Khandah- Bacheli MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
2186 |
Sanction Cost: |
150.70 lakh |
Length:
|
3.500 KM. |
District: |
Pauri |
Block: |
Pauri |
Constituency: |
Pauri |
Circle: |
Tehri WB Circle |
DEA: |
DEA Pauri |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 16
Package Name: 
UDRP/PWD/06/69/RD/016
Tender Date: 23-05-2015
Current Status: Agreement signed
Achieved on Date: 31-10-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/06/69/RD/016
Contractor Name: Sri Shiv Singh Gusain
|
Start Date: 07-11-2015
Intended Completion Date: 17-03-2018
Original End Date: 06-02-2017 |
Total Bond Cost: 42264358.39 (422.64 lakh)
Variation Cost: 10463724.21 (104.64 lakh) Hence Total Bond Cost is 52728082.6 (527.28 lakh)
|
Sub Project Cost: 95.78 lakh
Variation Cost of Sub Project: 3616371.84 (36.16 lakh)
Total Sub Project Cost:
131.94 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 2.06 KM | 10.45 | 20-11-2015 | 31-05-2017 | 2.06 KM | 2.06 KM | 7.29 | 10.45 | 2. | R/Wall, B/ Wall Type Protection works | 427.00 m | 36.32 | 20-11-2015 | 31-01-2017 | 427.00 m | 427.00 m | 25.32 | 36.32 | 3. | GSB/RBI/G-1 | 0.38 KM | 2.34 | 15-04-2016 | 15-02-2017 | 0.50 KM | 0.50 KM | 1.63 | 2.34 | 4. | G-2 | 0.50 KM | 2.42 | 01-05-2016 | 15-04-2017 | 1.01 KM | 1.01 KM | 1.69 | 2.42 | 5. | G-3 | 0.86 KM | 4.31 | 15-05-2016 | 30-04-2017 | 1.13 KM | 1.13 KM | 3.01 | 4.31 | 6. | PC/CC i/c Prime Coat, Tack Coat | 3.40 KM | 49.85 | 15-05-2016 | 31-05-2017 | 3.40 KM | 3.40 KM | 34.75 | 49.85 | 7. | Cause Way | 1.00 No | 3.64 | 15-04-2016 | 31-01-2017 | 1.00 No | 1.00 No | 2.54 | 3.64 | 8. | Culverts/Scupper | 8.00 No | 14.52 | 01-12-2015 | 30-04-2017 | 8.00 No | 8.00 No | 10.12 | 14.52 | 9. | longitudinal Drain | 3480.00 m | 6.37 | 01-05-2016 | 31-05-2017 | 3395.00 m | 3395.00 m | 4.44 | 6.37 | 10. | Crash Barrier | 50.00 m | 1.41 | 01-04-2017 | 31-05-2017 | 50.00 m | 50.00 m | 0.98 | 1.41 | 11. | Road Furniture | 34.00 No | 0.79 | 01-07-2016 | 15-06-2017 | 34.00 No | 34.00 No | 0.55 | 0.79 | 12. | Other Allied Works & Finishing Work | 1.00 Job | 11.03 | 20-11-2015 | 15-06-2017 | 1.00 Job | 1.00 Job | 7.69 | 11.03 |
Total Amount: |
143.45 |
|
100 |
143.45 |
|
Remarks:
No Remarks
Work Program Made On:
06-05-2016 } ?>
Updation of work program on:
20-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-March-2016 | 46.53 lakh | 2. | 05-August-2016 | 22.87 lakh | 3. | 12-January-2017 | 22.29 lakh | 4. | 30-March-2017 | 2.69 lakh | 5. | 12-June-2017 | 17.75 lakh | 6. | 30-June-2017 | 1.02 lakh | 7. | 17-August-2017 | 0.82 lakh | 8. | 13-April-2018 | 10.77 lakh | 9. | 21-August-2018 | 1.81 lakh |
Total |
126.55 lakh |
% Payment | 95.91 % |
|
Advance Amount: 78.04 lakh
Recovered Amount: 78.04 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 385 No. of Test Done : 412 No. of Test Passed : 385 No. of Test Failed : 27 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 89.54 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 71 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 28-11-2017 | Ch-1/13-14 | World bank visit. | Ankur Kukreti | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
2. | 28-11-2017 | Ch-1/12-13 | WORLD BANK visit. | Ankur Kukreti | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
3. | 24-04-2017 | Ch-0/8-9 | Laying seal coat. | Ashutosh Bhatt | JE | UDRP R&B Pauri | See Pic |
4. | 23-04-2017 | Ch-0/5-6 | Rolling on PC. | Ankur Kukreti | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
5. | 23-04-2017 | Ch-0/5-6 | PC Work | Ankur Kukreti | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
6. | 23-04-2017 | Ch-0/11-12 | RE sir for a visit. | Ankur Kukreti | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
7. | 23-04-2017 | Ch-0/5-6 | Rolling on pc | Ashutosh Bhatt | JE | UDRP R&B Pauri | See Pic |
8. | 23-04-2017 | Ch-0/5-6 | PC work in progress. | Ashutosh Bhatt | JE | UDRP R&B Pauri | See Pic |
9. | 20-04-2017 | 0/15 | Checking of undulation at PC surface | Deepak Goel | RE | DSC2 R&B WB Pauri | See Pic |
10. | 20-04-2017 | 0/11 | PC work in progress | Deepak Goel | RE | DSC2 R&B WB Pauri | See Pic |
11. | 15-04-2017 | Ch-0/30-31 | PC work . | Ankur Kukreti | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
12. | 15-04-2017 | Ch-0/31-32 | AE sir PWD (WB ) pauri for a visit. | Ankur Kukreti | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
13. | 15-04-2017 | Ch-30-31 | Laying PC work. | Ashutosh Bhatt | JE | UDRP R&B Pauri | See Pic |
14. | 15-04-2017 | Ch-0/30-31 | Undulation & roadthickness checking by Ae sir pwd (WB) Pauri found satisfactory. | Ashutosh Bhatt | JE | UDRP R&B Pauri | See Pic |
15. | 14-04-2017 | Ch-0/34-35 | Bitumen extraction test. | Ankur Kukreti | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
16. | 14-04-2017 | Ch-0/34-35 | PC Bitumen Extraction Test foudnd satisfactory. | Ashutosh Bhatt | JE | UDRP R&B Pauri | See Pic |
17. | 14-04-2017 | Ch-0/33-34 | PC work | Ankur Kukreti | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
18. | 14-04-2017 | Ch-0/33-34 | PC work | Ashutosh Bhatt | JE | UDRP R&B Pauri | See Pic |
19. | 12-04-2017 | Ch-0/34-35 | Visit by Ex.En sir (pauri WB) for checking of patch. | Ankur Kukreti | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
20. | 12-04-2017 | Ch-0/25-26 | Patch work. | Ankur Kukreti | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
|
|