Badiyu-jhakhanoli kunkuli MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
2271 |
Sanction Cost: |
416.29 lakh |
Length:
|
10.000 KM. |
District: |
Pauri |
Block: |
Kaljikhal |
Constituency: |
Pauri |
Circle: |
Tehri WB Circle |
DEA: |
DEA Pauri |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 132
Package Name: 
UDRP/PWD/06/67/RD/050(N)
Tender Date: 15-12-2016
Current Status: Agreement signed
Achieved on Date: 04-05-2017 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/06/67/RD/050(N)
Contractor Name: SRS Promoters
|
Start Date: 11-05-2017
Intended Completion Date: 31-12-2018
Original End Date: 10-02-2018 |
Total Bond Cost: 28432575.93 (284.33 lakh)
Variation Cost: -1882561.99 (-18.83 lakh) Hence Total Bond Cost is 26550013.94 (265.5 lakh)
|
Sub Project Cost: 201.59 lakh
Variation Cost of Sub Project: 443851.09 (4.44 lakh)
Total Sub Project Cost:
206.03 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.47 KM | 5.98 | 15-05-2017 | 30-11-2018 | 2.50 KM | 2.50 KM | 3.05 | 5.98 | 2. | R/Wall, B/ Wall Type Protection works | 450.00 m | 36.71 | 15-05-2017 | 30-08-2018 | 420.00 m | 420.00 m | 18.73 | 36.71 | 3. | GSB/RBI/G-1 | 0.00 KM | 0.00 | 15-07-2017 | 15-07-2017 | 0.00 KM | 0.00 KM | 0 | 0.00 | 4. | G-2 | 1.00 KM | 8.24 | 20-08-2017 | 15-09-2018 | 0.50 KM | 0.50 KM | 4.21 | 8.24 | 5. | G-3 | 3.80 KM | 30.09 | 25-08-2017 | 15-09-2018 | 3.50 KM | 3.50 KM | 15.35 | 30.09 | 6. | PC/CC i/c Prime Coat, Tack Coat | 9.50 KM | 87.49 | 01-03-2018 | 30-11-2018 | 9.50 KM | 9.50 KM | 44.64 | 87.49 | 7. | Culverts/Scupper | 2.00 No | 5.75 | 10-07-2017 | 30-08-2018 | 2.00 No | 2.00 No | 2.93 | 5.75 | 8. | longitudinal Drain | 9500.00 m | 8.55 | 20-05-2017 | 15-09-2018 | 9500.00 m | 9500.00 m | 4.36 | 8.55 | 9. | Road Furniture | 75.00 No | 1.29 | 15-04-2018 | 15-10-2018 | 20.00 No | 20.00 No | 0.66 | 1.29 | 10. | Other Allied Works & Finishing Work | 1.00 Job | 11.89 | 15-04-2018 | 30-10-2018 | 1.00 Job | 1.00 Job | 6.07 | 11.89 |
Total Amount: |
195.99 |
|
100 |
195.99 |
|
Remarks:
No Remarks
Work Program Made On:
18-11-2017 } ?>
Updation of work program on:
16-10-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-October-2014 | 17.99 lakh | 2. | 31-January-2015 | 24.77 lakh | 3. | 27-February-2015 | 27.71 lakh | 4. | 31-March-2015 | 22.88 lakh | 5. | 26-May-2015 | 17.04 lakh | 6. | 27-May-2015 | 2.45 lakh | 7. | 30-June-2015 | 17.59 lakh | 8. | 23-October-2015 | 1.00 lakh | 9. | 29-February-2016 | 8.75 lakh |
Previous Package Expenditure Total |
140.18 lakh |
SNo. |
Date |
Payment |
1. | 17-August-2017 | 8.03 lakh | 2. | 30-November-2017 | 27.73 lakh | 3. | 30-December-2017 | 11.17 lakh | 4. | 28-April-2018 | 25.89 lakh | 5. | 30-May-2018 | 21.26 lakh | 6. | 30-June-2018 | 17.16 lakh | 7. | 22-October-2018 | 7.39 lakh | 8. | 15-December-2018 | 1.27 lakh | 9. | 31-May-2019 | 30.70 lakh | 10. | 18-June-2019 | 13.73 lakh | 11. | 29-June-2019 | 19.06 lakh | 12. | 08-July-2019 | 15.45 lakh | 13. | 09-July-2019 | 8.60 lakh |
Total |
207.44 lakh |
% Payment | 100.68 % |
|
Advance Amount: 67.52 lakh
Recovered Amount: 67.52 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 222 No. of Test Done : 230 No. of Test Passed : 222 No. of Test Failed : 8 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 88.42 |
Number of Notice(s) issued: 2 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 35 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 17-05-2019 | Ch.2+950 | Laying of seal coat | Amit Kumar | JE | UDRP R&B Guptkashi | See Pic |
2. | 11-05-2019 | Ch.3+950 | Rolling over seal coat | Amit Kumar | JE | UDRP R&B Guptkashi | See Pic |
3. | 09-04-2019 | 1+500 | Slip clearance | Amit Kumar | JE | UDRP R&B Guptkashi | See Pic |
4. | 09-10-2018 | Km 4 ch.3+600 | Laying of PC | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
5. | 25-09-2018 | Km 9 Ch.8+925 | SRMD Road Block Due to Debris Falled km 9 | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
6. | 28-08-2018 | Km 3 ch.2+575 | SRMD Road Block Due to Debris Falled km 3 | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
7. | 28-08-2018 | Km 3 ch.2+550 | SRMD R /Wall Damage | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
8. | 28-08-2018 | Km 3 ch.2+475 | SRMD R/Wall Damage | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
9. | 28-08-2018 | Km 2 ch.1+975 | SRMD Road Block Due to Debris Falled km 2 | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
10. | 20-08-2018 | Km 5 ch.4+200 | SRMD Site clearance at km 5 | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
11. | 20-08-2018 | Km 5 ch.4+200 | SRMD R /Wall Damage | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
12. | 19-03-2018 | Ch 8/30 | Thickness checking of WBM G3 | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
13. | 15-09-2015 | X-S -3/16 | Slip clearance in progress | S.s.mewar | JE | DEA WB Pauri | See Pic |
14. | 15-09-2015 | Ch.2.500 | Slip clearance work | S.s.mewar | JE | DEA WB Pauri | See Pic |
15. | 21-07-2015 | Badyou-jhakhnoli-kunkuli ch2+450 | C/O of slip clearance | Vijay Tiwari | Site Supervisor | UDRP R&B DSC2 Pauri | See Pic |
16. | 21-07-2015 | Badyou-khakhnoli-kunkuli ch:2+450 | C/O of slip clearance | Vijay Tiwari | Site Supervisor | UDRP R&B DSC2 Pauri | See Pic |
17. | 04-06-2015 | Chh.2.500 | G-3 (ovet size) | S.s.mewar | JE | DEA WB Pauri | See Pic |
18. | 04-06-2015 | Chh.2.300 | G-3 (over size Rejected) | S.s.mewar | JE | DEA WB Pauri | See Pic |
19. | 04-06-2015 | Chh.0.575 | G-3 | S.s.mewar | JE | DEA WB Pauri | See Pic |
20. | 25-05-2015 | Jhakhanoli ch:0+975 | Aiv testing | Vijay Tiwari | Site Supervisor | UDRP R&B DSC2 Pauri | See Pic |
|
|