Neelkanth Link MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
2218 |
Sanction Cost: |
358.32 lakh |
Length:
|
5.000 KM. |
District: |
Pauri |
Block: |
Yamkeshwar |
Constituency: |
Yamkeshwar |
Circle: |
Tehri WB Circle |
DEA: |
DEA Pauri |
DSC: |
Egis International |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 78
Package Name: 
UDRP/PWD/06/71/RD/067
Tender Date: 28-01-2015
Current Status: Agreement signed
Achieved on Date: 14-08-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/06/71/RD/067
Contractor Name: Gaurav Builder
|
Start Date: 21-08-2015
Intended Completion Date: 31-05-2017
Original End Date: 20-11-2016 |
Total Bond Cost: 32064880.58 (320.65 lakh)
Variation Cost: -1255738.16 (-12.56 lakh) Hence Total Bond Cost is 30809142.42 (308.09 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 1811616 for 113 days
LD Analysis for Milestone2: calculated LD is Rs 4488960 for 280 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.76 KM | 27.46 | 01-09-2015 | 31-03-2017 | 1.76 KM | 1.76 KM | 8.91 | 27.46 | 2. | R/Wall, B/ Wall Type Protection works | 605.00 m | 68.78 | 01-09-2015 | 28-02-2017 | 605.00 m | 605.00 m | 22.33 | 68.78 | 3. | G-3 | 0.63 KM | 6.82 | 01-09-2015 | 31-03-2017 | 0.63 KM | 0.63 KM | 2.21 | 6.82 | 4. | PC/CC i/c Prime Coat, Tack Coat | 0.00 KM | 0.00 | 15-10-2016 | 15-10-2016 | 0.00 KM | 0.00 KM | 0 | 0.00 | 5. | BM i/c Prime Coat, Tack Coat | 1.36 KM | 27.54 | 01-11-2016 | 15-05-2017 | 1.36 KM | 1.36 KM | 8.94 | 27.54 | 6. | SDBC i/c Tackcoat | 4.68 KM | 69.85 | 04-11-2016 | 31-05-2017 | 4.68 KM | 4.68 KM | 22.67 | 69.85 | 7. | Cause Way | 10.00 No | 29.76 | 01-01-2016 | 31-03-2017 | 10.00 No | 10.00 No | 9.66 | 29.76 | 8. | Culverts/Scupper | 9.00 No | 24.06 | 01-01-2016 | 31-03-2017 | 9.00 No | 9.00 No | 7.81 | 24.06 | 9. | longitudinal Drain | 3628.00 m | 10.58 | 01-04-2016 | 10-04-2017 | 3628.00 m | 3628.00 m | 3.43 | 10.58 | 10. | Crash Barrier | 500.00 m | 11.75 | 15-12-2016 | 05-04-2017 | 500.00 m | 500.00 m | 3.81 | 11.75 | 11. | Parapet | 100.00 No | 2.17 | 01-12-2016 | 05-04-2017 | 100.00 No | 100.00 No | 0.7 | 2.17 | 12. | Road Furniture | 62.00 No | 1.46 | 01-07-2016 | 31-05-2017 | 62.00 No | 62.00 No | 0.47 | 1.46 | 13. | Other Allied Works & Finishing Work | 1.00 Job | 27.85 | 01-12-2016 | 31-05-2017 | 1.00 Job | 1.00 Job | 9.04 | 27.85 |
Total Amount: |
308.08 |
|
100 |
308.08 |
|
Remarks:
No Remarks
Work Program Made On:
07-05-2016 } ?>
Updation of work program on:
14-08-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 12-January-2016 | 19.06 lakh | 2. | 29-February-2016 | 15.29 lakh | 3. | 28-March-2016 | 7.74 lakh | 4. | 16-May-2016 | 24.05 lakh | 5. | 14-July-2016 | 20.18 lakh | 6. | 31-December-2016 | 17.67 lakh | 7. | 25-February-2017 | 20.14 lakh | 8. | 03-March-2017 | 17.77 lakh | 9. | 30-June-2017 | 87.58 lakh | 10. | 16-October-2017 | 78.14 lakh |
Total |
307.62 lakh |
% Payment |
99.86 % |
|
Advance Amount: 22.58 lakh
Recovered Amount: 22.58 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 133 No. of Test Done : 146 No. of Test Passed : 133 No. of Test Failed : 13 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 89.86 |
Number of Notice(s) issued: 108 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 28 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 31-05-2017 | Ch 3/11 | Sign board | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
2. | 28-05-2017 | Ch 1/37 | Slip | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
3. | 27-05-2017 | Ch 2/31 | Instructiob has been followed, given by TL to make platform so water should not come on the road surface | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
4. | 27-05-2017 | Ch 2/31 | Instruction by TL to make a concrete platform so water did not come on the road suraface | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
5. | 25-05-2017 | Ch 3/7 | Fixing sign board | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
6. | 25-05-2017 | Ch 1/0 | Kilometer stone and delinator | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
7. | 24-05-2017 | Ch 0/32 | Hectometer stone and delinator | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
8. | 24-05-2017 | Ch 0/30 | Sign board | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
9. | 24-05-2017 | Ch 0/0 | Board at starting point | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
10. | 24-05-2017 | Ch 4/7 | Fixing of thermoplastic white strip on the edge of road | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
11. | 10-04-2017 | 3/23 | Patch work | Deepak Goel | RE | DSC2 R&B WB Pauri | See Pic |
12. | 10-04-2017 | 3/23 | Patch work | Deepak Goel | RE | DSC2 R&B WB Pauri | See Pic |
13. | 10-04-2017 | Ch 3/17 | Rolling over bituminous layer | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
14. | 10-04-2017 | Ch 3/4 | Surface cleaning in progress for Bituminous layer | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
15. | 10-04-2017 | Ch 3/17 | Cleaning the surface for bituminous layer | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
16. | 09-04-2017 | Ch 0/10 | Plum concrete at the base of scupper in progress | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
17. | 09-04-2017 | Ch 2/12 | Parapet work in progress | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
18. | 08-04-2017 | Ch 3/4 | Slip | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
19. | 08-04-2017 | Ch 2/28 | M-10 Plum concrete | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
20. | 08-04-2017 | Ch 2/18 | Crash Barrier | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
|
|