Gangadarshan Band to NH-58 KM Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
2167 |
Sanction Cost: |
67.78 lakh |
Length:
|
0.500 KM. |
District: |
Pauri |
Block: |
Pauri |
Constituency: |
Pauri |
Circle: |
Tehri WB Circle |
DEA: |
DEA Pauri |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 16
Package Name: 
UDRP/PWD/06/69/RD/016
Tender Date: 23-05-2015
Current Status: Agreement signed
Achieved on Date: 31-10-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/06/69/RD/016
Contractor Name: Sri Shiv Singh Gusain
|
Start Date: 07-11-2015
Intended Completion Date: 17-03-2018
Original End Date: 06-02-2017 |
Total Bond Cost: 42264358.39 (422.64 lakh)
Variation Cost: 10463724.21 (104.64 lakh) Hence Total Bond Cost is 52728082.6 (527.28 lakh)
|
Sub Project Cost: 87.64 lakh
Variation Cost of Sub Project: -3172037.48 (-31.72 lakh)
Total Sub Project Cost:
55.92 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 3.13 KM | 7.51 | 30-11-2015 | 31-05-2017 | 3.13 KM | 3.13 KM | 13 | 7.51 | 2. | R/Wall, B/ Wall Type Protection works | 312.00 m | 26.17 | 30-11-2015 | 31-05-2017 | 312.00 m | 312.00 m | 45.26 | 26.17 | 3. | GSB/RBI/G-1 | 0.60 KM | 1.67 | 25-11-2016 | 30-09-2017 | 0.60 KM | 0.60 KM | 2.89 | 1.67 | 4. | G-2 | 0.00 KM | 0.00 | 01-12-2016 | 01-12-2016 | 0.00 KM | 0.00 KM | 0 | 0.00 | 5. | G-3 | 0.00 KM | 0.00 | 15-12-2016 | 15-12-2016 | 0.00 KM | 0.00 KM | 0 | 0.00 | 6. | PC/CC i/c Prime Coat, Tack Coat | 0.00 KM | 0.00 | 15-04-2017 | 15-04-2017 | 0.00 KM | 0.00 KM | 0 | 0.00 | 7. | Culverts/Scupper | 8.00 No | 13.43 | 20-01-2016 | 31-05-2017 | 8.00 No | 8.00 No | 23.22 | 13.43 | 8. | longitudinal Drain | 2671.00 m | 2.61 | 01-06-2016 | 17-03-2018 | 2671.00 m | 2671.00 m | 4.52 | 2.61 | 9. | Crash Barrier | 0.00 m | 0.00 | 01-04-2017 | 01-04-2017 | 0.00 m | 0.00 m | 0 | 0.00 | 10. | Parapet | 0.00 No | 0.00 | 01-04-2017 | 01-04-2017 | 0.00 No | 0.00 No | 0 | 0.00 | 11. | Road Furniture | 2.00 No | 0.11 | 01-11-2016 | 17-03-2018 | 2.00 No | 2.00 No | 0.19 | 0.11 | 12. | Other Allied Works & Finishing Work | 1.00 Job | 6.32 | 15-06-2016 | 17-03-2018 | 1.00 Job | 1.00 Job | 10.92 | 6.32 |
Total Amount: |
57.82 |
|
100 |
57.82 |
|
Remarks:
No Remarks
Work Program Made On:
06-05-2016 } ?>
Updation of work program on:
29-03-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-March-2016 | 36.09 lakh | 2. | 05-August-2016 | 8.97 lakh | 3. | 12-January-2017 | 2.49 lakh | 4. | 30-March-2017 | 2.99 lakh | 5. | 30-June-2017 | 0.42 lakh | 6. | 17-August-2017 | 0.34 lakh | 7. | 13-April-2018 | 3.46 lakh | 8. | 21-August-2018 | 3.10 lakh |
Total |
57.86 lakh |
% Payment | 103.47 % |
|
Advance Amount: 78.04 lakh
Recovered Amount: 78.04 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 385 No. of Test Done : 412 No. of Test Passed : 385 No. of Test Failed : 27 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 88.94 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 11 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 07-04-2017 | Ch-2/26-27 | Layers of wire crate. | Ankur Kukreti | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
2. | 06-04-2017 | Ch-2\26-27 | Three layer of wire crate R\W at ganga darshan bend to Nh-58 motor road. | Ashutosh Bhatt | JE | UDRP R&B Pauri | See Pic |
3. | 30-12-2016 | Ch-2/24-25 | Site inspection by SE sir "8th circle tehri" at ganga darshan to NH58m/r | Ashutosh Bhatt | JE | UDRP R&B Pauri | See Pic |
4. | 02-12-2016 | Ch - 1/26 | Visit by SE sir 12th circle pauri,SE sir world bank rudraprayag. | Ankur Kukreti | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
5. | 26-08-2016 | Ch-2.650 to 2.700 | Se sir site visit at ganga darshan bend to Nh58 m/road because road damaged due to heavy rainfall | Ashutosh Bhatt | JE | UDRP R&B Pauri | See Pic |
6. | 14-08-2016 | Ch-2.650 | Se sir site visit at ganga darshan bend to Nh-58 m/road. | Ashutosh Bhatt | JE | UDRP R&B Pauri | See Pic |
7. | 26-02-2016 | Ch-0.450 | Bended wall ,scupper toe wall at ganga darshan to Nh58road. | Ashutosh Bhatt | JE | UDRP R&B Pauri | See Pic |
8. | 26-02-2016 | Ch-1.125 | Scupper massonary &wing walls at ganga darshan to Nh58 road. | Ashutosh Bhatt | JE | UDRP R&B Pauri | See Pic |
9. | 26-02-2016 | Ch-1675 | Scupper massonary at ganga darshan to Nh58 road | Ashutosh Bhatt | JE | UDRP R&B Pauri | See Pic |
10. | 28-12-2015 | Ch- 0.450 ganga darshan to Nh 58 road. | Plum masonary at ganga darshan to Nh-58 road. | Ashutosh Bhatt | JE | UDRP R&B Pauri | See Pic |
11. | 18-12-2015 | Ch-1.800 R/W | Ganga darshan toNh-58 road dry R/W | Ashutosh Bhatt | JE | UDRP R&B Pauri | See Pic |
|
|