Sub Project Profile Report

Diet-Chadhigaon MR Work Completed
Project: UDRP-RB UID: 2160 Sanction Cost: 100.59  lakh Length: 2.500 KM.
District: Pauri Block: Khirsu Constituency: Srinagar Circle: Tehri WB Circle
DEA: DEA Pauri DSC: Egis International DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 16        Package Name:  UDRP/PWD/06/69/RD/016        Tender Date: 23-05-2015        Current Status: Agreement signed        Achieved on Date: 31-10-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/06/69/RD/016      Contractor Name: Sri Shiv Singh Gusain
Start Date:  07-11-2015      Intended Completion Date:  17-03-2018      Original End Date:  06-02-2017
Total Bond Cost: 42264358.39 (422.64 lakh)        Variation Cost: 10463724.21 (104.64 lakh)    Hence Total Bond Cost is   52728082.6 (527.28 lakh) 
Sub Project Cost: 64.42  lakh        Variation Cost of Sub Project: 1541414.73  (15.41 lakh)       Total Sub Project Cost:   79.83 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.81 KM7.2015-12-201531-03-20171.81 KM1.81 KM7.457.20
2.R/Wall, B/ Wall Type Protection works190.00 m28.6315-12-201531-01-2017190.00 m190.00 m29.6128.63
3.G-20.04 KM0.2515-02-201618-05-20160.04 KM0.04 KM0.260.25
4.G-30.31 KM1.0315-05-201615-06-20160.31 KM0.31 KM1.071.03
5.PC/CC i/c Prime Coat, Tack Coat2.40 KM35.1715-05-201631-05-20172.50 KM2.50 KM36.3735.17
6.Culverts/Scupper 4.00 No7.0010-01-201630-04-20175.00 No5.00 No7.247.00
7.longitudinal Drain2480.00 m3.2601-04-201630-09-20172480.00 m2480.00 m3.373.26
8.Crash Barrier50.00 m3.2415-12-201630-09-201750.00 m50.00 m3.353.24
9.Parapet100.00 No2.3515-04-201715-10-201790.00 No90.00 No2.432.35
10.Road Furniture32.00 No0.8115-06-201615-10-201732.00 No32.00 No0.840.81
11.Other Allied Works & Finishing Work 1.00 Job7.7615-12-201515-10-20171.00 Job1.00 Job8.037.76
Total Amount: 96.7 100   96.7
Remarks: No Remarks       Work Program Made On: 06-05-2016        Updation of work program on: 16-11-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-March-201619.34  lakh
2.25-May-201619.76  lakh
3.05-August-201624.37  lakh
4.12-January-20175.93  lakh
5.30-March-20172.93  lakh
6.30-June-20170.68  lakh
7.17-August-20170.55  lakh
8.13-April-20183.84  lakh
9.21-August-20181.21  lakh
Total 78.61  lakh
% Payment98.47 %
Advance Amount:  78.04  lakh        Recovered Amount:  78.04  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 385   No. of Test Done : 412    No. of Test Passed : 385   No. of Test Failed : 27   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.39
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 18
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.11-02-2017Ch-1/14-15Parapet castingAnkur KukretiSite SupervisorDSC2 R&B WB Pauri See Pic
2.11-02-2017Ch-1.350-1.375Casting of parapet (M10) diet Chadigaun M/RAshutosh BhattJEUDRP R&B Pauri See Pic
3.08-02-2017Ch-1/8-9Parapet castingAnkur KukretiSite SupervisorDSC2 R&B WB Pauri See Pic
4.08-02-2017Ch-1/7-8 diet Chadigaun M/RoadCasting of parapet( M10)at diet Chadigaun M/RAshutosh BhattJEUDRP R&B Pauri See Pic
5.02-12-20160/8Checking of scuppper by SE World Bank and SE 12th circle PWD PauriDeepak GoelREDSC2 R&B WB Pauri See Pic
6.02-12-2016Ch-2.200PC thickness checking by SE sir at diet Chadigaun M/ road.Ashutosh BhattJEUDRP R&B Pauri See Pic
7.02-12-2016Ch-2/8Checking of width by SC sirAnkur KukretiSite SupervisorDSC2 R&B WB Pauri See Pic
8.23-11-2016Ch-1/5-6World bank team visitAnkur KukretiSite SupervisorDSC2 R&B WB Pauri See Pic
9.23-11-2016Ch.2.500World Bank team visit at diet Chadigaun M/ road.Ashutosh BhattJEUDRP R&B Pauri See Pic
10.19-11-2016Ch-1.375-400RCC Scupper crash barrier casting at diet Chadigaun M/RAshutosh BhattJEUDRP R&B Pauri See Pic
11.23-09-2016Ch-2/19SC sir,AE sir, Xen sir ,RE sir for a visitAnkur KukretiSite SupervisorDSC2 R&B WB Pauri See Pic
12.15-08-2016Ch-2/20-18PC workAnkur KukretiSite SupervisorDSC2 R&B WB Pauri See Pic
13.20-05-2016Ch-2.450Bituminous testing for PC at diet chadigaon motor road.Ashutosh BhattJEUDRP R&B Pauri See Pic
14.18-05-2016Ch-2.225Patch work at diet chadigaon m/road.Ashutosh BhattJEUDRP R&B Pauri See Pic
15.16-05-20161.750Laying roller on G3 diet chadigaon motor roadAshutosh BhattJEUDRP R&B Pauri See Pic
16.16-05-2016Ch-2.400Diet chadigaon m/roadAshutosh BhattJEUDRP R&B Pauri See Pic
17.25-02-2016Ch-2.400Scupper massonary at diet chadigaun roadAshutosh BhattJEUDRP R&B Pauri See Pic
18.25-02-2016Ch-2.050Brestwall at diet chadigaun road.Ashutosh BhattJEUDRP R&B Pauri See Pic