Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Dharkot Tali Motor Road Work Completed
Project: UDRP-RB UID: 1465 Sanction Cost: 12.69  lakh Length: 4.000 KM.
District: Dehradun Block: Doiwala Constituency: Doiwala Circle: Tehri WB Circle
DEA: DEA Chakrata DSC: Egis International DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 5        Package Name:  UDRP/PWD/05/53/RD/005        Tender Date: 22-02-2014        Current Status: Agreement signed        Achieved on Date: 25-08-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/05/53/RD/005      Contractor Name: Vijay Engineering Associates
Start Date:  01-09-2014      Intended Completion Date:  30-04-2016      Original End Date:  31-12-2015
Total Bond Cost: 54378925.06 (543.79 lakh)        Variation Cost: 19270279.78 (192.7 lakh)    Hence Total Bond Cost is   73649204.84 (736.49 lakh) 
Sub Project Cost: 13.41  lakh        Variation Cost of Sub Project: 185567.87  (1.86 lakh)       Total Sub Project Cost:   15.27 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works170.00 m12.5101-12-201427-11-2015170.00 m170.00 m92.7412.51
2.Culverts/Scupper 1.00 No0.9801-04-201531-07-20151.00 No1.00 No7.270.98
Total Amount: 13.49 100   13.49
Remarks: No Remarks       Work Program Made On: 23-09-2014        Updation of work program on: 22-07-2016       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-March-20154.00  lakh
2.22-May-20150.76  lakh
3.31-July-20153.06  lakh
4.06-November-20151.82  lakh
5.29-February-20160.32  lakh
6.31-March-20160.74  lakh
7.04-February-20170.12  lakh
8.30-June-20170.12  lakh
Total 10.94  lakh
% Payment71.64 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 504   No. of Test Done : 514    No. of Test Passed : 504   No. of Test Failed : 10   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 4
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.25-12-2015Km3Protection work of bridgeLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
2.25-12-2015Km1RwallLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
3.23-12-2015Km 3Protection work by wire cratesDhwajvir SinghJEUDRP R&B Chakrata See Pic
4.23-12-2015Ch 0.00 at startingInformatory board.Dhwajvir SinghJEUDRP R&B Chakrata See Pic