Nagthat Bisoi Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1544 |
Sanction Cost: |
291.29 lakh |
Length:
|
5.500 KM. |
District: |
Dehradun |
Block: |
Kalsi |
Constituency: |
Chakrata |
Circle: |
Tehri WB Circle |
DEA: |
DEA Chakrata |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 40
Package Name: 
UDRP/PWD/05/56/RD/040
Tender Date: 27-03-2014
Current Status: Agreement signed
Achieved on Date: 03-07-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/05/56/RD/040
Contractor Name: Dilawar Singh Contractor
|
Start Date: 07-07-2014
Intended Completion Date: 14-06-2016
Original End Date: 06-10-2015 |
Total Bond Cost: 54721659.09 (547.22 lakh)
Variation Cost: 17612476.88 (176.12 lakh) Hence Total Bond Cost is 72334135.97 (723.34 lakh)
|
Sub Project Cost: 238.25 lakh
Variation Cost of Sub Project: 5503550.25 (55.04 lakh)
Total Sub Project Cost:
293.29 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 9.00 KM | 5.54 | 15-07-2014 | 30-07-2014 | 9.00 KM | 9.00 KM | 1.9 | 5.54 | 2. | R/Wall, B/ Wall Type Protection works | 1750.00 m | 74.10 | 01-08-2014 | 31-12-2015 | 1750.00 m | 1750.00 m | 25.35 | 74.10 | 3. | GSB/RBI/G-1 | 5.25 KM | 25.78 | 16-07-2014 | 15-11-2015 | 5.25 KM | 5.25 KM | 8.82 | 25.78 | 4. | G-2 | 5.25 KM | 18.00 | 26-09-2014 | 30-11-2015 | 5.25 KM | 5.25 KM | 6.16 | 18.00 | 5. | G-3 | 5.25 KM | 20.00 | 26-11-2014 | 31-12-2015 | 5.25 KM | 5.25 KM | 6.84 | 20.00 | 6. | PC/CC i/c Prime Coat, Tack Coat | 6.00 KM | 60.45 | 01-05-2015 | 14-06-2016 | 6.00 KM | 6.00 KM | 20.68 | 60.45 | 7. | Cause Way | 3.00 No | 13.28 | 15-01-2015 | 25-05-2016 | 3.00 No | 3.00 No | 4.54 | 13.28 | 8. | Culverts/Scupper | 8.00 No | 13.32 | 15-01-2015 | 30-11-2015 | 8.00 No | 8.00 No | 4.56 | 13.32 | 9. | longitudinal Drain | 5325.00 m | 47.46 | 01-10-2014 | 30-11-2015 | 5325.00 m | 5325.00 m | 16.23 | 47.46 | 10. | Crash Barrier | 605.00 m | 13.15 | 31-01-2015 | 31-10-2015 | 605.00 m | 605.00 m | 4.5 | 13.15 | 11. | Road Furniture | 47.00 No | 1.28 | 15-01-2015 | 15-10-2015 | 47.00 No | 47.00 No | 0.44 | 1.28 |
Total Amount: |
292.36 |
|
100 |
292.36 |
|
Remarks:
Work Program Made On:
16-07-2014 } ?>
Updation of work program on:
15-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 10-September-2014 | 1.73 lakh | 2. | 30-September-2014 | 12.37 lakh | 3. | 31-October-2014 | 16.51 lakh | 4. | 31-December-2014 | 6.51 lakh | 5. | 03-January-2015 | 23.48 lakh | 6. | 12-February-2015 | 6.50 lakh | 7. | 31-March-2015 | 4.81 lakh | 8. | 11-June-2015 | 15.16 lakh | 9. | 15-July-2015 | 1.81 lakh | 10. | 16-July-2015 | 10.88 lakh | 11. | 27-August-2015 | 18.37 lakh | 12. | 30-September-2015 | 10.69 lakh | 13. | 09-November-2015 | 9.78 lakh | 14. | 30-November-2015 | 14.29 lakh | 15. | 23-December-2015 | 16.10 lakh | 16. | 15-February-2016 | 13.19 lakh | 17. | 05-March-2016 | 28.39 lakh | 18. | 28-April-2016 | 4.78 lakh | 19. | 20-May-2016 | 13.89 lakh | 20. | 30-June-2016 | 62.23 lakh | 21. | 30-December-2016 | 4.55 lakh | 22. | 21-February-2017 | 0.97 lakh |
Total |
296.99 lakh |
% Payment | 101.26 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 740 No. of Test Done : 760 No. of Test Passed : 740 No. of Test Failed : 20 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 87.78 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 78 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 25-05-2016 | Ch7/8 | P.c work in progress | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
2. | 25-05-2016 | Ch 5/22 | Protection work in progress | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
3. | 18-05-2016 | Ch7/24 | P.c work in progress | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
4. | 05-04-2016 | Ch. 5.800 km | G-3 gradations test | Shivam Kumar | JE | UDRP R&B Chakrata | See Pic |
5. | 30-03-2016 | Stock yard | Preparation for p.c | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
6. | 19-03-2016 | Ch5/0 | WBM G3 Rolling in progress | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
7. | 19-03-2016 | Ch5/6 | WBM G3 in progress | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
8. | 18-03-2016 | X/s-5/2 | G-3 laying and rolling | Shivam Kumar | JE | UDRP R&B Chakrata | See Pic |
9. | 05-03-2016 | Ch6/24 | Fdd test in progress | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
10. | 05-03-2016 | Ch6/1 | FDD Test in progress | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
11. | 04-03-2016 | Ch5/37 | Gradation of WBM G3 in progress | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
12. | 04-03-2016 | Ch2/38 | Bitumen stacking for pc | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
13. | 26-02-2016 | Ch5/34 | K.c drain base cc in progress | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
14. | 23-02-2016 | Ch 5/20 | Protection work of sliding zone complete | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
15. | 23-02-2016 | Km 4/9 | Depression and super elevation checked . | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
16. | 22-02-2016 | Ch4/8 | WBM G3 test in progress by T.L & A E world bank pwd | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
17. | 18-02-2016 | Ch5/11 | Slips clearance for band in progress | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
18. | 18-02-2016 | Ch5/15 | WBM G2 in progress | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
19. | 18-02-2016 | Ch4/16 | WBM G3 bed after final compaction | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
20. | 15-02-2016 | Ch5/7 | WBM G2 test in progress | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
|
|