Kunwala to Sainik Colony Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1517 |
Sanction Cost: |
19.36 lakh |
Length:
|
1.000 KM. |
District: |
Dehradun |
Block: |
Doiwala |
Constituency: |
Doiwala |
Circle: |
Tehri WB Circle |
DEA: |
DEA Chakrata |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 5
Package Name: 
UDRP/PWD/05/53/RD/005
Tender Date: 22-02-2014
Current Status: Agreement signed
Achieved on Date: 25-08-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/05/53/RD/005
Contractor Name: Vijay Engineering Associates
|
Start Date: 01-09-2014
Intended Completion Date: 30-04-2016
Original End Date: 31-12-2015 |
Total Bond Cost: 54378925.06 (543.79 lakh)
Variation Cost: 19270279.78 (192.7 lakh) Hence Total Bond Cost is 73649204.84 (736.49 lakh)
|
Sub Project Cost: 10.87 lakh
Variation Cost of Sub Project: 480135.49 (4.8 lakh)
Total Sub Project Cost:
15.67 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | R/Wall, B/ Wall Type Protection works | 250.00 m | 19.27 | 21-10-2014 | 30-04-2016 | 250.00 m | 250.00 m | 100 | 19.27 |
Total Amount: |
19.27 |
|
100 |
19.27 |
|
Remarks:
No Remarks
Work Program Made On:
23-09-2014 } ?>
Updation of work program on:
16-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 22-May-2015 | 1.33 lakh | 2. | 31-July-2015 | 4.65 lakh | 3. | 23-January-2016 | 2.25 lakh | 4. | 29-February-2016 | 4.14 lakh | 5. | 08-August-2016 | 3.22 lakh | 6. | 04-February-2017 | 0.12 lakh |
Total |
15.71 lakh |
% Payment | 100.26 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 504 No. of Test Done : 514 No. of Test Passed : 504 No. of Test Failed : 10 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 10 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 31-03-2017 | Ch-0/38-0/39 | General inspection of kuwanwala to sainik colony Motor Road | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
2. | 02-03-2016 | Starting of road | Informatory board | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
3. | 02-03-2016 | At the beginning of nala | Protection work of the road | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
4. | 08-02-2016 | Km1 | Protection work of road as erosion occurred at the bottom of the road. | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
5. | 24-01-2016 | Km1 | Protection work of the road | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
6. | 22-08-2015 | Km1 | Protection work of road | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
7. | 07-07-2015 | Protection work of left bank | Kuanwala sanik colony rd protection work | L M Benjwal | AE | DEA WB Chakrata | See Pic |
8. | 07-07-2015 | Kuanwala sanik colony protection work | Rwall on the left bank | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
9. | 11-05-2015 | Sainik colony km1 | R wall | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
10. | 06-04-2015 | Junction of Harrawala sanik colony rd | Protection work with RR | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
|
|