Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Kotdwar-Pulinda motor road Work Completed
Project: UDRP-RB UID: 2108 Sanction Cost: 152.03  lakh Length: 12.000 KM.
District: Pauri Block: Dogadda Constituency: Kotdwar Circle: Tehri WB Circle
DEA: DEA Pauri DSC: Egis International DSC Scope: only Supervision Type: ODR
Procurement:
Package No.: 132        Package Name:  UDRP/PWD/06/67/RD/050(N)        Tender Date: 15-12-2016        Current Status: Agreement signed        Achieved on Date: 04-05-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/06/67/RD/050(N)      Contractor Name: SRS Promoters
Start Date:  11-05-2017      Intended Completion Date:  31-12-2018      Original End Date:  10-02-2018
Total Bond Cost: 28432575.93 (284.33 lakh)        Variation Cost: -1882561.99 (-18.83 lakh)    Hence Total Bond Cost is   26550013.94 (265.5 lakh) 
Sub Project Cost: 82.73  lakh        Variation Cost of Sub Project: -2326413.08  (-23.26 lakh)       Total Sub Project Cost:   59.47 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.32 KM0.7215-05-201715-08-20180.50 KM0.50 KM0.90.72
2.R/Wall, B/ Wall Type Protection works141.00 m17.6015-05-201730-11-2018125.00 m125.00 m21.8817.60
3.G-31.44 KM9.8115-08-201815-09-20181.50 KM1.50 KM12.199.81
4.PC/CC i/c Prime Coat, Tack Coat2.75 KM25.5315-09-201830-10-20182.75 KM2.75 KM31.7325.53
5.Culverts/Scupper 3.00 No4.9715-06-201715-09-20182.00 No2.00 No6.184.97
6.longitudinal Drain3.79 m3.9330-08-201825-12-20182000.00 m2000.00 m4.883.93
7.Parapet220.00 No5.6830-08-201830-09-2018164.00 No164.00 No7.065.68
8.Road Furniture10.00 No0.4010-04-201815-12-201810.00 No10.00 No0.50.40
9.Other Allied Works & Finishing Work 1.00 Job11.8215-05-201720-12-20181.00 Job1.00 Job14.6911.82
Total Amount: 80.46 100   80.46
Remarks: No Remarks       Work Program Made On: 18-11-2017        Updation of work program on: 17-11-2018       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
Previous Package Expenditure Total 0  lakh
SNo. Date Payment
1.17-August-20178.34  lakh
2.30-November-20173.10  lakh
3.28-April-20181.95  lakh
4.22-October-201815.77  lakh
5.15-December-201815.66  lakh
6.08-July-20195.81  lakh
7.09-July-20191.84  lakh
Total 52.47  lakh
% Payment88.23 %
Advance Amount:  67.52  lakh        Recovered Amount:  67.52  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 222   No. of Test Done : 230    No. of Test Passed : 222   No. of Test Failed : 8   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 86.71
Number of Notice(s) issued: 1

Mobile Pic Upload

Number of Pics Available on Web Repository: 31
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.15-08-2018Km 2 ch.1+350SRMD Road Block Due to Debris Falled km 2Amit KumarJEUDRP R&B Pauri See Pic
2.15-08-2018Km 3 ch.2+625SRMD Road Block Due to Debris Falled km 3Amit KumarJEUDRP R&B Pauri See Pic
3.15-08-2018Km 3 ch.2+575SRMD R/Wall DamageAmit KumarJEUDRP R&B Pauri See Pic
4.15-08-2018Km 2 ch.1+550SRMD Road Block Due to Debris Falled km 2Amit KumarJEUDRP R&B Pauri See Pic
5.12-04-2018Ch 20+525SE Sir inspectuonAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
6.07-04-20185/3Health cheakup for labour camp....Amit KumarJEUDRP R&B Pauri See Pic
7.07-04-20185/3Health chackup camp for labour.......Amit KumarJEUDRP R&B Pauri See Pic
8.04-12-20175+300Environmentall management training with environment expert of egis india and contractor....Noshad QureshiSite SupervisorDSC2 R&B WB Pauri See Pic
9.04-12-20170+ 700Clearance of land slides.....Noshad QureshiSite SupervisorDSC2 R&B WB Pauri See Pic
10.10-11-20178+900Discussion with environmental expert....Noshad QureshiSite SupervisorDSC2 R&B WB Pauri See Pic
11.10-11-20178+075Discussion with environment expert on safety arrangements.....Noshad QureshiSite SupervisorDSC2 R&B WB Pauri See Pic
12.07-04-201620+450 scupper slab M25 concrete1M span scupper slab castingSagar KumarJEUDRP R&B Pauri See Pic
13.01-04-201620+450Scupper reinforcement in progressSagar KumarJEUDRP R&B Pauri See Pic
14.01-04-201617+980Scupper stone masonry completeSagar KumarJEUDRP R&B Pauri See Pic
15.04-03-201620+450Scupper excavationSagar KumarJEUDRP R&B Pauri See Pic
16.25-02-2016Ch. 18+430Catchpit cleaningSagar KumarJEUDRP R&B Pauri See Pic
17.19-01-201620+750Site visit A.E. PK Chamoli sir (wb pauri), dadamandi-madanpur & kotdwar Pulinda MRSagar KumarJEUDRP R&B Pauri See Pic
18.29-12-201518+600B/wallUmesh MishraSite superviserDEA WB Pauri See Pic
19.29-12-2015Ch17+750R/wallUmesh MishraSite superviserDEA WB Pauri See Pic
20.29-12-201518+550R/wallUmesh MishraSite superviserDEA WB Pauri See Pic