Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Neelkanth Link MR Work Completed
Project: UDRP-RB UID: 2218 Sanction Cost: 358.32  lakh Length: 5.000 KM.
District: Pauri Block: Yamkeshwar Constituency: Yamkeshwar Circle: Tehri WB Circle
DEA: DEA Pauri DSC: Egis International DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 78        Package Name:  UDRP/PWD/06/71/RD/067        Tender Date: 28-01-2015        Current Status: Agreement signed        Achieved on Date: 14-08-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/06/71/RD/067      Contractor Name: Gaurav Builder
Start Date:  21-08-2015      Intended Completion Date:  31-05-2017      Original End Date:  20-11-2016
Total Bond Cost: 32064880.58 (320.65 lakh)        Variation Cost: -1255738.16 (-12.56 lakh)    Hence Total Bond Cost is   30809142.42 (308.09 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 1811616 for 113 days        LD Analysis for Milestone2: calculated LD is Rs 4488960 for 280 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.76 KM27.4601-09-201531-03-20171.76 KM1.76 KM8.9127.46
2.R/Wall, B/ Wall Type Protection works605.00 m68.7801-09-201528-02-2017605.00 m605.00 m22.3368.78
3.G-30.63 KM6.8201-09-201531-03-20170.63 KM0.63 KM2.216.82
4.PC/CC i/c Prime Coat, Tack Coat0.00 KM0.0015-10-201615-10-20160.00 KM0.00 KM00.00
5.BM i/c Prime Coat, Tack Coat1.36 KM27.5401-11-201615-05-20171.36 KM1.36 KM8.9427.54
6.SDBC i/c Tackcoat4.68 KM69.8504-11-201631-05-20174.68 KM4.68 KM22.6769.85
7.Cause Way10.00 No29.7601-01-201631-03-201710.00 No10.00 No9.6629.76
8.Culverts/Scupper 9.00 No24.0601-01-201631-03-20179.00 No9.00 No7.8124.06
9.longitudinal Drain3628.00 m10.5801-04-201610-04-20173628.00 m3628.00 m3.4310.58
10.Crash Barrier500.00 m11.7515-12-201605-04-2017500.00 m500.00 m3.8111.75
11.Parapet100.00 No2.1701-12-201605-04-2017100.00 No100.00 No0.72.17
12.Road Furniture62.00 No1.4601-07-201631-05-201762.00 No62.00 No0.471.46
13.Other Allied Works & Finishing Work 1.00 Job27.8501-12-201631-05-20171.00 Job1.00 Job9.0427.85
Total Amount: 308.08 100   308.08
Remarks: No Remarks       Work Program Made On: 07-05-2016        Updation of work program on: 14-08-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.12-January-201619.06  lakh
2.29-February-201615.29  lakh
3.28-March-20167.74  lakh
4.16-May-201624.05  lakh
5.14-July-201620.18  lakh
6.31-December-201617.67  lakh
7.25-February-201720.14  lakh
8.03-March-201717.77  lakh
9.30-June-201787.58  lakh
10.16-October-201778.14  lakh
Total 307.62  lakh
% Payment 99.86 %
Advance Amount:  22.58  lakh        Recovered Amount:  22.58  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 133   No. of Test Done : 146    No. of Test Passed : 133   No. of Test Failed : 13   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.86
Number of Notice(s) issued: 108

Mobile Pic Upload

Number of Pics Available on Web Repository: 28
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.31-05-2017Ch 3/11Sign boardAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
2.28-05-2017Ch 1/37SlipAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
3.27-05-2017Ch 2/31Instructiob has been followed, given by TL to make platform so water should not come on the road surfaceAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
4.27-05-2017Ch 2/31Instruction by TL to make a concrete platform so water did not come on the road surafaceAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
5.25-05-2017Ch 3/7Fixing sign boardAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
6.25-05-2017Ch 1/0Kilometer stone and delinatorAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
7.24-05-2017Ch 0/32Hectometer stone and delinatorAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
8.24-05-2017Ch 0/30Sign boardAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
9.24-05-2017Ch 0/0Board at starting pointAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
10.24-05-2017Ch 4/7Fixing of thermoplastic white strip on the edge of roadAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
11.10-04-20173/23Patch workDeepak GoelREDSC2 R&B WB Pauri See Pic
12.10-04-20173/23Patch workDeepak GoelREDSC2 R&B WB Pauri See Pic
13.10-04-2017Ch 3/17Rolling over bituminous layerAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
14.10-04-2017Ch 3/4Surface cleaning in progress for Bituminous layerAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
15.10-04-2017Ch 3/17Cleaning the surface for bituminous layerAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
16.09-04-2017Ch 0/10Plum concrete at the base of scupper in progressAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
17.09-04-2017Ch 2/12Parapet work in progressAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
18.08-04-2017Ch 3/4SlipAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
19.08-04-2017Ch 2/28M-10 Plum concreteAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
20.08-04-2017Ch 2/18Crash BarrierAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic