Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Talla Ramgarh Ratighat MR Work Completed
Project: UDRP-RB UID: 2039 Sanction Cost: 271.08  lakh Length: 8.000 KM.
District: Nainital Block: Ramgarh Constituency: Bhimtal Circle: Pithoragarh WB Circle
DEA: DEA Nanital DSC: Royal Haskoning DHV DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 53        Package Name:  UDRP/PWD/10/12/RD/053        Tender Date: 24-12-2014        Current Status: Agreement signed        Achieved on Date: 21-05-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/10/12/RD/053      Contractor Name: Jeena Enterprises
Start Date:  27-05-2015      Intended Completion Date:  26-08-2016     
Total Bond Cost: 18257078.51 (182.57 lakh)        Variation Cost: 6881701.48 (68.82 lakh)    Hence Total Bond Cost is   25138779.99 (251.39 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.23 KM5.0907-05-201615-08-20160.23 KM0.23 KM2.035.09
2.R/Wall, B/ Wall Type Protection works797.00 m87.9815-06-201515-08-2016797.00 m797.00 m3587.98
3.GSB/RBI/G-10.53 KM4.0601-10-201531-05-20160.53 KM0.53 KM1.614.06
4.G-20.53 KM3.0201-10-201531-05-20160.53 KM0.53 KM1.23.02
5.G-31.14 KM6.8601-10-201531-05-20161.14 KM1.14 KM2.736.86
6.PC/CC i/c Prime Coat, Tack Coat8.00 KM94.1801-09-201515-06-20168.00 KM8.00 KM37.4694.18
7.Cause Way3.00 No3.2515-08-201531-01-20163.00 No3.00 No1.293.25
8.longitudinal Drain8000.00 m21.0701-12-201530-04-20168000.00 m8000.00 m8.3821.07
9.Crash Barrier400.00 m9.7201-09-201530-11-2015400.00 m400.00 m3.879.72
10.Parapet500.00 No10.1101-10-201531-12-2015500.00 No500.00 No4.0210.11
11.Road Furniture63.00 No1.0201-07-201615-08-201663.00 No63.00 No0.411.02
12.Other Allied Works & Finishing Work 4.00 Job5.0201-07-201620-08-20164.00 Job4.00 Job25.02
Total Amount: 251.38 100   251.38
Remarks: No Remarks       Work Program Made On: 08-10-2015        Updation of work program on: 25-09-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.09-July-20158.46  lakh
2.05-August-201516.25  lakh
3.31-August-20159.28  lakh
4.30-September-201540.31  lakh
5.01-October-201511.09  lakh
6.07-November-201529.37  lakh
7.30-November-20154.92  lakh
8.31-December-20154.44  lakh
9.30-January-20162.66  lakh
10.29-February-20162.13  lakh
11.31-March-20163.02  lakh
12.22-April-20166.27  lakh
13.11-May-201616.06  lakh
14.31-May-201629.14  lakh
15.24-June-201629.35  lakh
16.29-August-20164.71  lakh
17.25-October-201632.53  lakh
Total 249.99  lakh
% Payment 99.44 %
Advance Amount:  18.25  lakh        Recovered Amount:  18.25  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 137   No. of Test Done : 137    No. of Test Passed : 131   No. of Test Failed : 6   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.14
Number of Notice(s) issued: 80

Mobile Pic Upload

Number of Pics Available on Web Repository: 63
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.21-05-20168+000World Bank VisitAlok Singh BaghelMIS ExpertDSC5 R&B WB See Pic
2.21-05-20162+500Debris DisposalAlok Singh BaghelMIS ExpertDSC5 R&B WB See Pic
3.21-05-20162+650World Bank VisitAlok Singh BaghelMIS ExpertDSC5 R&B WB See Pic
4.21-05-20162+500World Bank VisitAlok Singh BaghelMIS ExpertDSC5 R&B WB See Pic
5.21-05-20160+000World Bank VisitAlok Singh BaghelMIS ExpertDSC5 R&B WB See Pic
6.04-05-20162+300Hill cuttingrDharmendra Kumar SinghREDSC5 R&B WB Nainital See Pic
7.30-04-20162+300Hill cuttingAshvani KumarJEUDRP R&B Nainital See Pic
8.13-04-20162+600Profile correction by wbmDharmendra Kumar SinghREDSC5 R&B WB Nainital See Pic
9.14-03-20166+500Land slide clearanceDharmendra Kumar SinghREDSC5 R&B WB Nainital See Pic
10.14-03-20166+500Land slideDharmendra Kumar SinghREDSC5 R&B WB Nainital See Pic
11.02-03-2016Ch 3+100Topo surveyAshvani KumarJEUDRP R&B Nainital See Pic
12.29-02-20160+725Topo surveyNaseem AnsariSite SupervisorDSC5 R&B WB Nainital See Pic
13.29-02-20160+200Topo surveyNaseem AnsariSite SupervisorDSC5 R&B WB Nainital See Pic
14.26-02-20163+100Top pucca of. B/wDharmendra Kumar SinghREDSC5 R&B WB Nainital See Pic
15.26-02-20162+300E.e& to site visitDharmendra Kumar SinghREDSC5 R&B WB Nainital See Pic
16.26-02-20161+650Putcca drainDharmendra Kumar SinghREDSC5 R&B WB Nainital See Pic
17.08-02-20165+080C/PNaseem AnsariSite SupervisorDSC5 R&B WB Nainital See Pic
18.08-02-20162+200Transit walk for variationNaseem AnsariSite SupervisorDSC5 R&B WB Nainital See Pic
19.24-12-20150+600CausewayAshvani KumarJEUDRP R&B Nainital See Pic
20.04-11-20152+800K.C DrainAkash ChoudharyJEUDRP R&B Nainital See Pic