Pokhal-Bhawansi-mandlu motor road
Work Completed
|
Project: |
UDRP-RB |
UID: |
2237 |
Sanction Cost: |
920.16 lakh |
Length:
|
19.000 KM. |
District: |
Pauri |
Block: |
Dogadda |
Constituency: |
Yamkeshwar |
Circle: |
Tehri WB Circle |
DEA: |
DEA Pauri |
DSC: |
Egis International |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 79
Package Name: 
UDRP/PWD/06/71/RD/068
Tender Date: 28-01-2015
Current Status: Agreement signed
Achieved on Date: 05-06-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/06/71/RD/068
Contractor Name: MNR Construction Company
|
Start Date: 12-06-2015
Intended Completion Date: 31-03-2017
Original End Date: 11-09-2016 |
Total Bond Cost: 67993796.89 (679.94 lakh)
Variation Cost: 18816473.93 (188.16 lakh) Hence Total Bond Cost is 86810270.82 (868.1 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 8.54 KM | 131.82 | 01-10-2015 | 31-08-2016 | 8.54 KM | 8.54 KM | 15.14 | 131.82 | 2. | R/Wall, B/ Wall Type Protection works | 1143.00 m | 265.91 | 01-10-2015 | 15-06-2016 | 1143.00 m | 1143.00 m | 30.55 | 265.91 | 3. | GSB/RBI/G-1 | 8.00 KM | 52.43 | 15-02-2016 | 30-04-2016 | 8.00 KM | 8.00 KM | 6.02 | 52.43 | 4. | G-2 | 8.00 KM | 40.58 | 01-03-2016 | 30-06-2016 | 8.00 KM | 8.00 KM | 4.66 | 40.58 | 5. | G-3 | 12.00 KM | 59.39 | 15-10-2015 | 30-06-2016 | 12.00 KM | 12.00 KM | 6.82 | 59.39 | 6. | PC/CC i/c Prime Coat, Tack Coat | 13.50 KM | 141.58 | 15-10-2015 | 28-02-2017 | 13.50 KM | 13.50 KM | 16.26 | 141.58 | 7. | Cause Way | 9.00 No | 23.78 | 15-12-2015 | 10-09-2016 | 9.00 No | 9.00 No | 2.73 | 23.78 | 8. | Culverts/Scupper | 22.00 No | 58.89 | 01-10-2015 | 15-06-2016 | 22.00 No | 22.00 No | 6.77 | 58.89 | 9. | longitudinal Drain | 17330.00 m | 26.93 | 01-02-2016 | 28-02-2017 | 17330.00 m | 17330.00 m | 3.09 | 26.93 | 10. | Crash Barrier | 612.00 m | 15.33 | 01-01-2017 | 28-02-2017 | 612.00 m | 612.00 m | 1.76 | 15.33 | 11. | Parapet | 380.00 No | 9.39 | 01-01-2017 | 28-02-2017 | 380.00 No | 380.00 No | 1.08 | 9.39 | 12. | Road Furniture | 146.00 No | 2.39 | 01-11-2016 | 28-02-2017 | 148.00 No | 148.00 No | 0.28 | 2.39 | 13. | Other Allied Works & Finishing Work | 1.00 Job | 42.07 | 01-11-2015 | 28-02-2017 | 1.00 Job | 1.00 Job | 4.83 | 42.07 |
Total Amount: |
870.49 |
|
100 |
870.49 |
|
Remarks:
No Remarks
Work Program Made On:
06-05-2016 } ?>
Updation of work program on:
14-08-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 10-September-2015 | 75.03 lakh | 2. | 29-September-2015 | 42.47 lakh | 3. | 29-October-2015 | 35.27 lakh | 4. | 27-January-2016 | 68.61 lakh | 5. | 09-February-2016 | 66.17 lakh | 6. | 21-March-2016 | 78.15 lakh | 7. | 14-July-2016 | 127.21 lakh | 8. | 16-August-2016 | 30.28 lakh | 9. | 25-September-2016 | 71.98 lakh | 10. | 03-March-2017 | 52.13 lakh | 11. | 30-November-2017 | 223.24 lakh |
Total |
870.54 lakh |
% Payment |
100.27 % |
|
Advance Amount: 170.29 lakh
Recovered Amount: 170.29 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 208 No. of Test Done : 215 No. of Test Passed : 208 No. of Test Failed : 7 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 89.71 |
Number of Notice(s) issued: 102 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 20 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 27-03-2016 | 10.350km | R.wall | Pran Veer Singh | AAE | UDRP R&B Pauri | See Pic |
2. | 27-03-2016 | 17.375km | Scupper | Pran Veer Singh | AAE | UDRP R&B Pauri | See Pic |
3. | 27-03-2016 | 17.900km | Hill side cutting | Pran Veer Singh | AAE | UDRP R&B Pauri | See Pic |
4. | 03-02-2016 | 18.150km | R.wall | Pran Veer Singh | AAE | UDRP R&B Pauri | See Pic |
5. | 03-02-2016 | 14.350km | R.wall | Pran Veer Singh | AAE | UDRP R&B Pauri | See Pic |
6. | 03-02-2016 | 14.480km | Surface after laying G2 | Pran Veer Singh | AAE | UDRP R&B Pauri | See Pic |
7. | 03-02-2016 | 12.950km | Collection of g3 | Pran Veer Singh | AAE | UDRP R&B Pauri | See Pic |
8. | 03-02-2016 | 12.950km | Collection of G3 | Pran Veer Singh | AAE | UDRP R&B Pauri | See Pic |
9. | 27-01-2016 | 6.125 | Hsc,Coolie wall,etc. | Pran Veer Singh | AAE | UDRP R&B Pauri | See Pic |
10. | 27-01-2016 | 6.075km | Painting,hill side cutting | Pran Veer Singh | AAE | UDRP R&B Pauri | See Pic |
11. | 16-01-2016 | Ch 13/28 | Scupper slabe | Umesh Mishra | Site superviser | DEA WB Pauri | See Pic |
12. | 16-01-2016 | Ch 12/8 | H. S. Cuttings | Umesh Mishra | Site superviser | DEA WB Pauri | See Pic |
13. | 07-01-2016 | Ch 9/13 | Cause wey protection | Umesh Mishra | Site superviser | DEA WB Pauri | See Pic |
14. | 07-01-2016 | Ch17/15 | Scupper | Umesh Mishra | Site superviser | DEA WB Pauri | See Pic |
15. | 05-01-2016 | 10/12 | R/wall | Umesh Mishra | Site superviser | DEA WB Pauri | See Pic |
16. | 05-01-2016 | 10/21 | H. S. Cutting | Umesh Mishra | Site superviser | DEA WB Pauri | See Pic |
17. | 26-12-2015 | Ch15+950 | Scuppar | Umesh Mishra | Site superviser | DEA WB Pauri | See Pic |
18. | 26-12-2015 | Ch 14+500 | R/wall | Umesh Mishra | Site superviser | DEA WB Pauri | See Pic |
19. | 26-12-2015 | 10+600 | H. S. Cutting | Umesh Mishra | Site superviser | DEA WB Pauri | See Pic |
20. | 26-12-2015 | Ch 10+300 | R/ wall | Umesh Mishra | Site superviser | DEA WB Pauri | See Pic |
|
|