Latifpur-Khubbanpur road Work Completed
Project: UDRP-RB UID: 1782 Sanction Cost: 6.57  lakh Length: 0.610 KM.
District: Haridwar Block: Bhagwanpur Constituency: Bhagwanpur Circle: Tehri WB Circle
DEA: DEA Chakrata DSC: Egis International DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 56        Package Name:  UDRP/PWD/1/3/59/RD/006b        Tender Date: 03-05-2014        Current Status: Agreement signed        Achieved on Date: 25-08-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/1/3/59/RD/006b      Contractor Name: Link Enterprises
Start Date:  01-09-2014      Intended Completion Date:  31-12-2015     
Total Bond Cost: 25287112.5 (252.87 lakh)        Variation Cost: 4847628.80 (48.48 lakh)    Hence Total Bond Cost is   30134741.3 (301.35 lakh) 
Sub Project Cost: 9.00  lakh        Variation Cost of Sub Project: 702333.40  (7.02 lakh)       Total Sub Project Cost:   16.02 lakh
LD Analysis for Milestone1: calculated LD is Rs 986232 for 78 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.61 KM0.1701-12-201430-01-20150.61 KM0.61 KM1.090.17
2.GSB/RBI/G-10.07 KM2.4901-02-201528-02-20150.07 KM0.07 KM15.962.49
3.G-20.00 KM0.0001-02-201515-02-20150.00 KM0.00 KM00.00
4.G-30.00 KM0.0005-02-201528-02-20150.00 KM0.00 KM00.00
5.PC/CC i/c Prime Coat, Tack Coat0.62 KM12.8001-03-201520-10-20150.62 KM0.62 KM81.912.80
6.Road Furniture2.00 No0.1615-11-201530-11-20152.00 No2.00 No1.050.16
Total Amount: 15.62 100   15.62
Remarks: No Remarks       Work Program Made On: 15-11-2014        Updation of work program on: 09-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.23-April-20155.72  lakh
2.11-August-20150.17  lakh
3.27-July-20164.13  lakh
4.08-November-20165.16  lakh
Total 15.18  lakh
% Payment94.76 %
Advance Amount:  25.28  lakh        Recovered Amount:  25.28  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 273   No. of Test Done : 274    No. of Test Passed : 273   No. of Test Failed : 1   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 1
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.05-11-2014Km 0.550Mss on kubbanpur rdLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic