Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Koruba Kwarana Mangrauli MR Work Completed
Project: UDRP-RB UID: 1514 Sanction Cost: 605.05  lakh Length: 7.000 KM.
District: Dehradun Block: Chakrata Constituency: Chakrata Circle: Tehri WB Circle
DEA: DEA Chakrata DSC: Egis International DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 72        Package Name:  UDRP/PWD/05/56/RD/062        Tender Date: 20-11-2014        Current Status: Agreement signed        Achieved on Date: 05-08-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/05/56/RD/062      Contractor Name: Amit Joshi
Start Date:  12-08-2015      Intended Completion Date:  04-05-2017      Original End Date:  11-11-2016
Total Bond Cost: 43489374.46 (434.89 lakh)        Variation Cost: 9977920.85 (99.78 lakh)    Hence Total Bond Cost is   53467295.31 (534.67 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 43490 for 2 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence7.00 KM85.6412-08-201515-02-20177.00 KM7.00 KM16.7385.64
2.R/Wall, B/ Wall Type Protection works1036.00 m105.8812-08-201525-01-20171036.00 m1036.00 m20.68105.88
3.GSB/RBI/G-17.00 KM46.7812-08-201515-07-20167.00 KM7.00 KM9.1446.78
4.G-27.00 KM36.2709-09-201505-08-20167.00 KM7.00 KM7.0836.27
5.G-37.00 KM38.4410-10-201515-12-20167.00 KM7.00 KM7.5138.44
6.PC/CC i/c Prime Coat, Tack Coat7.00 KM82.5801-05-201604-05-20177.00 KM7.00 KM16.1382.58
7.Cause Way5.00 No5.9812-11-201530-04-20175.00 No5.00 No1.175.98
8.Culverts/Scupper 15.00 No29.8504-09-201515-12-201615.00 No15.00 No5.8329.85
9.longitudinal Drain7000.00 m58.5116-06-201604-05-20177000.00 m7000.00 m11.4358.51
10.Crash Barrier345.00 m19.5316-06-201604-05-2017345.00 m345.00 m3.8119.53
11.Road Furniture35.00 No2.5810-01-201604-05-201735.00 No35.00 No0.52.58
Total Amount: 512.04 100   512.04
Remarks: No Remarks       Work Program Made On: 11-09-2015        Updation of work program on: 22-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.07-November-201549.53  lakh
2.19-December-201546.93  lakh
3.29-January-201635.01  lakh
4.08-March-201617.33  lakh
5.12-April-201639.45  lakh
6.24-May-201619.19  lakh
7.12-August-201638.13  lakh
8.30-September-201612.87  lakh
9.28-October-201646.36  lakh
10.07-January-201730.14  lakh
11.28-February-201732.50  lakh
12.24-March-201761.49  lakh
13.08-June-201757.35  lakh
14.31-July-201740.55  lakh
Total 526.83  lakh
% Payment 98.54 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 311   No. of Test Done : 326    No. of Test Passed : 311   No. of Test Failed : 15   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.94
Number of Notice(s) issued: 59

Mobile Pic Upload

Number of Pics Available on Web Repository: 91
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.27-04-2017Ch 5/12-5/13Laying temperature of premix carpet Remark- acceptableDhwajvir SinghJEUDRP R&B Karnprayag See Pic
2.01-04-20173/29Pc work under progressLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
3.06-03-2017Ch 3/1-3/2Discuss with SE sir after Checking of kutcha drain and causeway.Dhwajvir SinghJEUDRP R&B Chakrata See Pic
4.25-02-2017Ch 4/1-4/2Laying of WBM G-3Dhwajvir SinghJEUDRP R&B Chakrata See Pic
5.20-02-20170/13Checking of measurements and quality of plum, found okLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
6.11-02-2017Ch 0/15-0/16Banded R/W complete and satisfactoryDhwajvir SinghJEUDRP R&B Chakrata See Pic
7.24-10-2016Km1Public meetingLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
8.05-10-2016Ch 0/15-0/16Checking of crust thickness and found okDhwajvir SinghJEUDRP R&B Chakrata See Pic
9.29-09-2016Km 1Pc work under progressLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
10.28-09-2016Ch 1/14-1/15Banded R/W is okDhwajvir SinghJEUDRP R&B Chakrata See Pic
11.28-09-2016Ch 0/2-0/3Laing of PC is satisfactoryDhwajvir SinghJEUDRP R&B Chakrata See Pic
12.28-09-2016Ch 0/2-0/3Laying of prime coat is okDhwajvir SinghJEUDRP R&B Chakrata See Pic
13.28-09-2016Cube testing of M-30 strength at ch 0/4Strength of cube is found okDhwajvir SinghJEUDRP R&B Chakrata See Pic
14.28-09-2016Ch 6/11WBM G-3 work have completed at ch 6/11 to 6/21and found satisfactoryDhwajvir SinghJEUDRP R&B Chakrata See Pic
15.27-09-2016At LaboratoryPC aggregate gradation checkingRajan NautiyalJEUDRP R&B Chakrata See Pic
16.27-09-2016At ch 0/2 - 0/3Seal coat work in progressRajan NautiyalJEUDRP R&B Chakrata See Pic
17.27-09-2016At ch 0/2PC work is in progressRajan NautiyalJEUDRP R&B Chakrata See Pic
18.29-08-2016Ch 3/23-3/24R/w under progress and quality of work is satisfactoryDhwajvir SinghJEUDRP R&B Chakrata See Pic
19.01-07-2016Ch 0/6-0/7WBM G-3 completedDhwajvir SinghJEUDRP R&B Chakrata See Pic
20.29-06-2016Km 3Slip clearance under progress.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic