Birsanikhal-Kota-Silsu-bhutnisi MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
2272 |
Sanction Cost: |
151.24 lakh |
Length:
|
3.500 KM. |
District: |
Pauri |
Block: |
Kot |
Constituency: |
Pauri |
Circle: |
Tehri WB Circle |
DEA: |
DEA Pauri |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 131
Package Name: 
UDRP/PWD/06/67/RD/049(N)
Tender Date: 15-12-2016
Current Status: Agreement signed
Achieved on Date: 03-08-2017 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/06/67/RD/049(N)
Contractor Name: Bharat Construction
|
Start Date: 10-08-2017
Intended Completion Date: 31-12-2018
|
Total Bond Cost: 32395168.87 (323.95 lakh)
Variation Cost: 1995359.61 (19.95 lakh) Hence Total Bond Cost is 34390528.48 (343.91 lakh)
|
Sub Project Cost: 96.00 lakh
Variation Cost of Sub Project: -4762179.74 (-47.62 lakh)
Total Sub Project Cost:
48.38 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.50 KM | 4.20 | 25-10-2017 | 20-12-2018 | 0.50 KM | 0.50 KM | 8.76 | 4.20 | 2. | R/Wall, B/ Wall Type Protection works | 280.00 m | 33.47 | 26-10-2017 | 31-12-2018 | 280.00 m | 280.00 m | 69.87 | 33.47 | 3. | GSB/RBI/G-1 | 0.00 KM | 0.00 | 26-12-2017 | 05-02-2018 | 0.00 KM | 0.00 KM | 0 | 0.00 | 4. | G-2 | 0.00 KM | 0.00 | 06-02-2018 | 10-03-2018 | 0.00 KM | 0.00 KM | 0 | 0.00 | 5. | G-3 | 0.00 KM | 0.00 | 11-03-2018 | 05-04-2018 | 0.00 KM | 0.00 KM | 0 | 0.00 | 6. | PC/CC i/c Prime Coat, Tack Coat | 0.00 KM | 0.00 | 05-04-2018 | 06-05-2018 | 0.00 KM | 0.00 KM | 0 | 0.00 | 7. | Culverts/Scupper | 2.00 No | 3.62 | 28-10-2017 | 31-03-2018 | 2.00 No | 2.00 No | 7.56 | 3.62 | 8. | longitudinal Drain | 3300.00 m | 2.36 | 02-03-2018 | 25-01-2019 | 3300.00 m | 3300.00 m | 4.92 | 2.36 | 9. | Road Furniture | 20.00 No | 0.39 | 05-03-2018 | 20-01-2019 | 2.00 No | 2.00 No | 0.82 | 0.39 | 10. | Other Allied Works & Finishing Work | 1.00 Job | 3.87 | 10-03-2018 | 31-01-2019 | 1.00 Job | 1.00 Job | 8.08 | 3.87 |
Total Amount: |
47.91 |
|
100 |
47.91 |
|
Remarks:
No Remarks
Work Program Made On:
22-11-2017 } ?>
Updation of work program on:
08-04-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-May-2015 | 15.09 lakh | 2. | 30-September-2015 | 30.34 lakh |
Previous Package Expenditure Total |
45.43 lakh |
SNo. |
Date |
Payment |
1. | 30-December-2017 | 12.87 lakh | 2. | 28-February-2018 | 14.08 lakh | 3. | 09-May-2018 | 8.64 lakh | 4. | 30-June-2018 | 0.22 lakh | 5. | 29-September-2018 | 1.23 lakh | 6. | 23-April-2019 | 5.66 lakh | 7. | 10-June-2019 | 5.69 lakh | 8. | 09-July-2019 | 2.69 lakh |
Total |
51.08 lakh |
% Payment | 105.58 % |
|
Advance Amount: 30.94 lakh
Recovered Amount: 30.94 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 203 No. of Test Done : 211 No. of Test Passed : 203 No. of Test Failed : 8 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 87.09 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 11 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 24-08-2018 | Ch. 3+500 | Chief sir visit | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
2. | 19-01-2018 | Ch 0/0 | B/wall | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
3. | 19-01-2018 | Ch 0+800 | B/wall is in progress | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
4. | 19-01-2018 | Ch 1/31 | Slip clearance at bend is progress | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
5. | 16-09-2015 | R/W .Wotk on progress | R/W Work on progress | S.s.mewar | JE | DEA WB Pauri | See Pic |
6. | 16-09-2015 | Ch.0.350 | Scupper work on progress | S.s.mewar | JE | DEA WB Pauri | See Pic |
7. | 16-09-2015 | ch.1.200 | Scupp.steel.Binding | S.s.mewar | JE | DEA WB Pauri | See Pic |
8. | 04-06-2015 | Chh.0 450 | G-3 (Rejected ) | S.s.mewar | JE | DEA WB Pauri | See Pic |
9. | 31-03-2015 | birsanikhal-kota-silsu CH:3+000 | c/o of G-1 | Vijay Tiwari | Site Supervisor | UDRP R&B DSC2 Pauri | See Pic |
10. | 31-03-2015 | birsanikhal-kota-silsu CH:0+600 | c/o of scupper | Vijay Tiwari | Site Supervisor | UDRP R&B DSC2 Pauri | See Pic |
11. | 28-03-2015 | 02+200 | G-1 | Umesh Mishra | Site superviser | DEA WB Pauri | See Pic |
|
|