Suryadhar Sangaoun Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1587 |
Sanction Cost: |
198.83 lakh |
Length:
|
5.500 KM. |
District: |
Dehradun |
Block: |
Raipur |
Constituency: |
Doiwala |
Circle: |
Tehri WB Circle |
DEA: |
DEA Chakrata |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 5
Package Name: 
UDRP/PWD/05/53/RD/005
Tender Date: 22-02-2014
Current Status: Agreement signed
Achieved on Date: 25-08-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/05/53/RD/005
Contractor Name: Vijay Engineering Associates
|
Start Date: 01-09-2014
Intended Completion Date: 30-04-2016
Original End Date: 31-12-2015 |
Total Bond Cost: 54378925.06 (543.79 lakh)
Variation Cost: 19270279.78 (192.7 lakh) Hence Total Bond Cost is 73649204.84 (736.49 lakh)
|
Sub Project Cost: 102.30 lakh
Variation Cost of Sub Project: 8125230.18 (81.25 lakh)
Total Sub Project Cost:
183.55 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | R/Wall, B/ Wall Type Protection works | 416.70 m | 126.18 | 22-09-2014 | 30-03-2016 | 416.70 m | 416.70 m | 66.47 | 126.18 | 2. | GSB/RBI/G-1 | 1.43 KM | 6.62 | 01-10-2015 | 28-02-2016 | 1.43 KM | 1.43 KM | 3.49 | 6.62 | 3. | Cause Way | 6.00 No | 12.16 | 01-05-2015 | 30-04-2016 | 6.00 No | 6.00 No | 6.41 | 12.16 | 4. | Culverts/Scupper | 9.00 No | 44.87 | 01-01-2015 | 30-01-2016 | 9.00 No | 9.00 No | 23.64 | 44.87 | 5. | longitudinal Drain | 0.00 m | 0.00 | 06-10-2015 | 30-04-2016 | 0.00 m | 0.00 m | 0 | 0.00 | 6. | Crash Barrier | 0.00 m | 0.00 | 01-01-2016 | 30-01-2016 | 0.00 m | 0.00 m | 0 | 0.00 |
Total Amount: |
189.83 |
|
100 |
189.83 |
|
Remarks:
No Remarks
Work Program Made On:
23-09-2014 } ?>
Updation of work program on:
03-08-2016
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 28-October-2014 | 5.01 lakh | 2. | 31-December-2014 | 17.69 lakh | 3. | 18-February-2015 | 12.12 lakh | 4. | 31-March-2015 | 3.26 lakh | 5. | 22-May-2015 | 4.23 lakh | 6. | 22-June-2015 | 2.34 lakh | 7. | 31-July-2015 | 2.24 lakh | 8. | 23-September-2015 | 13.52 lakh | 9. | 06-November-2015 | 42.52 lakh | 10. | 19-December-2015 | 23.46 lakh | 11. | 23-January-2016 | 6.21 lakh | 12. | 29-February-2016 | 7.78 lakh | 13. | 31-March-2016 | 2.00 lakh | 14. | 06-May-2016 | 1.33 lakh | 15. | 08-August-2016 | 31.69 lakh | 16. | 04-February-2017 | 1.90 lakh | 17. | 30-June-2017 | 4.36 lakh |
Total |
181.66 lakh |
% Payment | 98.97 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 504 No. of Test Done : 514 No. of Test Passed : 504 No. of Test Failed : 10 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 34 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 27-08-2016 | Ch1/16 | Joint inspection with constant clint & contractor regarding complition of work. | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
2. | 04-05-2016 | Km3 under RCC bridge | Repairing of Eroded base of of rcc bridge. | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
3. | 21-04-2016 | Ch 1/11-1/12 | Construction of R/W completed | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
4. | 30-03-2016 | 0/37 | Reconstruction of washed away portion | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
5. | 17-02-2016 | Km1 | Construction of breast wall | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
6. | 09-02-2016 | Km 2 | Hill side cutting | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
7. | 20-12-2015 | Km5 | Rwall under progress | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
8. | 20-10-2015 | Km1 | Protection work of washed away portion of the road km1 | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
9. | 20-10-2015 | Km1 | Protection work of the washed away portion 2nd layer | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
10. | 06-10-2015 | Km 2 | Protection work of washed away portion of the road. | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
11. | 28-09-2015 | Km 2 | Protection work of the washed away portion of the road. | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
12. | 28-09-2015 | Km 2 | Protection work for washed away portion of the road. | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
13. | 22-09-2015 | Km2 | Protection work for washed away portion of the road | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
14. | 18-09-2015 | Ch 0.075 | Maintenance of gravel rd and profile rectifying. | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
15. | 03-09-2015 | Km3 | Floor of bridge eroded | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
16. | 24-08-2015 | Ch 1.800 | Temporary opening of suryadhar Sangoun M/R to pass the trafic. | D S Tomar | JE | DEA WB Chakrata | See Pic |
17. | 22-08-2015 | RE construction of washed away portion of the road | Km2 | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
18. | 22-08-2015 | Km1 | Slip on rd | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
19. | 12-08-2015 | Km 2 | Road cut due to flood | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
20. | 10-08-2015 | Ch
1.800 | Temporary opening of suryadhar Sangoun Motor Road | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
|
|