Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Suryadhar Sangaoun Motor Road Work Completed
Project: UDRP-RB UID: 1587 Sanction Cost: 198.83  lakh Length: 5.500 KM.
District: Dehradun Block: Raipur Constituency: Doiwala Circle: Tehri WB Circle
DEA: DEA Chakrata DSC: Egis International DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 5        Package Name:  UDRP/PWD/05/53/RD/005        Tender Date: 22-02-2014        Current Status: Agreement signed        Achieved on Date: 25-08-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/05/53/RD/005      Contractor Name: Vijay Engineering Associates
Start Date:  01-09-2014      Intended Completion Date:  30-04-2016      Original End Date:  31-12-2015
Total Bond Cost: 54378925.06 (543.79 lakh)        Variation Cost: 19270279.78 (192.7 lakh)    Hence Total Bond Cost is   73649204.84 (736.49 lakh) 
Sub Project Cost: 102.30  lakh        Variation Cost of Sub Project: 8125230.18  (81.25 lakh)       Total Sub Project Cost:   183.55 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works416.70 m126.1822-09-201430-03-2016416.70 m416.70 m66.47126.18
2.GSB/RBI/G-11.43 KM6.6201-10-201528-02-20161.43 KM1.43 KM3.496.62
3.Cause Way6.00 No12.1601-05-201530-04-20166.00 No6.00 No6.4112.16
4.Culverts/Scupper 9.00 No44.8701-01-201530-01-20169.00 No9.00 No23.6444.87
5.longitudinal Drain0.00 m0.0006-10-201530-04-20160.00 m0.00 m00.00
6.Crash Barrier0.00 m0.0001-01-201630-01-20160.00 m0.00 m00.00
Total Amount: 189.83 100   189.83
Remarks: No Remarks       Work Program Made On: 23-09-2014        Updation of work program on: 03-08-2016       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-October-20145.01  lakh
2.31-December-201417.69  lakh
3.18-February-201512.12  lakh
4.31-March-20153.26  lakh
5.22-May-20154.23  lakh
6.22-June-20152.34  lakh
7.31-July-20152.24  lakh
8.23-September-201513.52  lakh
9.06-November-201542.52  lakh
10.19-December-201523.46  lakh
11.23-January-20166.21  lakh
12.29-February-20167.78  lakh
13.31-March-20162.00  lakh
14.06-May-20161.33  lakh
15.08-August-201631.69  lakh
16.04-February-20171.90  lakh
17.30-June-20174.36  lakh
Total 181.66  lakh
% Payment98.97 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 504   No. of Test Done : 514    No. of Test Passed : 504   No. of Test Failed : 10   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 34
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.27-08-2016Ch1/16Joint inspection with constant clint & contractor regarding complition of work.Om Prakash SinghSite SupervisorDSC2 R&B WB Dehradun See Pic
2.04-05-2016Km3 under RCC bridgeRepairing of Eroded base of of rcc bridge.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
3.21-04-2016Ch 1/11-1/12Construction of R/W completedDhwajvir SinghJEUDRP R&B Chakrata See Pic
4.30-03-20160/37Reconstruction of washed away portionLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
5.17-02-2016Km1Construction of breast wallLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
6.09-02-2016Km 2Hill side cuttingLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
7.20-12-2015Km5Rwall under progressLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
8.20-10-2015Km1Protection work of washed away portion of the road km1Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
9.20-10-2015Km1Protection work of the washed away portion 2nd layerLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
10.06-10-2015Km 2Protection work of washed away portion of the road.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
11.28-09-2015Km 2Protection work of the washed away portion of the road.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
12.28-09-2015Km 2Protection work for washed away portion of the road.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
13.22-09-2015Km2Protection work for washed away portion of the roadLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
14.18-09-2015Ch 0.075Maintenance of gravel rd and profile rectifying.Dhwajvir SinghJEUDRP R&B Chakrata See Pic
15.03-09-2015Km3Floor of bridge erodedLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
16.24-08-2015Ch 1.800Temporary opening of suryadhar Sangoun M/R to pass the trafic.D S TomarJEDEA WB Chakrata See Pic
17.22-08-2015RE construction of washed away portion of the roadKm2Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
18.22-08-2015Km1Slip on rdLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
19.12-08-2015Km 2Road cut due to floodLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
20.10-08-2015Ch 1.800Temporary opening of suryadhar Sangoun Motor RoadDhwajvir SinghJEUDRP R&B Chakrata See Pic