Rikhanikhal- chanikhal Motor Road Work Completed
Project: UDRP-RB UID: 2243 Sanction Cost: 139.39  lakh Length: 9.600 KM.
District: Pauri Block: Rikhnikhal Constituency: Lansdowne Circle: Tehri WB Circle
DEA: DEA Pauri DSC: Egis International DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 130        Package Name:  UDRP/PWD/06/70/RD/015(N)        Tender Date: 15-12-2016        Current Status: Agreement signed        Achieved on Date: 04-05-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/06/70/RD/015(N)      Contractor Name: R K Gupta Contractor
Start Date:  11-05-2017      Intended Completion Date:  15-06-2019      Original End Date:  10-08-2018
Total Bond Cost: 71282113.06 (712.82 lakh)        Variation Cost: -3164496.59 (-31.64 lakh)    Hence Total Bond Cost is   68117616.47 (681.18 lakh) 
Sub Project Cost: 132.43  lakh        Variation Cost of Sub Project: -2124217.35  (-21.24 lakh)       Total Sub Project Cost:   111.19 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 14078195 for 395 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.62 KM0.7115-06-201715-09-20180.62 KM0.62 KM0.590.71
2.R/Wall, B/ Wall Type Protection works103.00 m21.7510-08-201725-09-2018103.00 m103.00 m18.121.75
3.G-20.90 KM6.8310-01-201815-09-20180.90 KM0.90 KM5.686.83
4.G-32.40 KM16.9610-02-201825-09-20182.40 KM2.40 KM14.1116.96
5.PC/CC i/c Prime Coat, Tack Coat4.60 KM41.8101-04-201831-03-20194.60 KM4.60 KM34.7941.81
6.Culverts/Scupper 3.00 No6.0215-08-201730-09-20183.00 No3.00 No5.016.02
7.longitudinal Drain9.60 m3.0915-08-201715-09-20189600.00 m9600.00 m2.573.09
8.Crash Barrier150.00 m4.2015-12-201805-03-2019150.00 m150.00 m3.494.20
9.Parapet230.00 No6.4030-09-201715-03-2019230.00 No230.00 No5.326.40
10.Road Furniture53.00 No7.8415-10-201830-03-201953.00 No53.00 No6.527.84
11.Other Allied Works & Finishing Work 1.00 Job4.5915-06-201731-03-20191.00 Job1.00 Job3.824.59
Total Amount: 120.2 100   120.2
Remarks: No Remarks       Work Program Made On: 18-11-2017        Updation of work program on: 08-04-2019       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
Previous Package Expenditure Total 0  lakh
SNo. Date Payment
1.13-April-20181.26  lakh
2.30-May-201828.61  lakh
3.30-June-201816.60  lakh
4.14-August-20180.81  lakh
5.22-October-201814.65  lakh
6.15-December-20184.33  lakh
7.30-January-20191.81  lakh
8.28-February-20190.63  lakh
9.30-March-201915.56  lakh
10.30-April-201916.32  lakh
11.31-May-20191.09  lakh
12.18-June-20197.52  lakh
13.29-June-20191.64  lakh
14.09-July-20195.73  lakh
Total 116.56  lakh
% Payment104.83 %
Advance Amount:  14.32  lakh        Recovered Amount:  14.32  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 399   No. of Test Done : 414    No. of Test Passed : 399   No. of Test Failed : 15   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 85.84
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 20
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.16-08-20188+150Parapet construction in progress.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
2.25-05-20187/22PC laying in progress.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
3.17-05-20188+800PC laying in progress.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
4.09-05-20189+600PC laying Started today.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
5.08-05-20189+550WBM G3 laying in progress.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
6.11-03-20180+175Chainage Marking.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
7.23-02-20186+900Excavation for katcha drain.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
8.19-02-2018Ch. 6+000Noise Pollution TestingSagar KumarJEUDRP R&B Pauri See Pic
9.19-02-20187+880Air Quality Testing.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
10.07-09-2015Ch2.700Stone collection for R/wallPramod GauniyalJEDEA WB Pauri See Pic
11.07-09-2015Ch9.200End point of the roadPramod GauniyalJEDEA WB Pauri See Pic
12.07-09-2015Ch2.700R/wall RR Dry (rejected wall due to less base )Pramod GauniyalJEDEA WB Pauri See Pic
13.07-09-2015Ch1.900Damaged surface of roadPramod GauniyalJEDEA WB Pauri See Pic
14.07-09-2015Ch1.900Damaged surface of roadPramod GauniyalJEDEA WB Pauri See Pic
15.07-09-20152.700Damaged surface of the roadPramod GauniyalJEDEA WB Pauri See Pic
16.07-09-2015Ch2.200Damaged bitumin surface of the roadPramod GauniyalJEDEA WB Pauri See Pic
17.07-09-2015Ch7.800Damaged surface of the roadPramod GauniyalJEDEA WB Pauri See Pic
18.07-09-2015Ch2.700Damaged surfacePramod GauniyalJEDEA WB Pauri See Pic
19.07-09-2015Ch1.400-1.500R/wall RR Dry rejected (base less then standard, invited stone, slope not correct)Pramod GauniyalJEDEA WB Pauri See Pic
20.09-07-2015Ch9.600End point of the roadPramod GauniyalJEDEA WB Pauri See Pic