GT road to Lavva road Work Completed
Project: UDRP-RB UID: 1751 Sanction Cost: 23.00  lakh Length: 1.500 KM.
District: Haridwar Block: Bhagwanpur Constituency: Bhagwanpur Circle: Tehri WB Circle
DEA: DEA Chakrata DSC: Egis International DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 55        Package Name:  UDRP/PWD/1/3/59/RD/006A        Tender Date: 03-05-2014        Current Status: Agreement signed        Achieved on Date: 25-08-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/1/3/59/RD/006A      Contractor Name: Link Enterprises
Start Date:  01-09-2014      Intended Completion Date:  10-03-2016      Original End Date:  31-12-2015
Total Bond Cost: 22039759.64 (220.4 lakh)        Variation Cost: -2023917.29 (-20.24 lakh)    Hence Total Bond Cost is   20015842.35 (200.16 lakh) 
Sub Project Cost: 22.59  lakh        Variation Cost of Sub Project: -927539.27  (-9.28 lakh)       Total Sub Project Cost:   13.31 lakh
LD Analysis for Milestone1: calculated LD is Rs 440800 for 40 days        LD Analysis for Milestone2: calculated LD is Rs 1553820 for 141 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.40 KM1.4201-02-201528-02-20151.40 KM1.40 KM10.791.42
2.G-30.00 KM0.0001-03-201531-03-20150.01 KM0.01 KM00.00
3.PC/CC i/c Prime Coat, Tack Coat1.40 KM11.4101-04-201520-10-20151.40 KM1.40 KM86.7111.41
4.Road Furniture4.00 No0.3301-06-201505-06-20154.00 No4.00 No2.50.33
Total Amount: 13.16 100   13.16
Remarks: No Remarks       Work Program Made On: 07-10-2014        Updation of work program on: 16-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.17-March-20159.24  lakh
2.30-May-20152.17  lakh
3.31-March-20161.64  lakh
4.18-May-20170.73  lakh
Total 13.78  lakh
% Payment103.53 %
Advance Amount:  22.00  lakh        Recovered Amount:  22.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 160   No. of Test Done : 160    No. of Test Passed : 160   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 4
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.11-02-2017DtdfInspection of PC in Lavva RoadDhwajvir SinghJEUDRP R&B Chakrata See Pic
2.21-01-2017Ch 0.200 kmThis PC surface completed 2 years and two months.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
3.20-01-2017Km 1Surface of PC good even after two rainy season.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
4.10-09-201500+100G.T Road to Lavva RoadSonu SinghSite EngineerDSC2 R&B WB Chakrata See Pic