GT road to Seesona road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1752 |
Sanction Cost: |
35.00 lakh |
Length:
|
0.700 KM. |
District: |
Haridwar |
Block: |
Bhagwanpur |
Constituency: |
Bhagwanpur |
Circle: |
Tehri WB Circle |
DEA: |
DEA Chakrata |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 55
Package Name: 
UDRP/PWD/1/3/59/RD/006A
Tender Date: 03-05-2014
Current Status: Agreement signed
Achieved on Date: 25-08-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/1/3/59/RD/006A
Contractor Name: Link Enterprises
|
Start Date: 01-09-2014
Intended Completion Date: 10-03-2016
Original End Date: 31-12-2015 |
Total Bond Cost: 22039759.64 (220.4 lakh)
Variation Cost: -2023917.29 (-20.24 lakh) Hence Total Bond Cost is 20015842.35 (200.16 lakh)
|
Sub Project Cost: 30.86 lakh
Variation Cost of Sub Project: 489579.95 (4.9 lakh)
Total Sub Project Cost:
35.76 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 440800 for 40 days
LD Analysis for Milestone2: calculated LD is Rs 1553820 for 141 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.47 KM | 0.11 | 01-05-2015 | 30-05-2015 | 0.47 KM | 0.47 KM | 0.29 | 0.11 | 2. | GSB/RBI/G-1 | 0.48 KM | 4.85 | 01-06-2015 | 15-06-2015 | 0.48 KM | 0.48 KM | 12.58 | 4.85 | 3. | G-3 | 0.51 KM | 2.14 | 16-06-2015 | 30-06-2015 | 0.51 KM | 0.51 KM | 5.53 | 2.14 | 4. | PC/CC i/c Prime Coat, Tack Coat | 1.08 KM | 31.36 | 01-09-2015 | 30-09-2015 | 1.08 KM | 1.08 KM | 81.28 | 31.36 | 5. | Road Furniture | 1.00 No | 0.13 | 01-11-2015 | 05-11-2015 | 1.00 No | 1.00 No | 0.32 | 0.13 |
Total Amount: |
38.59 |
|
100 |
38.59 |
|
Remarks:
No Remarks
Work Program Made On:
07-10-2014 } ?>
Updation of work program on:
16-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 17-March-2015 | 2.08 lakh | 2. | 25-March-2015 | 17.21 lakh | 3. | 30-May-2015 | 13.48 lakh | 4. | 16-July-2015 | 0.11 lakh | 5. | 15-February-2016 | 5.49 lakh | 6. | 18-May-2017 | 0.96 lakh |
Total |
39.33 lakh |
% Payment | 109.98 % |
|
Advance Amount: 22.00 lakh
Recovered Amount: 22.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 160 No. of Test Done : 160 No. of Test Passed : 160 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 10 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 20-01-2017 | Km 1 | CC road surface good even after two rainy season. | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
2. | 04-10-2016 | ch 0/11-0/12 | Inspection of PC and found ok | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
3. | 04-10-2016 | Ch0/5-0/6 | Inspection of PC and found ok after completion of work | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
4. | 09-10-2015 | 00+400 | GT Road to Seesona road | Sonu Singh | Site Engineer | DSC2 R&B WB Chakrata | See Pic |
5. | 09-10-2015 | 00+230 | GT Road to Seesona road | Sonu Singh | Site Engineer | DSC2 R&B WB Chakrata | See Pic |
6. | 09-10-2015 | 00+300 | GT Road to Seesona road | Sonu Singh | Site Engineer | DSC2 R&B WB Chakrata | See Pic |
7. | 22-04-2015 | 0.190 km | Gsb completed | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
8. | 15-03-2015 | Km 1 near Seesona village | Work completed | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
9. | 14-03-2015 | Km1 near industrial arra | Cc rd complete | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
10. | 14-12-2014 | Widening of road ch.0.400km | Chainage 0 . 40 km | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
|
|