Byaschatti Chheitur-Bhutnisi MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
2134 |
Sanction Cost: |
510.77 lakh |
Length:
|
12.000 KM. |
District: |
Pauri |
Block: |
Kot |
Constituency: |
Pauri |
Circle: |
Tehri WB Circle |
DEA: |
DEA Pauri |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 131
Package Name: 
UDRP/PWD/06/67/RD/049(N)
Tender Date: 15-12-2016
Current Status: Agreement signed
Achieved on Date: 03-08-2017 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/06/67/RD/049(N)
Contractor Name: Bharat Construction
|
Start Date: 10-08-2017
Intended Completion Date: 31-12-2018
|
Total Bond Cost: 32395168.87 (323.95 lakh)
Variation Cost: 1995359.61 (19.95 lakh) Hence Total Bond Cost is 34390528.48 (343.91 lakh)
|
Sub Project Cost: 227.95 lakh
Variation Cost of Sub Project: 6757539.35 (67.58 lakh)
Total Sub Project Cost:
295.53 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 2.10 KM | 30.16 | 19-09-2017 | 20-12-2018 | 2.10 KM | 2.10 KM | 10.54 | 30.16 | 2. | R/Wall, B/ Wall Type Protection works | 600.00 m | 76.36 | 20-09-2017 | 31-01-2019 | 600.00 m | 600.00 m | 26.68 | 76.36 | 3. | GSB/RBI/G-1 | 0.20 KM | 1.53 | 05-01-2018 | 10-02-2018 | 0.20 KM | 0.20 KM | 0.54 | 1.53 | 4. | G-2 | 0.20 KM | 1.10 | 21-01-2018 | 25-02-2018 | 0.10 KM | 0.10 KM | 0.38 | 1.10 | 5. | G-3 | 6.00 KM | 32.48 | 06-02-2018 | 20-03-2018 | 5.00 KM | 5.00 KM | 11.35 | 32.48 | 6. | PC/CC i/c Prime Coat, Tack Coat | 8.20 KM | 89.85 | 15-03-2018 | 15-06-2018 | 8.20 KM | 8.20 KM | 31.4 | 89.85 | 7. | Cause Way | 3.00 No | 0.67 | 15-08-2018 | 30-01-2019 | 3.00 No | 3.00 No | 0.24 | 0.67 | 8. | Culverts/Scupper | 3.00 No | 6.54 | 25-10-2017 | 25-03-2018 | 3.00 No | 3.00 No | 2.29 | 6.54 | 9. | longitudinal Drain | 9600.00 m | 7.51 | 05-03-2018 | 10-06-2018 | 9600.00 m | 9600.00 m | 2.62 | 7.51 | 10. | Crash Barrier | 400.00 m | 17.18 | 20-12-2018 | 31-12-2018 | 400.00 m | 400.00 m | 6 | 17.18 | 11. | Parapet | 220.00 No | 5.89 | 18-12-2018 | 31-12-2018 | 220.00 No | 220.00 No | 2.06 | 5.89 | 12. | Road Furniture | 117.00 No | 2.40 | 02-02-2018 | 31-01-2019 | 117.00 No | 117.00 No | 0.84 | 2.40 | 13. | Other Allied Works & Finishing Work | 1.00 Job | 14.51 | 20-02-2018 | 31-12-2018 | 1.00 Job | 1.00 Job | 5.07 | 14.51 |
Total Amount: |
286.18 |
|
100 |
286.18 |
|
Remarks:
No Remarks
Work Program Made On:
22-11-2017 } ?>
Updation of work program on:
29-03-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-October-2014 | 4.99 lakh | 2. | 31-December-2014 | 39.35 lakh | 3. | 31-March-2015 | 79.94 lakh | 4. | 26-May-2015 | 27.83 lakh | 5. | 30-September-2015 | 4.49 lakh | 6. | 28-November-2015 | 1.00 lakh |
Previous Package Expenditure Total |
157.6 lakh |
SNo. |
Date |
Payment |
1. | 11-October-2017 | 29.06 lakh | 2. | 30-December-2017 | 7.14 lakh | 3. | 28-February-2018 | 10.30 lakh | 4. | 09-May-2018 | 38.62 lakh | 5. | 30-June-2018 | 79.47 lakh | 6. | 10-August-2018 | 30.23 lakh | 7. | 29-September-2018 | 26.57 lakh | 8. | 18-January-2019 | 32.35 lakh | 9. | 23-April-2019 | 15.70 lakh | 10. | 10-June-2019 | 26.09 lakh | 11. | 09-July-2019 | 16.03 lakh |
Total |
311.56 lakh |
% Payment | 105.42 % |
|
Advance Amount: 30.94 lakh
Recovered Amount: 30.94 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 203 No. of Test Done : 211 No. of Test Passed : 203 No. of Test Failed : 8 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 87.48 |
Number of Notice(s) issued: 2 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 67 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 31-10-2018 | km 9 ch.8+600 | S.E & A.E Sir Site Visit | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
2. | 31-10-2018 | km 10 ch.9+075 | S.E & A.E Sir Site Visit | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
3. | 29-08-2018 | Km 10 ch.9+400 | SRMD Road Block Due to Debris Falled km 10 | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
4. | 21-08-2018 | Km 10 ch.9+150 | SRMD Road Block Due to Debris Falled km 10 | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
5. | 17-08-2018 | Km 10 ch.9+250 | Site clearance at km 10 | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
6. | 14-08-2018 | Km 2 ch.1+575 | SRMD Road Block Due to Debris Falled km 2 | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
7. | 14-08-2018 | Km 3 ch.2+600 | SRMD R /Wall Damage | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
8. | 14-08-2018 | Km 4 ch.3+500 | SRMD Road Block Due to Debris Falled km 4 | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
9. | 14-08-2018 | Km 7 ch.6+175 | SRMD R/Wall Damage | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
10. | 14-08-2018 | Km 7 ch.6+500 | SRMD Road Block Due to Debris Falled km 7 | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
11. | 14-08-2018 | Km 7 ch.6+550 | SRMD Road Block Due to Debris Falled km 7 ch.6+550 | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
12. | 14-08-2018 | Km 9 ch.8+600 | SRMD R/Wall Damage | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
13. | 14-08-2018 | Km 9 ch.8+925 | SRMD R/Wall Damage | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
14. | 14-08-2018 | Km 10 ch.9+125 | SRMD Road Block Due to Debris Falled km 10 | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
15. | 14-08-2018 | Km 10 ch.9+250 | SRMD Road Block Due to Debris Falled km 10 | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
16. | 05-08-2018 | 4+000 | SRMD Debris at ch 4+000 Heavy Boulder | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
17. | 13-06-2018 | 0/3 | Progress of PC Work | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
18. | 27-05-2018 | 2+700 | SE visit during PC | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
19. | 22-05-2018 | 7+125 | Rolling of PC | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
20. | 13-05-2018 | 6/0 | Laying of PC & Compaction | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
|
|