Lahboli to Mannakheri road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1773 |
Sanction Cost: |
18.79 lakh |
Length:
|
0.500 KM. |
District: |
Haridwar |
Block: |
Narsan |
Constituency: |
Manglore |
Circle: |
Tehri WB Circle |
DEA: |
DEA Chakrata |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 6
Package Name: 
UDRP/PWD/13/59/RD/006
Tender Date: 03-05-2014
Current Status: Agreement signed
Achieved on Date: 18-10-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/13/59/RD/006
Contractor Name: satyam infratech
|
Start Date: 24-10-2014
Intended Completion Date: 31-05-2017
Original End Date: 23-01-2016 |
Total Bond Cost: 22693440.98 (226.93 lakh)
Variation Cost: 4475896.62 (44.76 lakh) Hence Total Bond Cost is 27169337.6 (271.69 lakh)
|
Sub Project Cost: 11.00 lakh
Variation Cost of Sub Project: 960889.84 (9.61 lakh)
Total Sub Project Cost:
20.61 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 45388 for 4 days
LD Analysis for Milestone2: calculated LD is Rs 192899 for 17 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | G-3 | 0.50 KM | 2.34 | 20-07-2015 | 30-07-2015 | 0.50 KM | 0.50 KM | 15.01 | 2.34 | 2. | PC/CC i/c Prime Coat, Tack Coat | 1.10 KM | 9.65 | 15-09-2015 | 30-09-2015 | 1.10 KM | 1.10 KM | 61.9 | 9.65 | 3. | Culverts/Scupper | 1.00 No | 3.43 | 10-01-2015 | 05-07-2015 | 1.00 No | 1.00 No | 22 | 3.43 | 4. | Road Furniture | 2.00 No | 0.17 | 01-01-2015 | 05-01-2015 | 2.00 No | 2.00 No | 1.09 | 0.17 |
Total Amount: |
15.59 |
|
100 |
15.59 |
|
Remarks:
No Remarks
Work Program Made On:
30-12-2014 } ?>
Updation of work program on:
22-07-2016
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 15-July-2015 | 2.97 lakh | 2. | 05-October-2015 | 12.29 lakh | 3. | 15-March-2016 | 4.78 lakh | 4. | 31-July-2017 | 0.00 lakh |
Total |
20.04 lakh |
% Payment | 97.23 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 124 No. of Test Done : 124 No. of Test Passed : 124 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 6 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 25-11-2017 | 1.000 | Joint inspection with AE PWD Laksar n AE WB Tehri | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
2. | 24-09-2015 | 00+700 | Lahboli to mannakhari road | Sonu Singh | Site Engineer | DSC2 R&B WB Chakrata | See Pic |
3. | 22-09-2015 | 00+500 | Lahboli to mannakhari road | Sonu Singh | Site Engineer | DSC2 R&B WB Chakrata | See Pic |
4. | 22-09-2015 | 00+400 | Lahboli to mannakhari road | Sonu Singh | Site Engineer | DSC2 R&B WB Chakrata | See Pic |
5. | 21-09-2015 | 00+900 | Lahboli to mannakhari road | Sonu Singh | Site Engineer | DSC2 R&B WB Chakrata | See Pic |
6. | 19-09-2015 | Km1 | Pc work in progress | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
|
|