Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Hasanpur-Madanpur road Work Completed
Project: UDRP-RB UID: 1760 Sanction Cost: 50.23  lakh Length: 1.650 KM.
District: Haridwar Block: Bhagwanpur Constituency: Bhagwanpur Circle: Tehri WB Circle
DEA: DEA Chakrata DSC: Egis International DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 56        Package Name:  UDRP/PWD/1/3/59/RD/006b        Tender Date: 03-05-2014        Current Status: Agreement signed        Achieved on Date: 25-08-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/1/3/59/RD/006b      Contractor Name: Link Enterprises
Start Date:  01-09-2014      Intended Completion Date:  31-12-2015     
Total Bond Cost: 25287112.5 (252.87 lakh)        Variation Cost: 4847628.80 (48.48 lakh)    Hence Total Bond Cost is   30134741.3 (301.35 lakh) 
Sub Project Cost: 58.00  lakh        Variation Cost of Sub Project: -1908138.78  (-19.08 lakh)       Total Sub Project Cost:   38.92 lakh
LD Analysis for Milestone1: calculated LD is Rs 986232 for 78 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.47 KM2.2105-01-201528-02-20150.47 KM0.47 KM7.092.21
2.R/Wall, B/ Wall Type Protection works0.00 m0.0005-07-201530-07-20150.00 m0.00 m00.00
3.GSB/RBI/G-10.45 KM6.2701-03-201510-07-20150.45 KM0.45 KM20.16.27
4.PC/CC i/c Prime Coat, Tack Coat0.70 KM22.5601-04-201520-10-20150.70 KM0.70 KM72.2822.56
5.longitudinal Drain0.00 m0.0015-06-201505-07-20150.00 m0.00 m00.00
6.Road Furniture2.00 No0.1615-11-201525-11-20152.00 No2.00 No0.530.16
Total Amount: 31.2 100   31.2
Remarks: No Remarks       Work Program Made On: 15-11-2014        Updation of work program on: 22-07-2016       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-December-201421.30  lakh
2.23-April-20150.01  lakh
3.16-July-20155.89  lakh
4.22-September-20153.86  lakh
5.27-July-20160.16  lakh
Total 31.22  lakh
% Payment80.22 %
Advance Amount:  25.28  lakh        Recovered Amount:  25.28  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 273   No. of Test Done : 274    No. of Test Passed : 273   No. of Test Failed : 1   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 1
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.19-04-2015Km 1 hasanpurCc pavement completeLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic