Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Bunga Malla Motor Road Work Completed
Project: UDRP-RB UID: 2132 Sanction Cost: 179.99  lakh Length: 5.000 KM.
District: Pauri Block: Rikhnikhal Constituency: Lansdowne Circle: Tehri WB Circle
DEA: DEA Pauri DSC: Egis International DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 130        Package Name:  UDRP/PWD/06/70/RD/015(N)        Tender Date: 15-12-2016        Current Status: Agreement signed        Achieved on Date: 04-05-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/06/70/RD/015(N)      Contractor Name: R K Gupta Contractor
Start Date:  11-05-2017      Intended Completion Date:  15-06-2019      Original End Date:  10-08-2018
Total Bond Cost: 71282113.06 (712.82 lakh)        Variation Cost: -3164496.59 (-31.64 lakh)    Hence Total Bond Cost is   68117616.47 (681.18 lakh) 
Sub Project Cost: 215.07  lakh        Variation Cost of Sub Project: -5500053.84  (-55 lakh)       Total Sub Project Cost:   160.07 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 14078195 for 395 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.50 KM3.8315-06-201730-09-20180.50 KM0.50 KM2.43.83
2.R/Wall, B/ Wall Type Protection works623.00 m34.9010-06-201730-08-2018623.00 m623.00 m21.8434.90
3.GSB/RBI/G-11.00 KM6.6430-06-201710-09-20171.00 KM1.00 KM4.156.64
4.G-23.00 KM23.3501-07-201710-12-20173.00 KM3.00 KM14.6123.35
5.G-33.00 KM23.3815-08-201715-04-20183.00 KM3.00 KM14.6423.38
6.PC/CC i/c Prime Coat, Tack Coat3.00 KM30.6706-05-201825-10-20193.00 KM3.00 KM19.230.67
7.Culverts/Scupper 8.00 No15.9015-06-201730-08-20188.00 No8.00 No9.9515.90
8.longitudinal Drain3000.00 m0.9715-08-201715-09-20183000.00 m3000.00 m0.610.97
9.Crash Barrier100.00 m2.8015-12-201828-02-2019100.00 m100.00 m1.752.80
10.Parapet150.00 No4.1115-08-201830-03-2019150.00 No150.00 No2.574.11
11.Road Furniture47.00 No3.3801-02-201830-03-201947.00 No47.00 No2.123.38
12.Other Allied Works & Finishing Work 1.00 Job9.8615-06-201731-03-20191.00 Job1.00 Job6.179.86
Total Amount: 159.79 100   159.79
Remarks: No Remarks       Work Program Made On: 22-11-2017        Updation of work program on: 08-04-2019       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-September-20155.55  lakh
2.28-November-20150.50  lakh
Previous Package Expenditure Total 6.05  lakh
SNo. Date Payment
1.03-October-201714.64  lakh
2.30-November-201726.01  lakh
3.28-February-201822.32  lakh
4.13-April-201817.09  lakh
5.30-May-20188.26  lakh
6.30-June-201817.00  lakh
7.14-August-20180.58  lakh
8.22-October-201814.13  lakh
9.15-December-20188.15  lakh
10.30-January-20195.26  lakh
11.28-February-20192.59  lakh
12.30-March-201914.15  lakh
13.30-April-20191.65  lakh
14.31-May-20190.96  lakh
15.18-June-20196.46  lakh
16.29-June-20190.97  lakh
17.09-July-201910.20  lakh
Total 170.42  lakh
% Payment106.47 %
Advance Amount:  14.32  lakh        Recovered Amount:  14.32  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 399   No. of Test Done : 414    No. of Test Passed : 399   No. of Test Failed : 15   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 86.39
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 42
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.02-06-20182+650Spreading and screaning of WBM gr-3 in ProgressManoj BhattREDSC2 R&B WB Pauri See Pic
2.28-05-20180+250PC laying/rolling in progress.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
3.07-04-20180+270WBM G3 laying.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
4.25-03-2018Ch. 1/11Excavation of Cutcha DrainSagar KumarJEUDRP R&B Pauri See Pic
5.19-02-2018Ch. 0/9Air & Noise pollution TestingSagar KumarJEUDRP R&B Pauri See Pic
6.19-02-20180+200Air Quality Testing.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
7.13-12-2017Ch. 0/15Old R/wall damage due to RainfallSagar KumarJEUDRP R&B Pauri See Pic
8.09-12-2017Ch. 2/21G-2 layingSagar KumarJEUDRP R&B Pauri See Pic
9.18-11-2017Ch 0+200G-2 watering & compactionSagar KumarJEUDRP R&B Pauri See Pic
10.13-10-2017CH. 2/28Survey for Hill side cuttingSagar KumarJEUDRP R&B Pauri See Pic
11.05-10-2017Ch 1/20Rolling over WBM G2Ankur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
12.05-10-2017Ch 0/22Bed block of scupperAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
13.03-10-2017Ch 1/31Laying of WBM G2 is in progressAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
14.30-09-2017Ch 0/26Laying of WBM G2Ankur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
15.30-09-2017Ch 2/3R/Wall in progressAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
16.30-09-2017Ch 1/12Slip clearanceAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
17.30-09-2017Ch 0/0Slip clearanceAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
18.30-09-2017Ch 0/9Testing of gradation for WBM G1Ankur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
19.19-09-2017Ch 1/27Excavation of scupper in progressAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
20.15-09-2017Ch 1/11Slip due to heavy rainAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic