Bunga Malla Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
2132 |
Sanction Cost: |
179.99 lakh |
Length:
|
5.000 KM. |
District: |
Pauri |
Block: |
Rikhnikhal |
Constituency: |
Lansdowne |
Circle: |
Tehri WB Circle |
DEA: |
DEA Pauri |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 130
Package Name: 
UDRP/PWD/06/70/RD/015(N)
Tender Date: 15-12-2016
Current Status: Agreement signed
Achieved on Date: 04-05-2017 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/06/70/RD/015(N)
Contractor Name: R K Gupta Contractor
|
Start Date: 11-05-2017
Intended Completion Date: 15-06-2019
Original End Date: 10-08-2018 |
Total Bond Cost: 71282113.06 (712.82 lakh)
Variation Cost: -3164496.59 (-31.64 lakh) Hence Total Bond Cost is 68117616.47 (681.18 lakh)
|
Sub Project Cost: 215.07 lakh
Variation Cost of Sub Project: -5500053.84 (-55 lakh)
Total Sub Project Cost:
160.07 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 14078195 for 395 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.50 KM | 3.83 | 15-06-2017 | 30-09-2018 | 0.50 KM | 0.50 KM | 2.4 | 3.83 | 2. | R/Wall, B/ Wall Type Protection works | 623.00 m | 34.90 | 10-06-2017 | 30-08-2018 | 623.00 m | 623.00 m | 21.84 | 34.90 | 3. | GSB/RBI/G-1 | 1.00 KM | 6.64 | 30-06-2017 | 10-09-2017 | 1.00 KM | 1.00 KM | 4.15 | 6.64 | 4. | G-2 | 3.00 KM | 23.35 | 01-07-2017 | 10-12-2017 | 3.00 KM | 3.00 KM | 14.61 | 23.35 | 5. | G-3 | 3.00 KM | 23.38 | 15-08-2017 | 15-04-2018 | 3.00 KM | 3.00 KM | 14.64 | 23.38 | 6. | PC/CC i/c Prime Coat, Tack Coat | 3.00 KM | 30.67 | 06-05-2018 | 25-10-2019 | 3.00 KM | 3.00 KM | 19.2 | 30.67 | 7. | Culverts/Scupper | 8.00 No | 15.90 | 15-06-2017 | 30-08-2018 | 8.00 No | 8.00 No | 9.95 | 15.90 | 8. | longitudinal Drain | 3000.00 m | 0.97 | 15-08-2017 | 15-09-2018 | 3000.00 m | 3000.00 m | 0.61 | 0.97 | 9. | Crash Barrier | 100.00 m | 2.80 | 15-12-2018 | 28-02-2019 | 100.00 m | 100.00 m | 1.75 | 2.80 | 10. | Parapet | 150.00 No | 4.11 | 15-08-2018 | 30-03-2019 | 150.00 No | 150.00 No | 2.57 | 4.11 | 11. | Road Furniture | 47.00 No | 3.38 | 01-02-2018 | 30-03-2019 | 47.00 No | 47.00 No | 2.12 | 3.38 | 12. | Other Allied Works & Finishing Work | 1.00 Job | 9.86 | 15-06-2017 | 31-03-2019 | 1.00 Job | 1.00 Job | 6.17 | 9.86 |
Total Amount: |
159.79 |
|
100 |
159.79 |
|
Remarks:
No Remarks
Work Program Made On:
22-11-2017 } ?>
Updation of work program on:
08-04-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-September-2015 | 5.55 lakh | 2. | 28-November-2015 | 0.50 lakh |
Previous Package Expenditure Total |
6.05 lakh |
SNo. |
Date |
Payment |
1. | 03-October-2017 | 14.64 lakh | 2. | 30-November-2017 | 26.01 lakh | 3. | 28-February-2018 | 22.32 lakh | 4. | 13-April-2018 | 17.09 lakh | 5. | 30-May-2018 | 8.26 lakh | 6. | 30-June-2018 | 17.00 lakh | 7. | 14-August-2018 | 0.58 lakh | 8. | 22-October-2018 | 14.13 lakh | 9. | 15-December-2018 | 8.15 lakh | 10. | 30-January-2019 | 5.26 lakh | 11. | 28-February-2019 | 2.59 lakh | 12. | 30-March-2019 | 14.15 lakh | 13. | 30-April-2019 | 1.65 lakh | 14. | 31-May-2019 | 0.96 lakh | 15. | 18-June-2019 | 6.46 lakh | 16. | 29-June-2019 | 0.97 lakh | 17. | 09-July-2019 | 10.20 lakh |
Total |
170.42 lakh |
% Payment | 106.47 % |
|
Advance Amount: 14.32 lakh
Recovered Amount: 14.32 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 399 No. of Test Done : 414 No. of Test Passed : 399 No. of Test Failed : 15 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 86.39 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 42 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 02-06-2018 | 2+650 | Spreading and screaning of WBM gr-3 in Progress | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
2. | 28-05-2018 | 0+250 | PC laying/rolling in progress. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
3. | 07-04-2018 | 0+270 | WBM G3 laying. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
4. | 25-03-2018 | Ch. 1/11 | Excavation of Cutcha Drain | Sagar Kumar | JE | UDRP R&B Pauri | See Pic |
5. | 19-02-2018 | Ch. 0/9 | Air & Noise pollution Testing | Sagar Kumar | JE | UDRP R&B Pauri | See Pic |
6. | 19-02-2018 | 0+200 | Air Quality Testing. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
7. | 13-12-2017 | Ch. 0/15 | Old R/wall damage due to Rainfall | Sagar Kumar | JE | UDRP R&B Pauri | See Pic |
8. | 09-12-2017 | Ch. 2/21 | G-2 laying | Sagar Kumar | JE | UDRP R&B Pauri | See Pic |
9. | 18-11-2017 | Ch 0+200 | G-2 watering & compaction | Sagar Kumar | JE | UDRP R&B Pauri | See Pic |
10. | 13-10-2017 | CH. 2/28 | Survey for Hill side cutting | Sagar Kumar | JE | UDRP R&B Pauri | See Pic |
11. | 05-10-2017 | Ch 1/20 | Rolling over WBM G2 | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
12. | 05-10-2017 | Ch 0/22 | Bed block of scupper | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
13. | 03-10-2017 | Ch 1/31 | Laying of WBM G2 is in progress | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
14. | 30-09-2017 | Ch 0/26 | Laying of WBM G2 | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
15. | 30-09-2017 | Ch 2/3 | R/Wall in progress | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
16. | 30-09-2017 | Ch 1/12 | Slip clearance | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
17. | 30-09-2017 | Ch 0/0 | Slip clearance | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
18. | 30-09-2017 | Ch 0/9 | Testing of gradation for WBM G1 | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
19. | 19-09-2017 | Ch 1/27 | Excavation of scupper in progress | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
20. | 15-09-2017 | Ch 1/11 | Slip due to heavy rain | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
|
|