Dharkot Tali Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1465 |
Sanction Cost: |
12.69 lakh |
Length:
|
4.000 KM. |
District: |
Dehradun |
Block: |
Doiwala |
Constituency: |
Doiwala |
Circle: |
Tehri WB Circle |
DEA: |
DEA Chakrata |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 5
Package Name: 
UDRP/PWD/05/53/RD/005
Tender Date: 22-02-2014
Current Status: Agreement signed
Achieved on Date: 25-08-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/05/53/RD/005
Contractor Name: Vijay Engineering Associates
|
Start Date: 01-09-2014
Intended Completion Date: 30-04-2016
Original End Date: 31-12-2015 |
Total Bond Cost: 54378925.06 (543.79 lakh)
Variation Cost: 19270279.78 (192.7 lakh) Hence Total Bond Cost is 73649204.84 (736.49 lakh)
|
Sub Project Cost: 13.41 lakh
Variation Cost of Sub Project: 185567.87 (1.86 lakh)
Total Sub Project Cost:
15.27 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | R/Wall, B/ Wall Type Protection works | 170.00 m | 12.51 | 01-12-2014 | 27-11-2015 | 170.00 m | 170.00 m | 92.74 | 12.51 | 2. | Culverts/Scupper | 1.00 No | 0.98 | 01-04-2015 | 31-07-2015 | 1.00 No | 1.00 No | 7.27 | 0.98 |
Total Amount: |
13.49 |
|
100 |
13.49 |
|
Remarks:
No Remarks
Work Program Made On:
23-09-2014 } ?>
Updation of work program on:
22-07-2016
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-March-2015 | 4.00 lakh | 2. | 22-May-2015 | 0.76 lakh | 3. | 31-July-2015 | 3.06 lakh | 4. | 06-November-2015 | 1.82 lakh | 5. | 29-February-2016 | 0.32 lakh | 6. | 31-March-2016 | 0.74 lakh | 7. | 04-February-2017 | 0.12 lakh | 8. | 30-June-2017 | 0.12 lakh |
Total |
10.94 lakh |
% Payment | 71.64 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 504 No. of Test Done : 514 No. of Test Passed : 504 No. of Test Failed : 10 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 4 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 25-12-2015 | Km3 | Protection work of bridge | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
2. | 25-12-2015 | Km1 | Rwall | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
3. | 23-12-2015 | Km 3 | Protection work by wire crates | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
4. | 23-12-2015 | Ch 0.00 at starting | Informatory board. | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
|
|