Makdumpur Link road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1787 |
Sanction Cost: |
37.81 lakh |
Length:
|
1.500 KM. |
District: |
Haridwar |
Block: |
Narsan |
Constituency: |
Jhabrera |
Circle: |
Tehri WB Circle |
DEA: |
DEA Chakrata |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 6
Package Name: 
UDRP/PWD/13/59/RD/006
Tender Date: 03-05-2014
Current Status: Agreement signed
Achieved on Date: 18-10-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/13/59/RD/006
Contractor Name: satyam infratech
|
Start Date: 24-10-2014
Intended Completion Date: 31-05-2017
Original End Date: 23-01-2016 |
Total Bond Cost: 22693440.98 (226.93 lakh)
Variation Cost: 4475896.62 (44.76 lakh) Hence Total Bond Cost is 27169337.6 (271.69 lakh)
|
Sub Project Cost: 49.00 lakh
Variation Cost of Sub Project: 8881912.69 (88.82 lakh)
Total Sub Project Cost:
137.82 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 45388 for 4 days
LD Analysis for Milestone2: calculated LD is Rs 192899 for 17 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.50 KM | 2.34 | 02-04-2015 | 06-04-2015 | 1.50 KM | 1.50 KM | 14.17 | 2.34 | 2. | GSB/RBI/G-1 | 0.35 KM | 5.64 | 15-01-2015 | 30-04-2015 | 0.35 KM | 0.35 KM | 34.16 | 5.64 | 3. | PC/CC i/c Prime Coat, Tack Coat | 1.50 KM | 8.53 | 15-03-2015 | 30-10-2016 | 1.50 KM | 1.50 KM | 51.67 | 8.53 |
Total Amount: |
16.51 |
|
100 |
16.51 |
|
Remarks:
No Remarks
Work Program Made On:
30-12-2014 } ?>
Updation of work program on:
16-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 25-June-2015 | 17.56 lakh | 2. | 15-July-2015 | 9.23 lakh | 3. | 23-July-2015 | 2.11 lakh | 4. | 15-March-2016 | 1.78 lakh | 5. | 01-June-2016 | 17.28 lakh | 6. | 27-September-2016 | 20.09 lakh | 7. | 28-October-2016 | 9.81 lakh | 8. | 07-January-2017 | 15.08 lakh | 9. | 27-March-2017 | 21.98 lakh | 10. | 31-July-2017 | 18.19 lakh |
Total |
133.11 lakh |
% Payment | 96.58 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 124 No. of Test Done : 124 No. of Test Passed : 124 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 86.08 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 4 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 11-02-2017 | 0/28-0/29 | Protection of approach road by plum concrete
Quality of plum is satisfactory | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
2. | 13-10-2016 | 0/28-0/29 | Protection of approach road by plum concrete
Quality of plum is satisfactory | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
3. | 02-09-2016 | Km1 | Earth work in widened portion | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
4. | 21-07-2015 | Ch 1.950 | PC work in makdoompur link Road | Sonu Singh | Site Engineer | DSC2 R&B WB Chakrata | See Pic |
|
|