Kotdwar-Pulinda motor road
Work Completed
|
Project: |
UDRP-RB |
UID: |
2108 |
Sanction Cost: |
152.03 lakh |
Length:
|
12.000 KM. |
District: |
Pauri |
Block: |
Dogadda |
Constituency: |
Kotdwar |
Circle: |
Tehri WB Circle |
DEA: |
DEA Pauri |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
Type: |
ODR |
|
Procurement: |
Package No.: 132
Package Name: 
UDRP/PWD/06/67/RD/050(N)
Tender Date: 15-12-2016
Current Status: Agreement signed
Achieved on Date: 04-05-2017 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/06/67/RD/050(N)
Contractor Name: SRS Promoters
|
Start Date: 11-05-2017
Intended Completion Date: 31-12-2018
Original End Date: 10-02-2018 |
Total Bond Cost: 28432575.93 (284.33 lakh)
Variation Cost: -1882561.99 (-18.83 lakh) Hence Total Bond Cost is 26550013.94 (265.5 lakh)
|
Sub Project Cost: 82.73 lakh
Variation Cost of Sub Project: -2326413.08 (-23.26 lakh)
Total Sub Project Cost:
59.47 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.32 KM | 0.72 | 15-05-2017 | 15-08-2018 | 0.50 KM | 0.50 KM | 0.9 | 0.72 | 2. | R/Wall, B/ Wall Type Protection works | 141.00 m | 17.60 | 15-05-2017 | 30-11-2018 | 125.00 m | 125.00 m | 21.88 | 17.60 | 3. | G-3 | 1.44 KM | 9.81 | 15-08-2018 | 15-09-2018 | 1.50 KM | 1.50 KM | 12.19 | 9.81 | 4. | PC/CC i/c Prime Coat, Tack Coat | 2.75 KM | 25.53 | 15-09-2018 | 30-10-2018 | 2.75 KM | 2.75 KM | 31.73 | 25.53 | 5. | Culverts/Scupper | 3.00 No | 4.97 | 15-06-2017 | 15-09-2018 | 2.00 No | 2.00 No | 6.18 | 4.97 | 6. | longitudinal Drain | 3.79 m | 3.93 | 30-08-2018 | 25-12-2018 | 2000.00 m | 2000.00 m | 4.88 | 3.93 | 7. | Parapet | 220.00 No | 5.68 | 30-08-2018 | 30-09-2018 | 164.00 No | 164.00 No | 7.06 | 5.68 | 8. | Road Furniture | 10.00 No | 0.40 | 10-04-2018 | 15-12-2018 | 10.00 No | 10.00 No | 0.5 | 0.40 | 9. | Other Allied Works & Finishing Work | 1.00 Job | 11.82 | 15-05-2017 | 20-12-2018 | 1.00 Job | 1.00 Job | 14.69 | 11.82 |
Total Amount: |
80.46 |
|
100 |
80.46 |
|
Remarks:
No Remarks
Work Program Made On:
18-11-2017 } ?>
Updation of work program on:
17-11-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
Previous Package Expenditure Total |
0 lakh |
SNo. |
Date |
Payment |
1. | 17-August-2017 | 8.34 lakh | 2. | 30-November-2017 | 3.10 lakh | 3. | 28-April-2018 | 1.95 lakh | 4. | 22-October-2018 | 15.77 lakh | 5. | 15-December-2018 | 15.66 lakh | 6. | 08-July-2019 | 5.81 lakh | 7. | 09-July-2019 | 1.84 lakh |
Total |
52.47 lakh |
% Payment | 88.23 % |
|
Advance Amount: 67.52 lakh
Recovered Amount: 67.52 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 222 No. of Test Done : 230 No. of Test Passed : 222 No. of Test Failed : 8 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 86.71 |
Number of Notice(s) issued: 1 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 31 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 15-08-2018 | Km 2 ch.1+350 | SRMD Road Block Due to Debris Falled km 2 | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
2. | 15-08-2018 | Km 3 ch.2+625 | SRMD Road Block Due to Debris Falled km 3 | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
3. | 15-08-2018 | Km 3 ch.2+575 | SRMD R/Wall Damage | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
4. | 15-08-2018 | Km 2 ch.1+550 | SRMD Road Block Due to Debris Falled km 2 | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
5. | 12-04-2018 | Ch 20+525 | SE Sir inspectuon | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
6. | 07-04-2018 | 5/3 | Health cheakup for labour camp.... | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
7. | 07-04-2018 | 5/3 | Health chackup camp for labour....... | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
8. | 04-12-2017 | 5+300 | Environmentall management training with environment expert of egis india and contractor.... | Noshad Qureshi | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
9. | 04-12-2017 | 0+ 700 | Clearance of land slides..... | Noshad Qureshi | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
10. | 10-11-2017 | 8+900 | Discussion with environmental expert.... | Noshad Qureshi | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
11. | 10-11-2017 | 8+075 | Discussion with environment expert on safety arrangements..... | Noshad Qureshi | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
12. | 07-04-2016 | 20+450 scupper slab M25 concrete | 1M span scupper slab casting | Sagar Kumar | JE | UDRP R&B Pauri | See Pic |
13. | 01-04-2016 | 20+450 | Scupper reinforcement in progress | Sagar Kumar | JE | UDRP R&B Pauri | See Pic |
14. | 01-04-2016 | 17+980 | Scupper stone masonry complete | Sagar Kumar | JE | UDRP R&B Pauri | See Pic |
15. | 04-03-2016 | 20+450 | Scupper excavation | Sagar Kumar | JE | UDRP R&B Pauri | See Pic |
16. | 25-02-2016 | Ch. 18+430 | Catchpit cleaning | Sagar Kumar | JE | UDRP R&B Pauri | See Pic |
17. | 19-01-2016 | 20+750 | Site visit A.E. PK Chamoli sir (wb pauri), dadamandi-madanpur & kotdwar Pulinda MR | Sagar Kumar | JE | UDRP R&B Pauri | See Pic |
18. | 29-12-2015 | 18+600 | B/wall | Umesh Mishra | Site superviser | DEA WB Pauri | See Pic |
19. | 29-12-2015 | Ch17+750 | R/wall | Umesh Mishra | Site superviser | DEA WB Pauri | See Pic |
20. | 29-12-2015 | 18+550 | R/wall | Umesh Mishra | Site superviser | DEA WB Pauri | See Pic |
|
|