Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Arkani-Janasu-Khandukhal MR Work Completed
Project: UDRP-RB UID: 2120 Sanction Cost: 298.75  lakh Length: 5.200 KM.
District: Pauri Block: Kot Constituency: Pauri Circle: Tehri WB Circle
DEA: DEA Pauri DSC: Egis International DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 75        Package Name:  UDRP/PWD/06/69/RD/065        Tender Date: 20-11-2014        Current Status: Agreement signed        Achieved on Date: 16-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/06/69/RD/065      Contractor Name: Divya Jyoti Construction
Start Date:  22-06-2015      Intended Completion Date:  15-03-2017      Original End Date:  21-09-2016
Total Bond Cost: 57567580.74 (575.68 lakh)        Variation Cost: 1551277.99 (15.51 lakh)    Hence Total Bond Cost is   59118858.73 (591.19 lakh) 
Sub Project Cost: 237.40  lakh        Variation Cost of Sub Project: 3044507.82  (30.45 lakh)       Total Sub Project Cost:   267.85 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 374192 for 13 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence2.06 KM5.2817-08-201530-09-20152.06 KM2.06 KM1.955.28
2.R/Wall, B/ Wall Type Protection works930.00 m93.0301-07-201531-01-2017930.00 m930.00 m34.3993.03
3.GSB/RBI/G-10.38 KM3.9301-05-201615-05-20160.38 KM0.38 KM1.453.93
4.G-20.55 KM3.0501-05-201615-06-20160.55 KM0.55 KM1.133.05
5.G-31.09 KM6.4223-02-201620-06-20161.09 KM1.09 KM2.376.42
6.PC/CC i/c Prime Coat, Tack Coat5.20 KM96.5520-05-201615-03-20175.20 KM5.20 KM35.6996.55
7.Cause Way5.00 No17.1501-10-201528-02-20175.00 No5.00 No6.3417.15
8.Culverts/Scupper 10.00 No19.6117-08-201531-01-201610.00 No10.00 No7.2519.61
9.longitudinal Drain5058.00 m9.7302-01-201631-01-20175058.00 m5058.00 m3.69.73
10.Crash Barrier0.00 m0.0001-01-201701-01-20170.00 m0.00 m00.00
11.Parapet109.00 No2.3315-01-201630-11-2016109.00 No109.00 No0.862.33
12.Road Furniture54.00 No8.5001-08-201615-03-201754.00 No54.00 No3.148.50
13.Other Allied Works & Finishing Work 1.00 Job4.9401-08-201515-03-20171.00 Job1.00 Job1.824.94
Total Amount: 270.52 100   270.52
Remarks: No Remarks       Work Program Made On: 03-10-2015        Updation of work program on: 29-03-2019       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-November-201545.08  lakh
2.08-April-201656.08  lakh
3.13-May-201610.51  lakh
4.04-August-201689.63  lakh
5.01-September-201859.71  lakh
6.28-February-20199.50  lakh
Total 270.51  lakh
% Payment100.99 %
Advance Amount:  198.11  lakh        Recovered Amount:  198.11  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 207   No. of Test Done : 217    No. of Test Passed : 207   No. of Test Failed : 10   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.38
Number of Notice(s) issued: 1

Mobile Pic Upload

Number of Pics Available on Web Repository: 15
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.07-04-2017Ch-0/3-5,.ParapetPradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
2.07-04-2017Ch-0/0-3,Breast wall.Pradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
3.14-03-2017Billkedar townEMP implementation training by Environmental Expert of EgisDeepak GoelREDSC2 R&B WB Pauri See Pic
4.11-02-2017km-01;ch-5.175.pc work.Pradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
5.09-02-2017km-5;ch-4/20-21R/wall.Pradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
6.09-02-2017km-5;ch-4.500.R/wall.Pradeep Kumar PrabhakarSite SupervisorDSC2 R&B WB Pauri See Pic
7.06-02-2017Km-5, ch-4.525Banded r/wallHema MallJEUDRP R&B Pauri See Pic
8.06-02-2017Km-5 ch-4.475Banded r/wallHema MallJEUDRP R&B Pauri See Pic
9.06-02-2017Km-3 ch -2.300Banded R/wallHema MallJEUDRP R&B Pauri See Pic
10.06-02-2017Km-1, ch-1.750Pc workHema MallJEUDRP R&B Pauri See Pic
11.06-02-2017Arkani janashu khanukhal m/r,km-1, ch-0/6Pc work & b/wallHema MallJEUDRP R&B Pauri See Pic
12.06-02-2017Km-3 ch-2.950Banded R/wallHema MallJEUDRP R&B Pauri See Pic
13.04-02-2017Arkani janashu khandukhal m/r, km-1,ch-0/12Pc work & b/wallHema MallJEUDRP R&B Pauri See Pic
14.03-02-2017Km-1, ch-0/1Pc work & parapet & b/wallHema MallJEUDRP R&B Pauri See Pic
15.24-09-2016Ch 4/7Inspection of damaged causeway by SE, WB PWDDeepak GoelREDSC2 R&B WB Pauri See Pic