Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Punav-Sipty Nayari Motor Road Work Completed
Project: UDRP-RB UID: 1355 Sanction Cost: 429.21  lakh Length: 8.000 KM.
District: Champawat Block: Champawat Constituency: Champawat Circle: Pithoragarh WB Circle
DEA: DEA Champawat DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 47        Package Name:  UDRP/PWD/10/19/RD/047        Tender Date: 19-04-2014        Current Status: Agreement signed        Achieved on Date: 13-08-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/10/19/RD/047      Contractor Name: Panchghati Constructions
Start Date:  20-08-2014      Intended Completion Date:  11-01-2016      Original End Date:  19-11-2015
Total Bond Cost: 46317208.08 (463.17 lakh)        Variation Cost: -6781420.28 (-67.81 lakh)    Hence Total Bond Cost is   39535787.8 (395.36 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 1157950 for 50 days        LD Analysis for Milestone2: calculated LD is Rs 2176946 for 94 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.29 KM5.2305-05-201525-10-20150.29 KM0.29 KM1.325.23
2.R/Wall, B/ Wall Type Protection works1843.00 m172.6425-08-201431-10-20151843.00 m1843.00 m43.67172.64
3.GSB/RBI/G-15.40 KM37.3510-01-201531-03-20155.40 KM5.40 KM9.4537.35
4.G-25.40 KM27.8303-02-201531-10-20155.40 KM5.40 KM7.0427.83
5.G-35.40 KM29.3201-04-201530-11-20155.40 KM5.40 KM7.4229.32
6.PC/CC i/c Prime Coat, Tack Coat5.40 KM58.3615-04-201515-12-20155.40 KM5.40 KM14.7658.36
7.Cause Way1.00 No2.4020-09-201531-10-20151.00 No1.00 No0.612.40
8.Culverts/Scupper 16.00 No23.3801-09-201402-12-201516.00 No16.00 No5.9123.38
9.longitudinal Drain5250.00 m9.6301-07-201502-12-20155250.00 m5250.00 m2.449.63
10.Crash Barrier404.00 m8.3902-12-201511-01-2016404.00 m404.00 m2.128.39
11.Parapet260.00 No6.5601-12-201511-01-2016260.00 No260.00 No1.666.56
12.Road Furniture101.00 No1.8902-01-201611-01-2016101.00 No101.00 No0.481.89
13.Other Allied Works & Finishing Work 1.00 Job12.3921-08-201401-11-20151.00 Job1.00 Job3.1312.39
Total Amount: 395.37 100   395.37
Remarks: No Remarks       Work Program Made On: 01-10-2014        Updation of work program on: 20-11-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.27-February-201558.11  lakh
2.31-March-201537.53  lakh
3.16-June-201525.00  lakh
4.30-June-201528.00  lakh
5.31-July-20156.50  lakh
6.29-September-201539.18  lakh
7.31-October-201542.00  lakh
8.31-August-2016155.98  lakh
Total 392.3  lakh
% Payment 99.21 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 337   No. of Test Done : 337    No. of Test Passed : 337   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.14
Number of Notice(s) issued: 58

Mobile Pic Upload

Number of Pics Available on Web Repository: 195
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.12-08-20164+200Tree PlantationManjeet SainiJEUDRP R&B Champawat See Pic
2.12-08-20164+900Tree plantationManjeet SainiJEUDRP R&B Champawat See Pic
3.12-08-20164+900Tree PlantationManjeet SainiJEUDRP R&B Champawat See Pic
4.11-08-20165+400Tree plantationDevki Nandan SharmaREDSC4 R&B WB Champawat See Pic
5.20-05-20164+100CatchpitDevki Nandan SharmaREDSC4 R&B WB Champawat See Pic
6.19-05-20160+000World bank mission on site visitSanjeev KumarJEUDRP R&B Champawat See Pic
7.19-05-20160+400World bank mission on site visitSanjeev KumarJEUDRP R&B Champawat See Pic
8.19-05-20160+400World bank mission on site visitSanjeev KumarJEUDRP R&B Champawat See Pic
9.19-05-20160+100World bank mission on site visitSanjeev KumarJEUDRP R&B Champawat See Pic
10.19-05-20160+100World bank mission on site visitSanjeev KumarJEUDRP R&B Champawat See Pic
11.19-05-20160+080World bank mission on site visitSanjeev KumarJEUDRP R&B Champawat See Pic
12.19-05-20160+070World bank mission on site visitSanjeev KumarJEUDRP R&B Champawat See Pic
13.19-05-20160+040World bank mission on site visitSanjeev KumarJEUDRP R&B Champawat See Pic
14.19-05-20160+050World bank mission on site visitSanjeev KumarJEUDRP R&B Champawat See Pic
15.19-05-20160+000World bank mission on site visitSanjeev KumarJEUDRP R&B Champawat See Pic
16.19-05-20160+000World bank mission on site visitSanjeev KumarJEUDRP R&B Champawat See Pic
17.19-05-20160+000World bank mission on site visitSanjeev KumarJEUDRP R&B Champawat See Pic
18.19-05-20160+000World bank mission on site visitSanjeev KumarJEUDRP R&B Champawat See Pic
19.19-05-20160+000World bank mission on site visitSanjeev KumarJEUDRP R&B Champawat See Pic
20.10-05-20160+150Site inspection by CE Sir with SE/EE With TL/RE DSC4Devki Nandan SharmaREDSC4 R&B WB Champawat See Pic