Chamrada- Asingi- Dadini MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
2136 |
Sanction Cost: |
287.25 lakh |
Length:
|
4.250 KM. |
District: |
Pauri |
Block: |
Khirsu |
Constituency: |
Srinagar |
Circle: |
Tehri WB Circle |
DEA: |
DEA Pauri |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 16
Package Name: 
UDRP/PWD/06/69/RD/016
Tender Date: 23-05-2015
Current Status: Agreement signed
Achieved on Date: 31-10-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/06/69/RD/016
Contractor Name: Sri Shiv Singh Gusain
|
Start Date: 07-11-2015
Intended Completion Date: 17-03-2018
Original End Date: 06-02-2017 |
Total Bond Cost: 42264358.39 (422.64 lakh)
Variation Cost: 10463724.21 (104.64 lakh) Hence Total Bond Cost is 52728082.6 (527.28 lakh)
|
Sub Project Cost: 168.70 lakh
Variation Cost of Sub Project: 8477975.12 (84.78 lakh)
Total Sub Project Cost:
253.48 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 3.05 KM | 22.70 | 01-01-2016 | 30-09-2017 | 3.05 KM | 3.05 KM | 7.91 | 22.70 | 2. | R/Wall, B/ Wall Type Protection works | 357.00 m | 40.04 | 07-11-2015 | 30-09-2017 | 357.00 m | 357.00 m | 13.95 | 40.04 | 3. | GSB/RBI/G-1 | 3.80 KM | 25.36 | 15-04-2016 | 10-04-2017 | 3.80 KM | 3.80 KM | 8.84 | 25.36 | 4. | G-2 | 3.80 KM | 17.76 | 15-06-2016 | 20-04-2017 | 3.80 KM | 3.80 KM | 6.19 | 17.76 | 5. | G-3 | 3.80 KM | 21.31 | 01-04-2017 | 15-10-2017 | 3.80 KM | 3.80 KM | 7.43 | 21.31 | 6. | PC/CC i/c Prime Coat, Tack Coat | 3.82 KM | 52.26 | 01-05-2017 | 20-06-2017 | 3.82 KM | 3.82 KM | 18.21 | 52.26 | 7. | Cause Way | 5.00 No | 33.26 | 01-02-2017 | 30-09-2017 | 5.00 No | 5.00 No | 11.59 | 33.26 | 8. | Culverts/Scupper | 9.00 No | 20.86 | 01-02-2016 | 10-10-2017 | 9.00 No | 9.00 No | 7.27 | 20.86 | 9. | longitudinal Drain | 4050.00 m | 7.99 | 15-06-2016 | 30-09-2017 | 3850.00 m | 3850.00 m | 2.78 | 7.99 | 10. | Crash Barrier | 350.00 m | 10.58 | 01-08-2017 | 10-10-2017 | 350.00 m | 350.00 m | 3.69 | 10.58 | 11. | Parapet | 390.00 No | 10.09 | 01-10-2016 | 15-10-2017 | 195.00 No | 195.00 No | 3.52 | 10.09 | 12. | Road Furniture | 36.00 No | 1.04 | 01-11-2016 | 15-10-2017 | 38.00 No | 38.00 No | 0.36 | 1.04 | 13. | Other Allied Works & Finishing Work | 1.00 Job | 23.73 | 01-12-2015 | 15-10-2017 | 1.00 Job | 1.00 Job | 8.27 | 23.73 |
Total Amount: |
286.98 |
|
100 |
286.98 |
|
Remarks:
No Remarks
Work Program Made On:
05-05-2016 } ?>
Updation of work program on:
16-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-March-2016 | 38.14 lakh | 2. | 05-August-2016 | 16.50 lakh | 3. | 12-January-2017 | 20.23 lakh | 4. | 30-March-2017 | 26.78 lakh | 5. | 30-June-2017 | 30.06 lakh | 6. | 17-August-2017 | 24.37 lakh | 7. | 13-April-2018 | 83.37 lakh | 8. | 21-August-2018 | 17.62 lakh |
Total |
257.07 lakh |
% Payment | 101.42 % |
|
Advance Amount: 78.04 lakh
Recovered Amount: 78.04 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 385 No. of Test Done : 412 No. of Test Passed : 385 No. of Test Failed : 27 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 89.15 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 33 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 18-06-2017 | 1/19 | PC work in progress | Deepak Goel | RE | DSC2 R&B WB Pauri | See Pic |
2. | 18-06-2017 | Field lab | Bitumen extraction test | Deepak Goel | RE | DSC2 R&B WB Pauri | See Pic |
3. | 18-06-2017 | 1/35 | Checking of thickness of PC layer | Deepak Goel | RE | DSC2 R&B WB Pauri | See Pic |
4. | 18-06-2017 | 1/34 | Checking of undulations at PC | Deepak Goel | RE | DSC2 R&B WB Pauri | See Pic |
5. | 20-05-2017 | Ch-3/28-29 | Laid G-3 | Ankur Kukreti | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
6. | 19-03-2017 | Ch - 0/20 | EMP IMPLEMENTATION TRAINING | Ankur Kukreti | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
7. | 14-03-2017 | 0+500 | EMP implementation training by Environmental Expert of Egis India | Deepak Goel | RE | DSC2 R&B WB Pauri | See Pic |
8. | 06-03-2017 | Field lab | Gradation test of G2 material. | Deepak Goel | RE | DSC2 R&B WB Pauri | See Pic |
9. | 06-03-2017 | Ch 2/33 | Construction of R/W | Deepak Goel | RE | DSC2 R&B WB Pauri | See Pic |
10. | 18-02-2017 | Ch-1/5-6 | Gradation of G2 ... Found satisfactory | Ankur Kukreti | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
11. | 03-12-2016 | 3/25 | Crust thickness of G1+G2 layer checked by SE World Bank & SE 12th circle PWD Pauri and found 175 mm. | Deepak Goel | RE | DSC2 R&B WB Pauri | See Pic |
12. | 02-12-2016 | Ch-3/25-26 | Road Crust checking by SC sir | Ankur Kukreti | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
13. | 02-12-2016 | Ch-3.625 | Road crust checking by se sir at chamrada asingi m/ road. | Ashutosh Bhatt | JE | UDRP R&B Pauri | See Pic |
14. | 19-11-2016 | Ch-1.400 | S/M 1:5 for catch pit at diet Chadigaun M/R | Ashutosh Bhatt | JE | UDRP R&B Pauri | See Pic |
15. | 15-10-2016 | Ch-0/24 | SC sir for a visit | Ankur Kukreti | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
16. | 08-10-2016 | 3/19 | Sampling of G2 material | Deepak Goel | RE | DSC2 R&B WB Pauri | See Pic |
17. | 08-10-2016 | Field lab | Gradation test of G2 material | Deepak Goel | RE | DSC2 R&B WB Pauri | See Pic |
18. | 07-10-2016 | Field Lab | Gradation test of G2 | Ankur Kukreti | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
19. | 17-09-2016 | Ch 3/36 | Collection of G2 material | Deepak Goel | RE | DSC2 R&B WB Pauri | See Pic |
20. | 07-09-2016 | Ch-3/35-34 | Stacking of G-2 | Ankur Kukreti | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
|
|