Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Thano Bhogpur Road Work Completed
Project: UDRP-RB UID: 1423 Sanction Cost: 50.11  lakh Length: 1.000 KM.
District: Dehradun Block: Raipur Constituency: Doiwala Circle: Tehri WB Circle
DEA: DEA Chakrata DSC: Egis International DSC Scope: only Supervision Type: ODR
Procurement:
Package No.: 5        Package Name:  UDRP/PWD/05/53/RD/005        Tender Date: 22-02-2014        Current Status: Agreement signed        Achieved on Date: 25-08-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/05/53/RD/005      Contractor Name: Vijay Engineering Associates
Start Date:  01-09-2014      Intended Completion Date:  30-04-2016      Original End Date:  31-12-2015
Total Bond Cost: 54378925.06 (543.79 lakh)        Variation Cost: 19270279.78 (192.7 lakh)    Hence Total Bond Cost is   73649204.84 (736.49 lakh) 
Sub Project Cost: 12.60  lakh        Variation Cost of Sub Project: 3201519.41  (32.02 lakh)       Total Sub Project Cost:   44.62 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works489.00 m25.0012-10-201430-04-2016489.00 m489.00 m50.2825.00
2.Cause Way2.00 No24.7210-11-201428-11-20152.00 No2.00 No49.7224.72
Total Amount: 49.72 100   49.72
Remarks: Causeway work is completed and diversion of main stream is in progress       Work Program Made On: 23-09-2014        Updation of work program on: 22-07-2016       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.18-February-20158.73  lakh
2.23-September-20153.15  lakh
3.06-November-20157.80  lakh
4.19-December-201515.42  lakh
5.23-January-20167.38  lakh
6.08-August-20161.42  lakh
7.04-February-20170.37  lakh
8.30-June-20170.00  lakh
Total 44.27  lakh
% Payment99.22 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 504   No. of Test Done : 514    No. of Test Passed : 504   No. of Test Failed : 10   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 13
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.09-02-2016Km 3Causeway completedLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
2.20-12-2015Km 2Plum concrete for protection workLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
3.19-12-2015Km 2Fixing of new Informatory board.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
4.17-11-2015Km3Causeway under progressR K ChauhanunknownDEA WB chakrata See Pic
5.26-10-2015Chainage 2kmConstriction of causewayLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
6.20-10-2015Km 3Constriction of causeway M10 under progressLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
7.17-10-2015Km 3Constriction of causewayLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
8.09-08-2015Km3Flood on Thano bhogpur causewayLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
9.08-06-2015DKm 3 causewayConstriction of causewayLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
10.05-12-2014Km 3 causewayRepairing of causewayLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
11.04-12-2014Km 3 causewayReconstruction of causewayLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
12.27-08-2014At km 3 CausewayCausewayLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
13.27-08-2014Km 3 causewayExtra damaged portion of roadLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic