Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Bhagwanpur-Sikhroda road Work Completed
Project: UDRP-RB UID: 1702 Sanction Cost: 55.00  lakh Length: 8.000 KM.
District: Haridwar Block: Bhagwanpur Constituency: Bhagwanpur Circle: Tehri WB Circle
DEA: DEA Chakrata DSC: Egis International DSC Scope: only Supervision Type: ODR
Procurement:
Package No.: 55        Package Name:  UDRP/PWD/1/3/59/RD/006A        Tender Date: 03-05-2014        Current Status: Agreement signed        Achieved on Date: 25-08-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/1/3/59/RD/006A      Contractor Name: Link Enterprises
Start Date:  01-09-2014      Intended Completion Date:  10-03-2016      Original End Date:  31-12-2015
Total Bond Cost: 22039759.64 (220.4 lakh)        Variation Cost: -2023917.29 (-20.24 lakh)    Hence Total Bond Cost is   20015842.35 (200.16 lakh) 
Sub Project Cost: 31.48  lakh        Variation Cost of Sub Project: 1169153.68  (11.69 lakh)       Total Sub Project Cost:   43.17 lakh
LD Analysis for Milestone1: calculated LD is Rs 440800 for 40 days        LD Analysis for Milestone2: calculated LD is Rs 1553820 for 141 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.24 KM6.2501-01-201501-04-20150.24 KM0.24 KM10.856.25
2.R/Wall, B/ Wall Type Protection works404.00 m28.5601-07-201520-07-2015404.00 m404.00 m49.5928.56
3.GSB/RBI/G-10.16 KM0.9001-02-201520-07-20150.16 KM0.16 KM1.570.90
4.G-20.16 KM0.6401-07-201520-07-20150.16 KM0.16 KM1.110.64
5.G-30.25 KM1.0201-07-201520-07-20150.25 KM0.25 KM1.771.02
6.PC/CC i/c Prime Coat, Tack Coat0.25 KM2.3920-07-201530-07-20150.25 KM0.25 KM4.152.39
7.Culverts/Scupper 2.00 No17.5005-01-201515-06-20152.00 No2.00 No30.3917.50
8.Road Furniture4.00 No0.3302-06-201508-06-20154.00 No4.00 No0.570.33
Total Amount: 57.59 100   57.59
Remarks: No Remarks       Work Program Made On: 07-10-2014        Updation of work program on: 22-07-2016       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-December-20144.33  lakh
2.17-March-20152.38  lakh
3.30-May-20154.06  lakh
4.25-June-20152.17  lakh
5.16-July-20151.38  lakh
6.11-August-20154.66  lakh
7.07-November-20152.10  lakh
8.15-February-201618.63  lakh
9.31-March-20166.00  lakh
10.29-August-201612.49  lakh
11.18-May-20170.22  lakh
Total 58.42  lakh
% Payment135.33 %
Advance Amount:  22.00  lakh        Recovered Amount:  22.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 160   No. of Test Done : 160    No. of Test Passed : 160   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
Number of Notice(s) issued: 1

Mobile Pic Upload

Number of Pics Available on Web Repository: 8
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.10-05-2016Ch 5.350PC work done in Bhagwanpur shikhroda m/rDhwajvir SinghJEUDRP R&B Chakrata See Pic
2.19-03-2016Km 06Protection work of the culvertLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
3.16-03-2016Km06Protection work of bridgeLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
4.09-10-20155+200Bhagwanpur to sikhroda roadSonu SinghSite EngineerDSC2 R&B WB Chakrata See Pic
5.09-10-20155+250Bhagwanpur to sikhroda roadSonu SinghSite EngineerDSC2 R&B WB Chakrata See Pic
6.09-10-20155+350Bhagwanpur to sikhroda roadSonu SinghSite EngineerDSC2 R&B WB Chakrata See Pic
7.19-04-20156.0 mtr culvert km 5.3Excavation of foundation for 6.0 mtr rcc culvertLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
8.14-03-2015Km 3 6.0 m scupperConstriction of scupper completeLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic