Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Badiyu-jhakhanoli kunkuli MR Work Completed
Project: UDRP-RB UID: 2271 Sanction Cost: 416.29  lakh Length: 10.000 KM.
District: Pauri Block: Kaljikhal Constituency: Pauri Circle: Tehri WB Circle
DEA: DEA Pauri DSC: Egis International DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 132        Package Name:  UDRP/PWD/06/67/RD/050(N)        Tender Date: 15-12-2016        Current Status: Agreement signed        Achieved on Date: 04-05-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/06/67/RD/050(N)      Contractor Name: SRS Promoters
Start Date:  11-05-2017      Intended Completion Date:  31-12-2018      Original End Date:  10-02-2018
Total Bond Cost: 28432575.93 (284.33 lakh)        Variation Cost: -1882561.99 (-18.83 lakh)    Hence Total Bond Cost is   26550013.94 (265.5 lakh) 
Sub Project Cost: 201.59  lakh        Variation Cost of Sub Project: 443851.09  (4.44 lakh)       Total Sub Project Cost:   206.03 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.47 KM5.9815-05-201730-11-20182.50 KM2.50 KM3.055.98
2.R/Wall, B/ Wall Type Protection works450.00 m36.7115-05-201730-08-2018420.00 m420.00 m18.7336.71
3.GSB/RBI/G-10.00 KM0.0015-07-201715-07-20170.00 KM0.00 KM00.00
4.G-21.00 KM8.2420-08-201715-09-20180.50 KM0.50 KM4.218.24
5.G-33.80 KM30.0925-08-201715-09-20183.50 KM3.50 KM15.3530.09
6.PC/CC i/c Prime Coat, Tack Coat9.50 KM87.4901-03-201830-11-20189.50 KM9.50 KM44.6487.49
7.Culverts/Scupper 2.00 No5.7510-07-201730-08-20182.00 No2.00 No2.935.75
8.longitudinal Drain9500.00 m8.5520-05-201715-09-20189500.00 m9500.00 m4.368.55
9.Road Furniture75.00 No1.2915-04-201815-10-201820.00 No20.00 No0.661.29
10.Other Allied Works & Finishing Work 1.00 Job11.8915-04-201830-10-20181.00 Job1.00 Job6.0711.89
Total Amount: 195.99 100   195.99
Remarks: No Remarks       Work Program Made On: 18-11-2017        Updation of work program on: 16-10-2019       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-October-201417.99  lakh
2.31-January-201524.77  lakh
3.27-February-201527.71  lakh
4.31-March-201522.88  lakh
5.26-May-201517.04  lakh
6.27-May-20152.45  lakh
7.30-June-201517.59  lakh
8.23-October-20151.00  lakh
9.29-February-20168.75  lakh
Previous Package Expenditure Total 140.18  lakh
SNo. Date Payment
1.17-August-20178.03  lakh
2.30-November-201727.73  lakh
3.30-December-201711.17  lakh
4.28-April-201825.89  lakh
5.30-May-201821.26  lakh
6.30-June-201817.16  lakh
7.22-October-20187.39  lakh
8.15-December-20181.27  lakh
9.31-May-201930.70  lakh
10.18-June-201913.73  lakh
11.29-June-201919.06  lakh
12.08-July-201915.45  lakh
13.09-July-20198.60  lakh
Total 207.44  lakh
% Payment100.68 %
Advance Amount:  67.52  lakh        Recovered Amount:  67.52  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 222   No. of Test Done : 230    No. of Test Passed : 222   No. of Test Failed : 8   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 88.42
Number of Notice(s) issued: 2

Mobile Pic Upload

Number of Pics Available on Web Repository: 35
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.17-05-2019Ch.2+950Laying of seal coatAmit KumarJEUDRP R&B Guptkashi See Pic
2.11-05-2019Ch.3+950Rolling over seal coatAmit KumarJEUDRP R&B Guptkashi See Pic
3.09-04-20191+500Slip clearanceAmit KumarJEUDRP R&B Guptkashi See Pic
4.09-10-2018Km 4 ch.3+600Laying of PCAmit KumarJEUDRP R&B Pauri See Pic
5.25-09-2018Km 9 Ch.8+925SRMD Road Block Due to Debris Falled km 9Amit KumarJEUDRP R&B Pauri See Pic
6.28-08-2018Km 3 ch.2+575SRMD Road Block Due to Debris Falled km 3Amit KumarJEUDRP R&B Pauri See Pic
7.28-08-2018Km 3 ch.2+550SRMD R /Wall DamageAmit KumarJEUDRP R&B Pauri See Pic
8.28-08-2018Km 3 ch.2+475SRMD R/Wall DamageAmit KumarJEUDRP R&B Pauri See Pic
9.28-08-2018Km 2 ch.1+975SRMD Road Block Due to Debris Falled km 2Amit KumarJEUDRP R&B Pauri See Pic
10.20-08-2018Km 5 ch.4+200SRMD Site clearance at km 5Amit KumarJEUDRP R&B Pauri See Pic
11.20-08-2018Km 5 ch.4+200SRMD R /Wall DamageAmit KumarJEUDRP R&B Pauri See Pic
12.19-03-2018Ch 8/30Thickness checking of WBM G3Ankur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
13.15-09-2015X-S -3/16Slip clearance in progressS.s.mewarJEDEA WB Pauri See Pic
14.15-09-2015Ch.2.500Slip clearance workS.s.mewarJEDEA WB Pauri See Pic
15.21-07-2015Badyou-jhakhnoli-kunkuli ch2+450C/O of slip clearanceVijay TiwariSite SupervisorUDRP R&B DSC2 Pauri See Pic
16.21-07-2015Badyou-khakhnoli-kunkuli ch:2+450C/O of slip clearanceVijay TiwariSite SupervisorUDRP R&B DSC2 Pauri See Pic
17.04-06-2015Chh.2.500G-3 (ovet size)S.s.mewarJEDEA WB Pauri See Pic
18.04-06-2015Chh.2.300G-3 (over size Rejected)S.s.mewarJEDEA WB Pauri See Pic
19.04-06-2015Chh.0.575G-3S.s.mewarJEDEA WB Pauri See Pic
20.25-05-2015Jhakhanoli ch:0+975Aiv testingVijay TiwariSite SupervisorUDRP R&B DSC2 Pauri See Pic