Bhagwanpur-Sikhroda road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1702 |
Sanction Cost: |
55.00 lakh |
Length:
|
8.000 KM. |
District: |
Haridwar |
Block: |
Bhagwanpur |
Constituency: |
Bhagwanpur |
Circle: |
Tehri WB Circle |
DEA: |
DEA Chakrata |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
Type: |
ODR |
|
Procurement: |
Package No.: 55
Package Name: 
UDRP/PWD/1/3/59/RD/006A
Tender Date: 03-05-2014
Current Status: Agreement signed
Achieved on Date: 25-08-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/1/3/59/RD/006A
Contractor Name: Link Enterprises
|
Start Date: 01-09-2014
Intended Completion Date: 10-03-2016
Original End Date: 31-12-2015 |
Total Bond Cost: 22039759.64 (220.4 lakh)
Variation Cost: -2023917.29 (-20.24 lakh) Hence Total Bond Cost is 20015842.35 (200.16 lakh)
|
Sub Project Cost: 31.48 lakh
Variation Cost of Sub Project: 1169153.68 (11.69 lakh)
Total Sub Project Cost:
43.17 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 440800 for 40 days
LD Analysis for Milestone2: calculated LD is Rs 1553820 for 141 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.24 KM | 6.25 | 01-01-2015 | 01-04-2015 | 0.24 KM | 0.24 KM | 10.85 | 6.25 | 2. | R/Wall, B/ Wall Type Protection works | 404.00 m | 28.56 | 01-07-2015 | 20-07-2015 | 404.00 m | 404.00 m | 49.59 | 28.56 | 3. | GSB/RBI/G-1 | 0.16 KM | 0.90 | 01-02-2015 | 20-07-2015 | 0.16 KM | 0.16 KM | 1.57 | 0.90 | 4. | G-2 | 0.16 KM | 0.64 | 01-07-2015 | 20-07-2015 | 0.16 KM | 0.16 KM | 1.11 | 0.64 | 5. | G-3 | 0.25 KM | 1.02 | 01-07-2015 | 20-07-2015 | 0.25 KM | 0.25 KM | 1.77 | 1.02 | 6. | PC/CC i/c Prime Coat, Tack Coat | 0.25 KM | 2.39 | 20-07-2015 | 30-07-2015 | 0.25 KM | 0.25 KM | 4.15 | 2.39 | 7. | Culverts/Scupper | 2.00 No | 17.50 | 05-01-2015 | 15-06-2015 | 2.00 No | 2.00 No | 30.39 | 17.50 | 8. | Road Furniture | 4.00 No | 0.33 | 02-06-2015 | 08-06-2015 | 4.00 No | 4.00 No | 0.57 | 0.33 |
Total Amount: |
57.59 |
|
100 |
57.59 |
|
Remarks:
No Remarks
Work Program Made On:
07-10-2014 } ?>
Updation of work program on:
22-07-2016
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-December-2014 | 4.33 lakh | 2. | 17-March-2015 | 2.38 lakh | 3. | 30-May-2015 | 4.06 lakh | 4. | 25-June-2015 | 2.17 lakh | 5. | 16-July-2015 | 1.38 lakh | 6. | 11-August-2015 | 4.66 lakh | 7. | 07-November-2015 | 2.10 lakh | 8. | 15-February-2016 | 18.63 lakh | 9. | 31-March-2016 | 6.00 lakh | 10. | 29-August-2016 | 12.49 lakh | 11. | 18-May-2017 | 0.22 lakh |
Total |
58.42 lakh |
% Payment | 135.33 % |
|
Advance Amount: 22.00 lakh
Recovered Amount: 22.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 160 No. of Test Done : 160 No. of Test Passed : 160 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
Number of Notice(s) issued: 1 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 8 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 10-05-2016 | Ch 5.350 | PC work done in Bhagwanpur shikhroda m/r | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
2. | 19-03-2016 | Km 06 | Protection work of the culvert | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
3. | 16-03-2016 | Km06 | Protection work of bridge | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
4. | 09-10-2015 | 5+200 | Bhagwanpur to sikhroda road | Sonu Singh | Site Engineer | DSC2 R&B WB Chakrata | See Pic |
5. | 09-10-2015 | 5+250 | Bhagwanpur to sikhroda road | Sonu Singh | Site Engineer | DSC2 R&B WB Chakrata | See Pic |
6. | 09-10-2015 | 5+350 | Bhagwanpur to sikhroda road | Sonu Singh | Site Engineer | DSC2 R&B WB Chakrata | See Pic |
7. | 19-04-2015 | 6.0 mtr culvert km 5.3 | Excavation of foundation for 6.0 mtr rcc culvert | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
8. | 14-03-2015 | Km 3 6.0 m scupper | Constriction of scupper complete | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
|
|