Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Byaschatti Chheitur-Bhutnisi MR Work Completed
Project: UDRP-RB UID: 2134 Sanction Cost: 510.77  lakh Length: 12.000 KM.
District: Pauri Block: Kot Constituency: Pauri Circle: Tehri WB Circle
DEA: DEA Pauri DSC: Egis International DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 131        Package Name:  UDRP/PWD/06/67/RD/049(N)        Tender Date: 15-12-2016        Current Status: Agreement signed        Achieved on Date: 03-08-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/06/67/RD/049(N)      Contractor Name: Bharat Construction
Start Date:  10-08-2017      Intended Completion Date:  31-12-2018     
Total Bond Cost: 32395168.87 (323.95 lakh)        Variation Cost: 1995359.61 (19.95 lakh)    Hence Total Bond Cost is   34390528.48 (343.91 lakh) 
Sub Project Cost: 227.95  lakh        Variation Cost of Sub Project: 6757539.35  (67.58 lakh)       Total Sub Project Cost:   295.53 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence2.10 KM30.1619-09-201720-12-20182.10 KM2.10 KM10.5430.16
2.R/Wall, B/ Wall Type Protection works600.00 m76.3620-09-201731-01-2019600.00 m600.00 m26.6876.36
3.GSB/RBI/G-10.20 KM1.5305-01-201810-02-20180.20 KM0.20 KM0.541.53
4.G-20.20 KM1.1021-01-201825-02-20180.10 KM0.10 KM0.381.10
5.G-36.00 KM32.4806-02-201820-03-20185.00 KM5.00 KM11.3532.48
6.PC/CC i/c Prime Coat, Tack Coat8.20 KM89.8515-03-201815-06-20188.20 KM8.20 KM31.489.85
7.Cause Way3.00 No0.6715-08-201830-01-20193.00 No3.00 No0.240.67
8.Culverts/Scupper 3.00 No6.5425-10-201725-03-20183.00 No3.00 No2.296.54
9.longitudinal Drain9600.00 m7.5105-03-201810-06-20189600.00 m9600.00 m2.627.51
10.Crash Barrier400.00 m17.1820-12-201831-12-2018400.00 m400.00 m617.18
11.Parapet220.00 No5.8918-12-201831-12-2018220.00 No220.00 No2.065.89
12.Road Furniture117.00 No2.4002-02-201831-01-2019117.00 No117.00 No0.842.40
13.Other Allied Works & Finishing Work 1.00 Job14.5120-02-201831-12-20181.00 Job1.00 Job5.0714.51
Total Amount: 286.18 100   286.18
Remarks: No Remarks       Work Program Made On: 22-11-2017        Updation of work program on: 29-03-2019       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-October-20144.99  lakh
2.31-December-201439.35  lakh
3.31-March-201579.94  lakh
4.26-May-201527.83  lakh
5.30-September-20154.49  lakh
6.28-November-20151.00  lakh
Previous Package Expenditure Total 157.6  lakh
SNo. Date Payment
1.11-October-201729.06  lakh
2.30-December-20177.14  lakh
3.28-February-201810.30  lakh
4.09-May-201838.62  lakh
5.30-June-201879.47  lakh
6.10-August-201830.23  lakh
7.29-September-201826.57  lakh
8.18-January-201932.35  lakh
9.23-April-201915.70  lakh
10.10-June-201926.09  lakh
11.09-July-201916.03  lakh
Total 311.56  lakh
% Payment105.42 %
Advance Amount:  30.94  lakh        Recovered Amount:  30.94  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 203   No. of Test Done : 211    No. of Test Passed : 203   No. of Test Failed : 8   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 87.48
Number of Notice(s) issued: 2

Mobile Pic Upload

Number of Pics Available on Web Repository: 67
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.31-10-2018km 9 ch.8+600S.E & A.E Sir Site VisitAmit KumarJEUDRP R&B Pauri See Pic
2.31-10-2018km 10 ch.9+075S.E & A.E Sir Site VisitAmit KumarJEUDRP R&B Pauri See Pic
3.29-08-2018Km 10 ch.9+400SRMD Road Block Due to Debris Falled km 10Amit KumarJEUDRP R&B Pauri See Pic
4.21-08-2018Km 10 ch.9+150SRMD Road Block Due to Debris Falled km 10Amit KumarJEUDRP R&B Pauri See Pic
5.17-08-2018Km 10 ch.9+250Site clearance at km 10Amit KumarJEUDRP R&B Pauri See Pic
6.14-08-2018Km 2 ch.1+575SRMD Road Block Due to Debris Falled km 2Amit KumarJEUDRP R&B Pauri See Pic
7.14-08-2018Km 3 ch.2+600SRMD R /Wall DamageAmit KumarJEUDRP R&B Pauri See Pic
8.14-08-2018Km 4 ch.3+500SRMD Road Block Due to Debris Falled km 4Amit KumarJEUDRP R&B Pauri See Pic
9.14-08-2018Km 7 ch.6+175SRMD R/Wall DamageAmit KumarJEUDRP R&B Pauri See Pic
10.14-08-2018Km 7 ch.6+500SRMD Road Block Due to Debris Falled km 7Amit KumarJEUDRP R&B Pauri See Pic
11.14-08-2018Km 7 ch.6+550SRMD Road Block Due to Debris Falled km 7 ch.6+550Amit KumarJEUDRP R&B Pauri See Pic
12.14-08-2018Km 9 ch.8+600SRMD R/Wall DamageAmit KumarJEUDRP R&B Pauri See Pic
13.14-08-2018Km 9 ch.8+925SRMD R/Wall DamageAmit KumarJEUDRP R&B Pauri See Pic
14.14-08-2018Km 10 ch.9+125SRMD Road Block Due to Debris Falled km 10Amit KumarJEUDRP R&B Pauri See Pic
15.14-08-2018Km 10 ch.9+250SRMD Road Block Due to Debris Falled km 10Amit KumarJEUDRP R&B Pauri See Pic
16.05-08-20184+000SRMD Debris at ch 4+000 Heavy BoulderAmit KumarJEUDRP R&B Pauri See Pic
17.13-06-20180/3Progress of PC WorkAmit KumarJEUDRP R&B Pauri See Pic
18.27-05-20182+700SE visit during PCManoj BhattREDSC2 R&B WB Pauri See Pic
19.22-05-20187+125Rolling of PCManoj BhattREDSC2 R&B WB Pauri See Pic
20.13-05-20186/0Laying of PC & CompactionAmit KumarJEUDRP R&B Pauri See Pic