Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Raipur link road Work Completed
Project: UDRP-RB UID: 1818 Sanction Cost: 266.56  lakh Length: 1.200 KM.
District: Haridwar Block: Bhagwanpur Constituency: Bhagwanpur Circle: Tehri WB Circle
DEA: DEA Chakrata DSC: Egis International DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 56        Package Name:  UDRP/PWD/1/3/59/RD/006b        Tender Date: 03-05-2014        Current Status: Agreement signed        Achieved on Date: 25-08-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/1/3/59/RD/006b      Contractor Name: Link Enterprises
Start Date:  01-09-2014      Intended Completion Date:  31-12-2015     
Total Bond Cost: 25287112.5 (252.87 lakh)        Variation Cost: 4847628.80 (48.48 lakh)    Hence Total Bond Cost is   30134741.3 (301.35 lakh) 
Sub Project Cost: 204.00  lakh        Variation Cost of Sub Project: 6053434.18  (60.53 lakh)       Total Sub Project Cost:   264.53 lakh
LD Analysis for Milestone1: calculated LD is Rs 986232 for 78 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.10 KM7.3316-10-201431-12-20141.10 KM1.10 KM37.33
2.GSB/RBI/G-11.20 KM16.6101-12-201410-05-20151.20 KM1.20 KM6.7816.61
3.PC/CC i/c Prime Coat, Tack Coat1.20 KM217.2405-02-201530-06-20151.20 KM1.20 KM88.73217.24
4.longitudinal Drain100.00 m3.4915-06-201505-07-2015100.00 m100.00 m1.433.49
5.Road Furniture2.00 No0.1610-03-201510-05-20152.00 No2.00 No0.070.16
Total Amount: 244.83 100   244.83
Remarks: No Remarks       Work Program Made On: 15-11-2014        Updation of work program on: 22-07-2016       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.23-April-201521.75  lakh
2.30-May-201511.97  lakh
3.25-June-201534.55  lakh
4.16-July-201535.07  lakh
5.11-August-201538.85  lakh
6.22-September-201541.43  lakh
7.30-September-201528.10  lakh
8.06-November-201512.16  lakh
9.22-December-20159.84  lakh
10.30-January-20166.76  lakh
11.27-July-201617.44  lakh
12.06-November-2016-2.96  lakh
Total 254.96  lakh
% Payment96.38 %
Advance Amount:  25.28  lakh        Recovered Amount:  25.28  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 273   No. of Test Done : 274    No. of Test Passed : 273   No. of Test Failed : 1   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.55
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 15
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.04-10-2016Ch 0/14-0/16Core cutting of raipur link roadDhwajvir SinghJEUDRP R&B Chakrata See Pic
2.04-10-2016Ch 0/7Inspection of raipur link road after completionDhwajvir SinghJEUDRP R&B Chakrata See Pic
3.06-08-2015Ch. 0.370Expansion/ Construction joint in CC RoadDhwajvir SinghJEUDRP R&B Chakrata See Pic
4.21-07-2015Km1 hm1Camber checkingLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
5.24-06-2015Ch. 0.300kmC. C pavement under progressLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
6.12-06-2015Km1 near akona engineering Co.Cc road under constructionLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
7.31-05-2015Ch. - 0.850CC work in Raipur link Road at Roorkee, BhagwanpurD S TomarJEDEA WB Chakrata See Pic
8.31-05-2015Ch 0.825C C in Raipur Link RoadD S TomarJEDEA WB Chakrata See Pic
9.18-05-2015Km1 raipur link rdDLC concrete under progressLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
10.06-05-2015End of km 1 near unisef cable industryCompaction of gsbLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
11.05-05-2015Ch 8.025GSB in Raipur M/RD S TomarJEDEA WB Chakrata See Pic
12.19-04-2015Km1 dense industrial areaTest conducted to find out the percentage of clay in Gsb.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
13.29-03-2015Km o.450 Raipur Rd industrial estate.sprinkling of water for consolidation of GSB workLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
14.25-03-2015Km o.450 Raipur Rd industrial estate.sprinkling of water for consolidation of GSB workLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
15.25-03-2015Km1 raipurGSB in progressLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic