58 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 225910 for 58 days        LD Analysis for Milestone2: calculated LD is Rs 233700 for 60 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.38 KM1.3307-08-201507-10-20150.38 KM0.38 KM1.841.33
2.R/Wall, B/ Wall Type Protection works448.00 m45.2310-08-201515-08-2016448.00 m448.00 m62.4845.23
3.GSB/RBI/G-10.65 KM0.7820-06-201625-09-20160.65 KM0.65 KM1.080.78
4.G-20.68 KM0.7130-06-201630-09-20160.68 KM0.68 KM0.980.71
5.G-30.68 KM1.0220-07-201625-11-20160.68 KM0.68 KM1.411.02
6.BM i/c Prime Coat, Tack Coat0.68 KM6.8825-11-201615-12-20160.68 KM0.68 KM9.56.88
7.Culverts/Scupper 1.00 No3.1002-02-201620-05-20161.00 No1.00 No4.283.10
8.longitudinal Drain675.00 m7.5403-03-201631-01-2017675.00 m675.00 m10.427.54
9.Crash Barrier0.00 m0.0008-08-201630-11-20160.00 m0.00 m00.00
10.Parapet80.00 No2.2911-08-201615-01-201780.00 No80.00 No3.162.29
11.Road Furniture6.00 No0.3501-12-201631-01-20176.00 No6.00 No0.480.35
12.Other Allied Works & Finishing Work 1.00 Job3.1620-07-201631-01-20171.00 Job1.00 Job4.373.16
Total Amount: 72.39 100   72.39
Remarks: No Remarks       Work Program Made On: 10-05-2016        Updation of work program on: 26-09-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.27-February-201612.44  lakh
2.14-March-20167.76  lakh
3.08-April-20165.15  lakh
4.13-May-20162.28  lakh
5.14-July-20167.41  lakh
6.30-September-201613.02  lakh
7.25-January-201716.27  lakh
8.30-June-20178.07  lakh
Total 72.4  lakh
% Payment 99.76 %
Advance Amount:  17.68  lakh        Recovered Amount:  17.68  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 43   No. of Test Done : 47    No. of Test Passed : 43   No. of Test Failed : 4   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.97
Number of Notice(s) issued: 97

Mobile Pic Upload

Number of Pics Available on Web Repository: 19
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.28-11-20170+250Discussion... During Site visit by world bank team....Noshad QureshiSite SupervisorDSC2 R&B WB Pauri See Pic
2.28-11-20170+200Discussion... during Site visit by world bank team....Noshad QureshiSite SupervisorDSC2 R&B WB Pauri See Pic
3.24-12-20160+000 to 0+050Providing concreat M15 in KC drainAmit KumarJEUDRP R&B Pauri See Pic
4.20-11-20160+080Progress of HP Filling in R/WAmit KumarJEUDRP R&B Pauri See Pic
5.28-09-20160/7Construction of R/WDeepak GoelREDSC2 R&B WB Pauri See Pic
6.21-09-20160+445 to 0+475Providing M10 concreat for KC drain.Amit KumarJEUDRP R&B Pauri See Pic
7.21-09-20160+440Progress of excavation & slope stablation & compacting for KC drain.Amit KumarJEUDRP R&B Pauri See Pic
8.20-09-20160/7construction of R/W with 9 layer of plum wallNoshad QureshiSite SupervisorDSC2 R&B WB Pauri See Pic
9.20-09-20160/20construction of kc drain in progressNoshad QureshiSite SupervisorDSC2 R&B WB Pauri See Pic
10.10-09-20160+065 to 0+120Progress of R/WAmit KumarJEUDRP R&B Pauri See Pic
11.24-05-20160+110Progress of wire cratesAmit KumarJEUDRP R&B Pauri See Pic
12.16-03-20160+080Progress of plum in B/WAmit KumarJEUDRP R&B Pauri See Pic
13.07-03-20160+070Progress off Plum in R/WAmit KumarJEUDRP R&B Pauri See Pic
14.04-03-20160+065Progress of Plum in B/WAmit KumarJEUDRP R&B Pauri See Pic
15.01-03-20160+178Progress of scuperAmit KumarJEUDRP R&B Pauri See Pic
16.29-02-20160/3Construction of plum concreteNoshad QureshiSite SupervisorDSC2 R&B WB Pauri See Pic
17.02-02-20160+350Collie wallAmit KumarJEUDRP R&B Pauri See Pic
18.12-01-20160+415Breast wallNoshad QureshiSite SupervisorDSC2 R&B WB Pauri See Pic
19.09-01-20160+410Hill cuttingAmit KumarJEUDRP R&B Pauri See Pic