Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Mundlana to Harjoli jatt road Work Completed
Project: UDRP-RB UID: 1795 Sanction Cost: 21.04  lakh Length: 0.580 KM.
District: Haridwar Block: Narsan Constituency: Manglore Circle: Tehri WB Circle
DEA: DEA Chakrata DSC: Egis International DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 6        Package Name:  UDRP/PWD/13/59/RD/006        Tender Date: 03-05-2014        Current Status: Agreement signed        Achieved on Date: 18-10-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/13/59/RD/006      Contractor Name: satyam infratech
Start Date:  24-10-2014      Intended Completion Date:  31-05-2017      Original End Date:  23-01-2016
Total Bond Cost: 22693440.98 (226.93 lakh)        Variation Cost: 4475896.62 (44.76 lakh)    Hence Total Bond Cost is   27169337.6 (271.69 lakh) 
Sub Project Cost: 30.00  lakh        Variation Cost of Sub Project: -872508.58  (-8.73 lakh)       Total Sub Project Cost:   21.27 lakh
LD Analysis for Milestone1: calculated LD is Rs 45388 for 4 days        LD Analysis for Milestone2: calculated LD is Rs 192899 for 17 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.GSB/RBI/G-10.30 KM4.0805-01-201520-02-20150.30 KM0.30 KM17.494.08
2.PC/CC i/c Prime Coat, Tack Coat0.38 KM19.0706-01-201515-01-20150.38 KM0.38 KM81.7819.07
3.Road Furniture2.00 No0.1701-01-201505-01-20152.00 No2.00 No0.730.17
Total Amount: 23.32 100   23.32
Remarks: No Remarks       Work Program Made On: 30-12-2014        Updation of work program on: 22-07-2016       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.19-March-20154.09  lakh
2.09-September-201510.15  lakh
3.05-October-20152.95  lakh
4.15-March-20161.34  lakh
5.31-July-20170.00  lakh
Total 18.53  lakh
% Payment87.12 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 124   No. of Test Done : 124    No. of Test Passed : 124   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 85.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 2
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.25-11-20170.300Joint inspection with AE PWD laksar n AE WB TehriSudhir Kumar AEAEUDRP R&B Tehri See Pic
2.10-09-201500+250Mudlana to Harjoli jattSonu SinghSite EngineerDSC2 R&B WB Chakrata See Pic