Raipur link road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1818 |
Sanction Cost: |
266.56 lakh |
Length:
|
1.200 KM. |
District: |
Haridwar |
Block: |
Bhagwanpur |
Constituency: |
Bhagwanpur |
Circle: |
Tehri WB Circle |
DEA: |
DEA Chakrata |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 56
Package Name: 
UDRP/PWD/1/3/59/RD/006b
Tender Date: 03-05-2014
Current Status: Agreement signed
Achieved on Date: 25-08-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/1/3/59/RD/006b
Contractor Name: Link Enterprises
|
Start Date: 01-09-2014
Intended Completion Date: 31-12-2015
|
Total Bond Cost: 25287112.5 (252.87 lakh)
Variation Cost: 4847628.80 (48.48 lakh) Hence Total Bond Cost is 30134741.3 (301.35 lakh)
|
Sub Project Cost: 204.00 lakh
Variation Cost of Sub Project: 6053434.18 (60.53 lakh)
Total Sub Project Cost:
264.53 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 986232 for 78 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.10 KM | 7.33 | 16-10-2014 | 31-12-2014 | 1.10 KM | 1.10 KM | 3 | 7.33 | 2. | GSB/RBI/G-1 | 1.20 KM | 16.61 | 01-12-2014 | 10-05-2015 | 1.20 KM | 1.20 KM | 6.78 | 16.61 | 3. | PC/CC i/c Prime Coat, Tack Coat | 1.20 KM | 217.24 | 05-02-2015 | 30-06-2015 | 1.20 KM | 1.20 KM | 88.73 | 217.24 | 4. | longitudinal Drain | 100.00 m | 3.49 | 15-06-2015 | 05-07-2015 | 100.00 m | 100.00 m | 1.43 | 3.49 | 5. | Road Furniture | 2.00 No | 0.16 | 10-03-2015 | 10-05-2015 | 2.00 No | 2.00 No | 0.07 | 0.16 |
Total Amount: |
244.83 |
|
100 |
244.83 |
|
Remarks:
No Remarks
Work Program Made On:
15-11-2014 } ?>
Updation of work program on:
22-07-2016
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 23-April-2015 | 21.75 lakh | 2. | 30-May-2015 | 11.97 lakh | 3. | 25-June-2015 | 34.55 lakh | 4. | 16-July-2015 | 35.07 lakh | 5. | 11-August-2015 | 38.85 lakh | 6. | 22-September-2015 | 41.43 lakh | 7. | 30-September-2015 | 28.10 lakh | 8. | 06-November-2015 | 12.16 lakh | 9. | 22-December-2015 | 9.84 lakh | 10. | 30-January-2016 | 6.76 lakh | 11. | 27-July-2016 | 17.44 lakh | 12. | 06-November-2016 | -2.96 lakh |
Total |
254.96 lakh |
% Payment | 96.38 % |
|
Advance Amount: 25.28 lakh
Recovered Amount: 25.28 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 273 No. of Test Done : 274 No. of Test Passed : 273 No. of Test Failed : 1 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.55 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 15 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 04-10-2016 | Ch 0/14-0/16 | Core cutting of raipur link road | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
2. | 04-10-2016 | Ch 0/7 | Inspection of raipur link road after completion | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
3. | 06-08-2015 | Ch. 0.370 | Expansion/ Construction joint in CC Road | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
4. | 21-07-2015 | Km1 hm1 | Camber checking | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
5. | 24-06-2015 | Ch. 0.300km | C. C pavement under progress | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
6. | 12-06-2015 | Km1 near akona engineering Co. | Cc road under construction | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
7. | 31-05-2015 | Ch. - 0.850 | CC work in Raipur link Road at Roorkee, Bhagwanpur | D S Tomar | JE | DEA WB Chakrata | See Pic |
8. | 31-05-2015 | Ch 0.825 | C C in Raipur Link Road | D S Tomar | JE | DEA WB Chakrata | See Pic |
9. | 18-05-2015 | Km1 raipur link rd | DLC concrete under progress | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
10. | 06-05-2015 | End of km 1 near unisef cable industry | Compaction of gsb | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
11. | 05-05-2015 | Ch 8.025 | GSB in Raipur M/R | D S Tomar | JE | DEA WB Chakrata | See Pic |
12. | 19-04-2015 | Km1 dense industrial area | Test conducted to find out the percentage of clay in Gsb. | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
13. | 29-03-2015 | Km o.450 Raipur Rd industrial estate. | sprinkling of water for consolidation of GSB work | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
14. | 25-03-2015 | Km o.450 Raipur Rd industrial estate. | sprinkling of water for consolidation of GSB work | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
15. | 25-03-2015 | Km1 raipur | GSB in progress | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
|
|