Submergence Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1585 |
Sanction Cost: |
433.01 lakh |
Length:
|
22.000 KM. |
District: |
Dehradun |
Block: |
Kalsi |
Constituency: |
Chakrata |
Circle: |
Tehri WB Circle |
DEA: |
DEA Chakrata |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 40
Package Name: 
UDRP/PWD/05/56/RD/040
Tender Date: 27-03-2014
Current Status: Agreement signed
Achieved on Date: 03-07-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/05/56/RD/040
Contractor Name: Dilawar Singh Contractor
|
Start Date: 07-07-2014
Intended Completion Date: 14-06-2016
Original End Date: 06-10-2015 |
Total Bond Cost: 54721659.09 (547.22 lakh)
Variation Cost: 17612476.88 (176.12 lakh) Hence Total Bond Cost is 72334135.97 (723.34 lakh)
|
Sub Project Cost: 307.23 lakh
Variation Cost of Sub Project: 12108926.62 (121.09 lakh)
Total Sub Project Cost:
428.32 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 4.85 KM | 60.32 | 15-07-2014 | 30-07-2014 | 4.85 KM | 4.85 KM | 14.16 | 60.32 | 2. | R/Wall, B/ Wall Type Protection works | 3058.00 m | 108.05 | 08-07-2014 | 23-12-2015 | 3058.00 m | 3058.00 m | 25.36 | 108.05 | 3. | GSB/RBI/G-1 | 4.00 KM | 18.55 | 15-07-2014 | 24-10-2015 | 4.00 KM | 4.00 KM | 4.35 | 18.55 | 4. | G-2 | 4.00 KM | 15.04 | 01-10-2014 | 08-11-2015 | 4.00 KM | 4.00 KM | 3.53 | 15.04 | 5. | G-3 | 4.00 KM | 15.53 | 16-12-2014 | 23-12-2015 | 4.00 KM | 4.00 KM | 3.65 | 15.53 | 6. | PC/CC i/c Prime Coat, Tack Coat | 4.00 KM | 38.82 | 15-04-2016 | 14-06-2016 | 4.00 KM | 4.00 KM | 9.11 | 38.82 | 7. | Cause Way | 15.00 No | 31.92 | 01-01-2015 | 08-12-2015 | 15.00 No | 15.00 No | 7.49 | 31.92 | 8. | Culverts/Scupper | 14.00 No | 65.99 | 15-01-2015 | 23-11-2015 | 14.00 No | 14.00 No | 15.49 | 65.99 | 9. | longitudinal Drain | 10400.00 m | 59.06 | 20-01-2015 | 08-11-2015 | 10400.00 m | 10400.00 m | 13.86 | 59.06 | 10. | Crash Barrier | 500.00 m | 10.79 | 31-01-2015 | 23-11-2015 | 500.00 m | 500.00 m | 2.53 | 10.79 | 11. | Road Furniture | 105.00 No | 1.97 | 15-01-2015 | 30-11-2015 | 105.00 No | 105.00 No | 0.46 | 1.97 |
Total Amount: |
426.04 |
|
100 |
426.04 |
|
Remarks:
Work Program Made On:
16-07-2014 } ?>
Updation of work program on:
15-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 10-September-2014 | 10.19 lakh | 2. | 30-September-2014 | 12.20 lakh | 3. | 31-October-2014 | 14.61 lakh | 4. | 31-December-2014 | 4.74 lakh | 5. | 03-January-2015 | 2.27 lakh | 6. | 12-February-2015 | 21.49 lakh | 7. | 30-March-2015 | 35.91 lakh | 8. | 31-March-2015 | 8.10 lakh | 9. | 11-June-2015 | 24.92 lakh | 10. | 15-July-2015 | 20.90 lakh | 11. | 16-July-2015 | 5.63 lakh | 12. | 20-August-2015 | 21.32 lakh | 13. | 30-September-2015 | 28.87 lakh | 14. | 09-November-2015 | 8.99 lakh | 15. | 30-November-2015 | 34.60 lakh | 16. | 23-December-2015 | 4.67 lakh | 17. | 15-February-2016 | 13.99 lakh | 18. | 05-March-2016 | 23.70 lakh | 19. | 30-March-2016 | 18.93 lakh | 20. | 28-April-2016 | 18.65 lakh | 21. | 20-May-2016 | 40.67 lakh | 22. | 30-June-2016 | 39.45 lakh | 23. | 30-December-2016 | 9.91 lakh | 24. | 21-February-2017 | 1.02 lakh |
Total |
425.73 lakh |
% Payment | 99.4 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 740 No. of Test Done : 760 No. of Test Passed : 740 No. of Test Failed : 20 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 88.01 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 137 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 06-10-2016 | Ch10/40 | Checking of cutting width for completion | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
2. | 18-05-2016 | Ch10/24 | Protection work in progress | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
3. | 15-05-2016 | Ch15/6 | Seal coat in progress | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
4. | 15-05-2016 | Ch17/31 | P.c work in progress | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
5. | 15-05-2016 | Ch8/12 | Seal coat in progress | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
6. | 06-05-2016 | Ch17/12 | P.c work in progress | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
7. | 06-05-2016 | Ch16/15 | P.c work in progress | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
8. | 06-05-2016 | Ch16/18 | Seal coat in progress | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
9. | 25-04-2016 | Ch-15.475 | Compaction of pc | Shivam Kumar | JE | UDRP R&B Chakrata | See Pic |
10. | 25-04-2016 | Km 11/1 | Hill side cutting completed | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
11. | 23-04-2016 | Ch-18.325 km | Checking of undulations by ee and exen sir of pc | Shivam Kumar | JE | UDRP R&B Chakrata | See Pic |
12. | 23-04-2016 | Ch-18.300 km | Ee and ae sir Enspection with re dsc during pc work | Shivam Kumar | JE | UDRP R&B Chakrata | See Pic |
13. | 23-04-2016 | Ch-18.325 km | Enspection of exen sir during pc work | Shivam Kumar | JE | UDRP R&B Chakrata | See Pic |
14. | 23-04-2016 | Ch-18.325 km | Pc work on progress | Shivam Kumar | JE | UDRP R&B Chakrata | See Pic |
15. | 22-04-2016 | Ch- 18.425 km | Pc work stopped due to rain fall | Shivam Kumar | JE | UDRP R&B Chakrata | See Pic |
16. | 19-04-2016 | Ch-17.900km | Mixing of pc material | Shivam Kumar | JE | UDRP R&B Chakrata | See Pic |
17. | 12-04-2016 | Ch 10/23 | Hill side cutting in progress | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
18. | 04-04-2016 | Ch18/16 | Gradition of WBM G3 in progress | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
19. | 30-03-2016 | Ch17//9 | Protection work in progress | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
20. | 04-03-2016 | Ch17/8 | Bended wall in progress | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
|
|