Arkani-Janasu-Khandukhal MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
2120 |
Sanction Cost: |
298.75 lakh |
Length:
|
5.200 KM. |
District: |
Pauri |
Block: |
Kot |
Constituency: |
Pauri |
Circle: |
Tehri WB Circle |
DEA: |
DEA Pauri |
DSC: |
Egis International |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 75
Package Name: 
UDRP/PWD/06/69/RD/065
Tender Date: 20-11-2014
Current Status: Agreement signed
Achieved on Date: 16-06-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/06/69/RD/065
Contractor Name: Divya Jyoti Construction
|
Start Date: 22-06-2015
Intended Completion Date: 15-03-2017
Original End Date: 21-09-2016 |
Total Bond Cost: 57567580.74 (575.68 lakh)
Variation Cost: 1551277.99 (15.51 lakh) Hence Total Bond Cost is 59118858.73 (591.19 lakh)
|
Sub Project Cost: 237.40 lakh
Variation Cost of Sub Project: 3044507.82 (30.45 lakh)
Total Sub Project Cost:
267.85 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 374192 for 13 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 2.06 KM | 5.28 | 17-08-2015 | 30-09-2015 | 2.06 KM | 2.06 KM | 1.95 | 5.28 | 2. | R/Wall, B/ Wall Type Protection works | 930.00 m | 93.03 | 01-07-2015 | 31-01-2017 | 930.00 m | 930.00 m | 34.39 | 93.03 | 3. | GSB/RBI/G-1 | 0.38 KM | 3.93 | 01-05-2016 | 15-05-2016 | 0.38 KM | 0.38 KM | 1.45 | 3.93 | 4. | G-2 | 0.55 KM | 3.05 | 01-05-2016 | 15-06-2016 | 0.55 KM | 0.55 KM | 1.13 | 3.05 | 5. | G-3 | 1.09 KM | 6.42 | 23-02-2016 | 20-06-2016 | 1.09 KM | 1.09 KM | 2.37 | 6.42 | 6. | PC/CC i/c Prime Coat, Tack Coat | 5.20 KM | 96.55 | 20-05-2016 | 15-03-2017 | 5.20 KM | 5.20 KM | 35.69 | 96.55 | 7. | Cause Way | 5.00 No | 17.15 | 01-10-2015 | 28-02-2017 | 5.00 No | 5.00 No | 6.34 | 17.15 | 8. | Culverts/Scupper | 10.00 No | 19.61 | 17-08-2015 | 31-01-2016 | 10.00 No | 10.00 No | 7.25 | 19.61 | 9. | longitudinal Drain | 5058.00 m | 9.73 | 02-01-2016 | 31-01-2017 | 5058.00 m | 5058.00 m | 3.6 | 9.73 | 10. | Crash Barrier | 0.00 m | 0.00 | 01-01-2017 | 01-01-2017 | 0.00 m | 0.00 m | 0 | 0.00 | 11. | Parapet | 109.00 No | 2.33 | 15-01-2016 | 30-11-2016 | 109.00 No | 109.00 No | 0.86 | 2.33 | 12. | Road Furniture | 54.00 No | 8.50 | 01-08-2016 | 15-03-2017 | 54.00 No | 54.00 No | 3.14 | 8.50 | 13. | Other Allied Works & Finishing Work | 1.00 Job | 4.94 | 01-08-2015 | 15-03-2017 | 1.00 Job | 1.00 Job | 1.82 | 4.94 |
Total Amount: |
270.52 |
|
100 |
270.52 |
|
Remarks:
No Remarks
Work Program Made On:
03-10-2015 } ?>
Updation of work program on:
29-03-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 28-November-2015 | 45.08 lakh | 2. | 08-April-2016 | 56.08 lakh | 3. | 13-May-2016 | 10.51 lakh | 4. | 04-August-2016 | 89.63 lakh | 5. | 01-September-2018 | 59.71 lakh | 6. | 28-February-2019 | 9.50 lakh |
Total |
270.51 lakh |
% Payment | 100.99 % |
|
Advance Amount: 198.11 lakh
Recovered Amount: 198.11 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 207 No. of Test Done : 217 No. of Test Passed : 207 No. of Test Failed : 10 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 89.38 |
Number of Notice(s) issued: 1 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 15 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 07-04-2017 | Ch-0/3-5, | .Parapet | Pradeep Kumar Prabhakar | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
2. | 07-04-2017 | Ch-0/0-3, | Breast wall. | Pradeep Kumar Prabhakar | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
3. | 14-03-2017 | Billkedar town | EMP implementation training by Environmental Expert of Egis | Deepak Goel | RE | DSC2 R&B WB Pauri | See Pic |
4. | 11-02-2017 | km-01;ch-5.175. | pc work. | Pradeep Kumar Prabhakar | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
5. | 09-02-2017 | km-5;ch-4/20-21 | R/wall. | Pradeep Kumar Prabhakar | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
6. | 09-02-2017 | km-5;ch-4.500. | R/wall. | Pradeep Kumar Prabhakar | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
7. | 06-02-2017 | Km-5, ch-4.525 | Banded r/wall | Hema Mall | JE | UDRP R&B Pauri | See Pic |
8. | 06-02-2017 | Km-5 ch-4.475 | Banded r/wall | Hema Mall | JE | UDRP R&B Pauri | See Pic |
9. | 06-02-2017 | Km-3 ch -2.300 | Banded R/wall | Hema Mall | JE | UDRP R&B Pauri | See Pic |
10. | 06-02-2017 | Km-1, ch-1.750 | Pc work | Hema Mall | JE | UDRP R&B Pauri | See Pic |
11. | 06-02-2017 | Arkani janashu khanukhal m/r,km-1, ch-0/6 | Pc work & b/wall | Hema Mall | JE | UDRP R&B Pauri | See Pic |
12. | 06-02-2017 | Km-3 ch-2.950 | Banded R/wall | Hema Mall | JE | UDRP R&B Pauri | See Pic |
13. | 04-02-2017 | Arkani janashu khandukhal m/r, km-1,ch-0/12 | Pc work & b/wall | Hema Mall | JE | UDRP R&B Pauri | See Pic |
14. | 03-02-2017 | Km-1, ch-0/1 | Pc work & parapet & b/wall | Hema Mall | JE | UDRP R&B Pauri | See Pic |
15. | 24-09-2016 | Ch 4/7 | Inspection of damaged causeway by SE, WB PWD | Deepak Goel | RE | DSC2 R&B WB Pauri | See Pic |
|
|