Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Gangadarshan Band to NH-58 KM Motor Road Work Completed
Project: UDRP-RB UID: 2167 Sanction Cost: 67.78  lakh Length: 0.500 KM.
District: Pauri Block: Pauri Constituency: Pauri Circle: Tehri WB Circle
DEA: DEA Pauri DSC: Egis International DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 16        Package Name:  UDRP/PWD/06/69/RD/016        Tender Date: 23-05-2015        Current Status: Agreement signed        Achieved on Date: 31-10-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/06/69/RD/016      Contractor Name: Sri Shiv Singh Gusain
Start Date:  07-11-2015      Intended Completion Date:  17-03-2018      Original End Date:  06-02-2017
Total Bond Cost: 42264358.39 (422.64 lakh)        Variation Cost: 10463724.21 (104.64 lakh)    Hence Total Bond Cost is   52728082.6 (527.28 lakh) 
Sub Project Cost: 87.64  lakh        Variation Cost of Sub Project: -3172037.48  (-31.72 lakh)       Total Sub Project Cost:   55.92 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence3.13 KM7.5130-11-201531-05-20173.13 KM3.13 KM137.51
2.R/Wall, B/ Wall Type Protection works312.00 m26.1730-11-201531-05-2017312.00 m312.00 m45.2626.17
3.GSB/RBI/G-10.60 KM1.6725-11-201630-09-20170.60 KM0.60 KM2.891.67
4.G-20.00 KM0.0001-12-201601-12-20160.00 KM0.00 KM00.00
5.G-30.00 KM0.0015-12-201615-12-20160.00 KM0.00 KM00.00
6.PC/CC i/c Prime Coat, Tack Coat0.00 KM0.0015-04-201715-04-20170.00 KM0.00 KM00.00
7.Culverts/Scupper 8.00 No13.4320-01-201631-05-20178.00 No8.00 No23.2213.43
8.longitudinal Drain2671.00 m2.6101-06-201617-03-20182671.00 m2671.00 m4.522.61
9.Crash Barrier0.00 m0.0001-04-201701-04-20170.00 m0.00 m00.00
10.Parapet0.00 No0.0001-04-201701-04-20170.00 No0.00 No00.00
11.Road Furniture2.00 No0.1101-11-201617-03-20182.00 No2.00 No0.190.11
12.Other Allied Works & Finishing Work 1.00 Job6.3215-06-201617-03-20181.00 Job1.00 Job10.926.32
Total Amount: 57.82 100   57.82
Remarks: No Remarks       Work Program Made On: 06-05-2016        Updation of work program on: 29-03-2019       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-March-201636.09  lakh
2.05-August-20168.97  lakh
3.12-January-20172.49  lakh
4.30-March-20172.99  lakh
5.30-June-20170.42  lakh
6.17-August-20170.34  lakh
7.13-April-20183.46  lakh
8.21-August-20183.10  lakh
Total 57.86  lakh
% Payment103.47 %
Advance Amount:  78.04  lakh        Recovered Amount:  78.04  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 385   No. of Test Done : 412    No. of Test Passed : 385   No. of Test Failed : 27   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 88.94
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 11
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.07-04-2017Ch-2/26-27Layers of wire crate.Ankur KukretiSite SupervisorDSC2 R&B WB Pauri See Pic
2.06-04-2017Ch-2\26-27Three layer of wire crate R\W at ganga darshan bend to Nh-58 motor road.Ashutosh BhattJEUDRP R&B Pauri See Pic
3.30-12-2016Ch-2/24-25Site inspection by SE sir "8th circle tehri" at ganga darshan to NH58m/rAshutosh BhattJEUDRP R&B Pauri See Pic
4.02-12-2016Ch - 1/26Visit by SE sir 12th circle pauri,SE sir world bank rudraprayag.Ankur KukretiSite SupervisorDSC2 R&B WB Pauri See Pic
5.26-08-2016Ch-2.650 to 2.700Se sir site visit at ganga darshan bend to Nh58 m/road because road damaged due to heavy rainfallAshutosh BhattJEUDRP R&B Pauri See Pic
6.14-08-2016Ch-2.650Se sir site visit at ganga darshan bend to Nh-58 m/road.Ashutosh BhattJEUDRP R&B Pauri See Pic
7.26-02-2016Ch-0.450Bended wall ,scupper toe wall at ganga darshan to Nh58road.Ashutosh BhattJEUDRP R&B Pauri See Pic
8.26-02-2016Ch-1.125Scupper massonary &wing walls at ganga darshan to Nh58 road.Ashutosh BhattJEUDRP R&B Pauri See Pic
9.26-02-2016Ch-1675Scupper massonary at ganga darshan to Nh58 roadAshutosh BhattJEUDRP R&B Pauri See Pic
10.28-12-2015Ch- 0.450 ganga darshan to Nh 58 road.Plum masonary at ganga darshan to Nh-58 road.Ashutosh BhattJEUDRP R&B Pauri See Pic
11.18-12-2015Ch-1.800 R/WGanga darshan toNh-58 road dry R/WAshutosh BhattJEUDRP R&B Pauri See Pic