Rikhanikhal- chanikhal Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
2243 |
Sanction Cost: |
139.39 lakh |
Length:
|
9.600 KM. |
District: |
Pauri |
Block: |
Rikhnikhal |
Constituency: |
Lansdowne |
Circle: |
Tehri WB Circle |
DEA: |
DEA Pauri |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 130
Package Name: 
UDRP/PWD/06/70/RD/015(N)
Tender Date: 15-12-2016
Current Status: Agreement signed
Achieved on Date: 04-05-2017 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/06/70/RD/015(N)
Contractor Name: R K Gupta Contractor
|
Start Date: 11-05-2017
Intended Completion Date: 15-06-2019
Original End Date: 10-08-2018 |
Total Bond Cost: 71282113.06 (712.82 lakh)
Variation Cost: -3164496.59 (-31.64 lakh) Hence Total Bond Cost is 68117616.47 (681.18 lakh)
|
Sub Project Cost: 132.43 lakh
Variation Cost of Sub Project: -2124217.35 (-21.24 lakh)
Total Sub Project Cost:
111.19 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 14078195 for 395 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.62 KM | 0.71 | 15-06-2017 | 15-09-2018 | 0.62 KM | 0.62 KM | 0.59 | 0.71 | 2. | R/Wall, B/ Wall Type Protection works | 103.00 m | 21.75 | 10-08-2017 | 25-09-2018 | 103.00 m | 103.00 m | 18.1 | 21.75 | 3. | G-2 | 0.90 KM | 6.83 | 10-01-2018 | 15-09-2018 | 0.90 KM | 0.90 KM | 5.68 | 6.83 | 4. | G-3 | 2.40 KM | 16.96 | 10-02-2018 | 25-09-2018 | 2.40 KM | 2.40 KM | 14.11 | 16.96 | 5. | PC/CC i/c Prime Coat, Tack Coat | 4.60 KM | 41.81 | 01-04-2018 | 31-03-2019 | 4.60 KM | 4.60 KM | 34.79 | 41.81 | 6. | Culverts/Scupper | 3.00 No | 6.02 | 15-08-2017 | 30-09-2018 | 3.00 No | 3.00 No | 5.01 | 6.02 | 7. | longitudinal Drain | 9.60 m | 3.09 | 15-08-2017 | 15-09-2018 | 9600.00 m | 9600.00 m | 2.57 | 3.09 | 8. | Crash Barrier | 150.00 m | 4.20 | 15-12-2018 | 05-03-2019 | 150.00 m | 150.00 m | 3.49 | 4.20 | 9. | Parapet | 230.00 No | 6.40 | 30-09-2017 | 15-03-2019 | 230.00 No | 230.00 No | 5.32 | 6.40 | 10. | Road Furniture | 53.00 No | 7.84 | 15-10-2018 | 30-03-2019 | 53.00 No | 53.00 No | 6.52 | 7.84 | 11. | Other Allied Works & Finishing Work | 1.00 Job | 4.59 | 15-06-2017 | 31-03-2019 | 1.00 Job | 1.00 Job | 3.82 | 4.59 |
Total Amount: |
120.2 |
|
100 |
120.2 |
|
Remarks:
No Remarks
Work Program Made On:
18-11-2017 } ?>
Updation of work program on:
08-04-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
Previous Package Expenditure Total |
0 lakh |
SNo. |
Date |
Payment |
1. | 13-April-2018 | 1.26 lakh | 2. | 30-May-2018 | 28.61 lakh | 3. | 30-June-2018 | 16.60 lakh | 4. | 14-August-2018 | 0.81 lakh | 5. | 22-October-2018 | 14.65 lakh | 6. | 15-December-2018 | 4.33 lakh | 7. | 30-January-2019 | 1.81 lakh | 8. | 28-February-2019 | 0.63 lakh | 9. | 30-March-2019 | 15.56 lakh | 10. | 30-April-2019 | 16.32 lakh | 11. | 31-May-2019 | 1.09 lakh | 12. | 18-June-2019 | 7.52 lakh | 13. | 29-June-2019 | 1.64 lakh | 14. | 09-July-2019 | 5.73 lakh |
Total |
116.56 lakh |
% Payment | 104.83 % |
|
Advance Amount: 14.32 lakh
Recovered Amount: 14.32 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 399 No. of Test Done : 414 No. of Test Passed : 399 No. of Test Failed : 15 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 85.84 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 20 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 16-08-2018 | 8+150 | Parapet construction in progress. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
2. | 25-05-2018 | 7/22 | PC laying in progress. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
3. | 17-05-2018 | 8+800 | PC laying in progress. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
4. | 09-05-2018 | 9+600 | PC laying Started today. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
5. | 08-05-2018 | 9+550 | WBM G3 laying in progress. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
6. | 11-03-2018 | 0+175 | Chainage Marking. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
7. | 23-02-2018 | 6+900 | Excavation for katcha drain. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
8. | 19-02-2018 | Ch. 6+000 | Noise Pollution Testing | Sagar Kumar | JE | UDRP R&B Pauri | See Pic |
9. | 19-02-2018 | 7+880 | Air Quality Testing. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
10. | 07-09-2015 | Ch2.700 | Stone collection for R/wall | Pramod Gauniyal | JE | DEA WB Pauri | See Pic |
11. | 07-09-2015 | Ch9.200 | End point of the road | Pramod Gauniyal | JE | DEA WB Pauri | See Pic |
12. | 07-09-2015 | Ch2.700 | R/wall RR Dry (rejected wall due to less base ) | Pramod Gauniyal | JE | DEA WB Pauri | See Pic |
13. | 07-09-2015 | Ch1.900 | Damaged surface of road | Pramod Gauniyal | JE | DEA WB Pauri | See Pic |
14. | 07-09-2015 | Ch1.900 | Damaged surface of road | Pramod Gauniyal | JE | DEA WB Pauri | See Pic |
15. | 07-09-2015 | 2.700 | Damaged surface of the road | Pramod Gauniyal | JE | DEA WB Pauri | See Pic |
16. | 07-09-2015 | Ch2.200 | Damaged bitumin surface of the road | Pramod Gauniyal | JE | DEA WB Pauri | See Pic |
17. | 07-09-2015 | Ch7.800 | Damaged surface of the road | Pramod Gauniyal | JE | DEA WB Pauri | See Pic |
18. | 07-09-2015 | Ch2.700 | Damaged surface | Pramod Gauniyal | JE | DEA WB Pauri | See Pic |
19. | 07-09-2015 | Ch1.400-1.500 | R/wall RR Dry rejected (base less then standard, invited stone, slope not correct) | Pramod Gauniyal | JE | DEA WB Pauri | See Pic |
20. | 09-07-2015 | Ch9.600 | End point of the road | Pramod Gauniyal | JE | DEA WB Pauri | See Pic |
|
|