Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Submergence Road Work Completed
Project: UDRP-RB UID: 1585 Sanction Cost: 433.01  lakh Length: 22.000 KM.
District: Dehradun Block: Kalsi Constituency: Chakrata Circle: Tehri WB Circle
DEA: DEA Chakrata DSC: Egis International DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 40        Package Name:  UDRP/PWD/05/56/RD/040        Tender Date: 27-03-2014        Current Status: Agreement signed        Achieved on Date: 03-07-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/05/56/RD/040      Contractor Name: Dilawar Singh Contractor
Start Date:  07-07-2014      Intended Completion Date:  14-06-2016      Original End Date:  06-10-2015
Total Bond Cost: 54721659.09 (547.22 lakh)        Variation Cost: 17612476.88 (176.12 lakh)    Hence Total Bond Cost is   72334135.97 (723.34 lakh) 
Sub Project Cost: 307.23  lakh        Variation Cost of Sub Project: 12108926.62  (121.09 lakh)       Total Sub Project Cost:   428.32 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence4.85 KM60.3215-07-201430-07-20144.85 KM4.85 KM14.1660.32
2.R/Wall, B/ Wall Type Protection works3058.00 m108.0508-07-201423-12-20153058.00 m3058.00 m25.36108.05
3.GSB/RBI/G-14.00 KM18.5515-07-201424-10-20154.00 KM4.00 KM4.3518.55
4.G-24.00 KM15.0401-10-201408-11-20154.00 KM4.00 KM3.5315.04
5.G-34.00 KM15.5316-12-201423-12-20154.00 KM4.00 KM3.6515.53
6.PC/CC i/c Prime Coat, Tack Coat4.00 KM38.8215-04-201614-06-20164.00 KM4.00 KM9.1138.82
7.Cause Way15.00 No31.9201-01-201508-12-201515.00 No15.00 No7.4931.92
8.Culverts/Scupper 14.00 No65.9915-01-201523-11-201514.00 No14.00 No15.4965.99
9.longitudinal Drain10400.00 m59.0620-01-201508-11-201510400.00 m10400.00 m13.8659.06
10.Crash Barrier500.00 m10.7931-01-201523-11-2015500.00 m500.00 m2.5310.79
11.Road Furniture105.00 No1.9715-01-201530-11-2015105.00 No105.00 No0.461.97
Total Amount: 426.04 100   426.04
Remarks:        Work Program Made On: 16-07-2014        Updation of work program on: 15-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.10-September-201410.19  lakh
2.30-September-201412.20  lakh
3.31-October-201414.61  lakh
4.31-December-20144.74  lakh
5.03-January-20152.27  lakh
6.12-February-201521.49  lakh
7.30-March-201535.91  lakh
8.31-March-20158.10  lakh
9.11-June-201524.92  lakh
10.15-July-201520.90  lakh
11.16-July-20155.63  lakh
12.20-August-201521.32  lakh
13.30-September-201528.87  lakh
14.09-November-20158.99  lakh
15.30-November-201534.60  lakh
16.23-December-20154.67  lakh
17.15-February-201613.99  lakh
18.05-March-201623.70  lakh
19.30-March-201618.93  lakh
20.28-April-201618.65  lakh
21.20-May-201640.67  lakh
22.30-June-201639.45  lakh
23.30-December-20169.91  lakh
24.21-February-20171.02  lakh
Total 425.73  lakh
% Payment99.4 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 740   No. of Test Done : 760    No. of Test Passed : 740   No. of Test Failed : 20   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 88.01
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 137
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.06-10-2016Ch10/40Checking of cutting width for completionOm Prakash SinghSite SupervisorDSC2 R&B WB Dehradun See Pic
2.18-05-2016Ch10/24Protection work in progressOm Prakash SinghSite SupervisorDSC2 R&B WB Dehradun See Pic
3.15-05-2016Ch15/6Seal coat in progressOm Prakash SinghSite SupervisorDSC2 R&B WB Dehradun See Pic
4.15-05-2016Ch17/31P.c work in progressOm Prakash SinghSite SupervisorDSC2 R&B WB Dehradun See Pic
5.15-05-2016Ch8/12Seal coat in progressOm Prakash SinghSite SupervisorDSC2 R&B WB Dehradun See Pic
6.06-05-2016Ch17/12P.c work in progressOm Prakash SinghSite SupervisorDSC2 R&B WB Dehradun See Pic
7.06-05-2016Ch16/15P.c work in progressOm Prakash SinghSite SupervisorDSC2 R&B WB Dehradun See Pic
8.06-05-2016Ch16/18Seal coat in progressOm Prakash SinghSite SupervisorDSC2 R&B WB Dehradun See Pic
9.25-04-2016Ch-15.475Compaction of pcShivam KumarJEUDRP R&B Chakrata See Pic
10.25-04-2016Km 11/1Hill side cutting completedLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
11.23-04-2016Ch-18.325 kmChecking of undulations by ee and exen sir of pcShivam KumarJEUDRP R&B Chakrata See Pic
12.23-04-2016Ch-18.300 kmEe and ae sir Enspection with re dsc during pc workShivam KumarJEUDRP R&B Chakrata See Pic
13.23-04-2016Ch-18.325 kmEnspection of exen sir during pc workShivam KumarJEUDRP R&B Chakrata See Pic
14.23-04-2016Ch-18.325 kmPc work on progressShivam KumarJEUDRP R&B Chakrata See Pic
15.22-04-2016Ch- 18.425 kmPc work stopped due to rain fallShivam KumarJEUDRP R&B Chakrata See Pic
16.19-04-2016Ch-17.900kmMixing of pc materialShivam KumarJEUDRP R&B Chakrata See Pic
17.12-04-2016Ch 10/23Hill side cutting in progressOm Prakash SinghSite SupervisorDSC2 R&B WB Dehradun See Pic
18.04-04-2016Ch18/16Gradition of WBM G3 in progressOm Prakash SinghSite SupervisorDSC2 R&B WB Dehradun See Pic
19.30-03-2016Ch17//9Protection work in progressOm Prakash SinghSite SupervisorDSC2 R&B WB Dehradun See Pic
20.04-03-2016Ch17/8Bended wall in progressOm Prakash SinghSite SupervisorDSC2 R&B WB Dehradun See Pic