Johari Jakhan Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1608 |
Sanction Cost: |
70.60 lakh |
Length:
|
1.600 KM. |
District: |
Dehradun |
Block: |
Sahaspur |
Constituency: |
Mussoorie |
Circle: |
|
DEA: |
DEA Chakrata |
DSC: |
Egis International |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 129
Package Name: 
UDRP/PWD/05/51/RD/117
Tender Date: 28-04-2016
Current Status: Agreement signed
Achieved on Date: 30-06-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/05/51/RD/117
Contractor Name: Shivom Construction
|
Start Date: 07-07-2016
Intended Completion Date: 23-04-2017
Original End Date: 06-01-2017 |
Total Bond Cost: 6142238.98 (61.42 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 187331 for +61 days
LD Analysis for Milestone2: calculated LD is Rs 445295 for 145 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | GSB/RBI/G-1 | 0.10 KM | 0.75 | 01-09-2016 | 15-12-2016 | 0.10 KM | 0.10 KM | 1.28 | 0.75 | 2. | G-2 | 0.20 KM | 1.24 | 18-09-2016 | 15-12-2016 | 0.20 KM | 0.20 KM | 2.11 | 1.24 | 3. | G-3 | 0.20 KM | 0.81 | 28-09-2016 | 15-12-2016 | 0.20 KM | 0.20 KM | 1.38 | 0.81 | 4. | PC/CC i/c Prime Coat, Tack Coat | 0.53 KM | 15.76 | 01-10-2016 | 21-04-2017 | 0.53 KM | 0.53 KM | 26.8 | 15.76 | 5. | BM i/c Prime Coat, Tack Coat | 0.40 KM | 3.00 | 07-10-2016 | 01-04-2017 | 0.40 KM | 0.40 KM | 5.1 | 3.00 | 6. | SDBC i/c Tackcoat | 1.20 KM | 15.99 | 24-11-2016 | 06-04-2017 | 1.20 KM | 1.20 KM | 27.19 | 15.99 | 7. | longitudinal Drain | 2000.00 m | 21.00 | 05-10-2016 | 23-04-2017 | 2000.00 m | 2000.00 m | 35.71 | 21.00 | 8. | Crash Barrier | 0.00 m | 0.00 | 25-12-2016 | 23-04-2017 | 0.00 m | 0.00 m | 0 | 0.00 | 9. | Road Furniture | 2.00 No | 0.25 | 10-09-2016 | 23-04-2017 | 2.00 No | 2.00 No | 0.43 | 0.25 |
Total Amount: |
58.8 |
|
100 |
58.8 |
|
Remarks:
No Remarks
Work Program Made On:
05-09-2016 } ?>
Updation of work program on:
08-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-November-2016 | 5.02 lakh | 2. | 25-January-2017 | 13.46 lakh | 3. | 25-March-2017 | 9.53 lakh | 4. | 27-April-2017 | 14.45 lakh | 5. | 02-June-2017 | 10.43 lakh | 6. | 31-July-2017 | 15.87 lakh |
Total |
68.76 lakh |
% Payment |
111.95 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 82 No. of Test Done : 82 No. of Test Passed : 82 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 89.81 |
Number of Notice(s) issued: 51 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 77 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 09-01-2018 | Site inspection by SE Sir n EE Mam WB PWD Tehri | 1.425 | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
2. | 09-01-2018 | 0.110 | Site inspection by SE Sir n EE Mam WB PWD Tehri | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
3. | 16-05-2017 | Ch 0/18 towards johri village | Shoulder work in progress at johari jakhan m/r. Quality is good | Ashish Kalura | AE | UDRP R&B Chakrata | See Pic |
4. | 25-04-2017 | Ch 0/20 towards jakhan village | Meeting with local people at johari jakhan m/r | Ashish Kalura | AE | UDRP R&B Chakrata | See Pic |
5. | 25-04-2017 | Ch 0/26 near forest area | Site inspection by S.E sir world bank circle Tehri at johari jakhan m/r | Ashish Kalura | AE | UDRP R&B Chakrata | See Pic |
6. | 17-04-2017 | Ch 1/3 Near himalaya garden | Site inspection of johari jakhan m/r after laying of sdbc work on previous day | Ashish Kalura | AE | UDRP R&B Chakrata | See Pic |
7. | 17-04-2017 | 0/28 near forest area | Site visit of johari jakhan m/r after completion of sdbc work on previous day. | Ashish Kalura | AE | UDRP R&B Chakrata | See Pic |
8. | 14-04-2017 | Ch 1/6 near himalaya garden | Rolling over Sdbc at johri jakhan m/r pkg 117 | Ashish Kalura | AE | UDRP R&B Chakrata | See Pic |
9. | 14-04-2017 | 0/25 towards johri village | Sdbc work in progress at johari jakhan m/r,pkg 117 | Ashish Kalura | AE | UDRP R&B Chakrata | See Pic |
10. | 13-04-2017 | Bituminous plant near Selaque,Dehradun | Bitumen content test at bituminous plant. Found satisfactory.pkg 117 johri jakhan m/r | Ashish Kalura | AE | UDRP R&B Chakrata | See Pic |
11. | 13-04-2017 | At ch 0/21-22 | SDBC Rolling work in progress | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
12. | 13-04-2017 | At Ch 0/9-10 | SDBC Rolling work checking in progress work found satisfactory | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
13. | 13-04-2017 | At Ch 0/19-20 | SDBC thickness checking found satisfactory And Temperature = 132 degree | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
14. | 13-04-2017 | At Ch 0/18-19 | SDBC Rolling in progress | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
15. | 13-04-2017 | At Ch 0/18-19 | SDBC work in progress and found satisfactory | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
16. | 13-04-2017 | Ch 0/5 towards johri village | Laying of SDBC at johari jakhan m/r | Ashish Kalura | AE | UDRP R&B Chakrata | See Pic |
17. | 13-04-2017 | Ch 0/5 towards johri village | Applying tack coat on hungry surface at pkg 117 johari jakhan m/r | Ashish Kalura | AE | UDRP R&B Chakrata | See Pic |
18. | 13-04-2017 | At Bituminous plant selaqui,Dehradun | Bitumen content test at bituminous plant. Pkg 117 johari jakhan m/r | Ashish Kalura | AE | UDRP R&B Chakrata | See Pic |
19. | 13-04-2017 | At bituminous plant near Selaqui,Dehradun | Temperature is checked at bituminous plant.found ok.pkg 117 johari jakhan m/r | Ashish Kalura | AE | UDRP R&B Chakrata | See Pic |
20. | 12-04-2017 | At Bituminous Plant near selaqui,Dehradun | Bitumen content test at bituminous plant. Result- Bitumen content 5.1% found satisfactory.pkg 117 johari jakhan m/r | Ashish Kalura | AE | UDRP R&B Chakrata | See Pic |
|
|