Vill Dada Jalalpur to Samsaan Ghat road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1711 |
Sanction Cost: |
15.00 lakh |
Length:
|
1.000 KM. |
District: |
Haridwar |
Block: |
Bhagwanpur |
Constituency: |
Bhagwanpur |
Circle: |
Tehri WB Circle |
DEA: |
DEA Chakrata |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 55
Package Name: 
UDRP/PWD/1/3/59/RD/006A
Tender Date: 03-05-2014
Current Status: Agreement signed
Achieved on Date: 25-08-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/1/3/59/RD/006A
Contractor Name: Link Enterprises
|
Start Date: 01-09-2014
Intended Completion Date: 10-03-2016
Original End Date: 31-12-2015 |
Total Bond Cost: 22039759.64 (220.4 lakh)
Variation Cost: -2023917.29 (-20.24 lakh) Hence Total Bond Cost is 20015842.35 (200.16 lakh)
|
Sub Project Cost: 14.67 lakh
Variation Cost of Sub Project: 3945951.70 (39.46 lakh)
Total Sub Project Cost:
54.13 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 440800 for 40 days
LD Analysis for Milestone2: calculated LD is Rs 1553820 for 141 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.35 KM | 1.12 | 01-02-2015 | 28-02-2015 | 0.35 KM | 0.35 KM | 9.08 | 1.12 | 2. | G-2 | 0.15 KM | 0.60 | 01-03-2015 | 31-03-2015 | 0.15 KM | 0.15 KM | 4.89 | 0.60 | 3. | G-3 | 0.35 KM | 1.43 | 01-04-2015 | 28-04-2015 | 0.35 KM | 0.35 KM | 11.62 | 1.43 | 4. | PC/CC i/c Prime Coat, Tack Coat | 0.86 KM | 7.27 | 02-04-2015 | 31-05-2015 | 0.86 KM | 0.86 KM | 59.14 | 7.27 | 5. | Cause Way | 1.00 No | 1.75 | 02-12-2014 | 31-01-2015 | 1.00 No | 1.00 No | 14.25 | 1.75 | 6. | Road Furniture | 1.00 No | 0.13 | 01-06-2015 | 05-06-2015 | 1.00 No | 1.00 No | 1.02 | 0.13 |
Total Amount: |
12.3 |
|
100 |
12.3 |
|
Remarks:
No Remarks
Work Program Made On:
07-10-2014 } ?>
Updation of work program on:
16-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 07-November-2015 | 3.56 lakh | 2. | 15-February-2016 | 19.56 lakh | 3. | 31-March-2016 | 13.87 lakh | 4. | 29-August-2016 | 12.49 lakh | 5. | 18-May-2017 | 7.99 lakh |
Total |
57.47 lakh |
% Payment | 106.17 % |
|
Advance Amount: 22.00 lakh
Recovered Amount: 22.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 160 No. of Test Done : 160 No. of Test Passed : 160 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
Number of Notice(s) issued: 1 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 4 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 13-10-2016 | Ch 0/16-0/18 | Inspection of PC and found OK | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
2. | 19-03-2016 | Km1 | Constriction of causeway under progress | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
3. | 21-10-2015 | 00+550 | Dada jalapur | Sonu Singh | Site Engineer | DSC2 R&B WB Chakrata | See Pic |
4. | 05-10-2015 | Km1 | Cc road required | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
|
|