Basantpur Madsi Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1440 |
Sanction Cost: |
144.76 lakh |
Length:
|
5.000 KM. |
District: |
Dehradun |
Block: |
Doiwala |
Constituency: |
Doiwala |
Circle: |
Tehri WB Circle |
DEA: |
DEA Chakrata |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 5
Package Name: 
UDRP/PWD/05/53/RD/005
Tender Date: 22-02-2014
Current Status: Agreement signed
Achieved on Date: 25-08-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/05/53/RD/005
Contractor Name: Vijay Engineering Associates
|
Start Date: 01-09-2014
Intended Completion Date: 30-04-2016
Original End Date: 31-12-2015 |
Total Bond Cost: 54378925.06 (543.79 lakh)
Variation Cost: 19270279.78 (192.7 lakh) Hence Total Bond Cost is 73649204.84 (736.49 lakh)
|
Sub Project Cost: 128.67 lakh
Variation Cost of Sub Project: 4001355.50 (40.01 lakh)
Total Sub Project Cost:
168.68 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | R/Wall, B/ Wall Type Protection works | 398.00 m | 36.43 | 01-10-2014 | 30-03-2016 | 398.00 m | 398.00 m | 21.57 | 36.43 | 2. | G-3 | 0.05 KM | 11.48 | 01-03-2015 | 30-04-2015 | 0.05 KM | 0.05 KM | 6.8 | 11.48 | 3. | PC/CC i/c Prime Coat, Tack Coat | 6.50 KM | 51.39 | 01-05-2015 | 30-04-2016 | 6.50 KM | 6.50 KM | 30.42 | 51.39 | 4. | Cause Way | 1.00 No | 4.42 | 10-11-2014 | 30-04-2015 | 1.00 No | 1.00 No | 2.62 | 4.42 | 5. | Culverts/Scupper | 9.00 No | 48.32 | 10-09-2014 | 30-04-2016 | 9.00 No | 9.00 No | 28.6 | 48.32 | 6. | longitudinal Drain | 1400.00 m | 14.61 | 01-06-2015 | 25-03-2016 | 1400.00 m | 1400.00 m | 8.65 | 14.61 | 7. | Crash Barrier | 106.00 m | 2.28 | 01-09-2015 | 25-02-2016 | 106.00 m | 106.00 m | 1.35 | 2.28 |
Total Amount: |
168.93 |
|
100 |
168.93 |
|
Remarks:
No Remarks
Work Program Made On:
23-09-2014 } ?>
Updation of work program on:
17-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-December-2014 | 2.84 lakh | 2. | 18-February-2015 | 7.19 lakh | 3. | 31-March-2015 | 5.59 lakh | 4. | 22-May-2015 | 1.30 lakh | 5. | 06-July-2015 | 13.39 lakh | 6. | 31-July-2015 | 4.30 lakh | 7. | 23-September-2015 | 9.20 lakh | 8. | 29-February-2016 | 12.86 lakh | 9. | 31-March-2016 | 13.93 lakh | 10. | 06-May-2016 | 17.02 lakh | 11. | 08-August-2016 | 47.89 lakh | 12. | 04-February-2017 | 1.89 lakh | 13. | 30-June-2017 | 0.77 lakh |
Total |
138.17 lakh |
% Payment | 81.91 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 504 No. of Test Done : 514 No. of Test Passed : 504 No. of Test Failed : 10 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 40 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 04-10-2016 | Km 7 HM-6 | Inspection of PC by SE,EE,AE and TL | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
2. | 06-05-2016 | Ch 2/6 | Checking of thickness of PC | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
3. | 06-05-2016 | Ch 2/11 | PC work under progress | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
4. | 28-04-2016 | Ch 3/32 | PC and seal coat completed | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
5. | 25-04-2016 | Ch 3/30 | Laying of PC | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
6. | 25-04-2016 | Ch 3/35 | Rolling of PC | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
7. | 25-04-2016 | Km1 | WB's team visited the site for EMP verification | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
8. | 25-04-2016 | Km 7 | Undulation checking | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
9. | 12-04-2016 | Ch 7 th Km | SE WB Tehri visit with EE WB Chakrata AE WB Chakrata fo4 checking of Bitumen PC work | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
10. | 12-04-2016 | Km 2 | Site inspection by SE WB PWD TEHRI | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
11. | 12-04-2016 | Km 7 ch 6/28 | Joint Inspection of PC work by SE Sir, EE sir and AE sir | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
12. | 05-04-2016 | Km2 | Cc drain complete | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
13. | 05-04-2016 | Km 7 | Seal coat under progress | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
14. | 05-04-2016 | Km 7 | Premix carpet surfacing | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
15. | 30-03-2016 | Km 7 | Preparation for premix carpet going on. | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
16. | 30-03-2016 | Km 2.95 | Constriction of cc drain parapets under progress | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
17. | 30-03-2016 | 0/31 | Base Repairing of scupper completed | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
18. | 04-03-2016 | Km 4/11 | Construction of parapets, kc drain in progress | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
19. | 04-03-2016 | Km 2 | Repairing of floor of old culvert | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
20. | 04-03-2016 | Km4/13 | Erection of crash barrier | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
|
|