Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Barakot Simalkhet MR Work Completed
Project: UDRP-RB UID: 1306 Sanction Cost: 938.94  lakh Length: 25.000 KM.
District: Champawat Block: Barakot Constituency: Lohaghat Circle: Pithoragarh WB Circle
DEA: DEA Champawat DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 46        Package Name:  UDRP/PWD/10/18/RD/046        Tender Date: 19-04-2014        Current Status: Agreement signed        Achieved on Date: 18-12-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/10/18/RD/046      Contractor Name: Parwataiya Constructions
Start Date:  25-12-2014      Intended Completion Date:  31-08-2016      Original End Date:  24-03-2016
Total Bond Cost: 76722979.51 (767.23 lakh)        Variation Cost: 21842145.84 (218.42 lakh)    Hence Total Bond Cost is   98565125.35 (985.65 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.36 KM19.5905-02-201510-01-20160.36 KM0.36 KM1.9919.59
2.R/Wall, B/ Wall Type Protection works2808.00 m271.3108-01-201515-08-20162808.00 m2808.00 m27.53271.31
3.GSB/RBI/G-11.89 KM12.7115-06-201510-06-20161.89 KM1.89 KM1.2912.71
4.G-23.06 KM28.4101-01-201512-06-20163.06 KM3.06 KM2.8828.41
5.G-36.16 KM42.0601-04-201520-08-20166.16 KM6.16 KM4.2742.06
6.PC/CC i/c Prime Coat, Tack Coat25.00 KM355.0401-02-201525-08-201625.00 KM25.00 KM36.02355.04
7.Cause Way17.00 No70.9001-04-201515-08-201617.00 No17.00 No7.1970.90
8.Culverts/Scupper 41.00 No81.0201-04-201515-08-201641.00 No41.00 No8.2281.02
9.longitudinal Drain23600.00 m55.2101-07-201520-08-201623600.00 m23600.00 m5.655.21
10.Crash Barrier0.00 m0.0020-06-201620-06-20160.00 m0.00 m00.00
11.Parapet1500.00 No36.3621-12-201520-08-20161500.00 No1500.00 No3.6936.36
12.Road Furniture359.00 No6.5801-02-201630-08-2016359.00 No359.00 No0.676.58
13.Other Allied Works & Finishing Work 1.00 Job6.4931-12-201431-08-20161.00 Job1.00 Job0.666.49
Total Amount: 985.68 100   985.68
Remarks: No Remarks       Work Program Made On: 27-01-2015        Updation of work program on: 20-11-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-March-201546.11  lakh
2.16-June-201522.00  lakh
3.20-June-201546.00  lakh
4.30-June-201543.00  lakh
5.31-July-20158.19  lakh
6.05-August-201537.00  lakh
7.29-September-201592.55  lakh
8.31-October-201550.00  lakh
9.06-November-201526.00  lakh
10.27-November-201510.00  lakh
11.29-December-201564.07  lakh
12.31-December-201533.08  lakh
13.20-January-201627.19  lakh
14.31-January-201618.00  lakh
15.29-February-201628.72  lakh
16.28-March-201611.10  lakh
17.30-March-201617.00  lakh
18.19-April-20167.33  lakh
19.30-April-201625.00  lakh
20.16-May-20166.89  lakh
21.31-May-201662.59  lakh
22.28-June-2016158.24  lakh
23.24-August-201654.03  lakh
24.30-August-201612.42  lakh
25.26-October-201678.32  lakh
Total 984.83  lakh
% Payment 99.91 %
Advance Amount:  71.00  lakh        Recovered Amount:  71.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 2026   No. of Test Done : 2027    No. of Test Passed : 2021   No. of Test Failed : 6   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 92.64
Number of Notice(s) issued: 60

Mobile Pic Upload

Number of Pics Available on Web Repository: 944
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.23-09-201612+550Site inspection by DPM Sir.Mansoon damages.Devki Nandan SharmaREDSC4 R&B WB Champawat See Pic
2.23-09-201613+900Site inspection by DPMSirDevki Nandan SharmaREDSC4 R&B WB Champawat See Pic
3.14-09-20164+325Site inspection by DPM Sir with AE Sir, JE wb pwd champawat , RE sir & contractorBaldev AryaSite SupervisorDSC4 R&B WB Pithoragar See Pic
4.14-09-201610+500Site inspection by DPM Sir with AE Sir, JE wb pwd champawat, RE Sir & contractorBaldev AryaSite SupervisorDSC4 R&B WB Pithoragar See Pic
5.14-09-201612+550Site inspection by DPM Sir with AE Sir, JE wb pwd champawat, RE Sir, contractorBaldev AryaSite SupervisorDSC4 R&B WB Pithoragar See Pic
6.14-09-20164+325Site inspection by DPM sir with AE sir, RE & contractorManjeet SainiJEUDRP R&B Champawat See Pic
7.14-09-201613+900Site inspection by DPM sir with AE sir, RE & contractorManjeet SainiJEUDRP R&B Champawat See Pic
8.14-09-201613+900Site inspection by DPM Sir with AE Sir, JE wb pwd champawat, RE Sir & contractorBaldev AryaSite SupervisorDSC4 R&B WB Pithoragar See Pic
9.22-08-201619+575R/Wall with Toe wall & Scupper.Narendra Kumar PantEEUDRP R&B Champawat See Pic
10.22-08-201614+200R/Wall with Toe Wall.Narendra Kumar PantEEUDRP R&B Champawat See Pic
11.22-08-201612+000KM Stone foundation RCCDevki Nandan SharmaREDSC4 R&B WB Champawat See Pic
12.22-08-201619+575Wire crates at toe wallDevki Nandan SharmaREDSC4 R&B WB Champawat See Pic
13.22-08-201619+575Slab shuttering for slab culvertDevki Nandan SharmaREDSC4 R&B WB Champawat See Pic
14.22-08-201619+575Banded Retaining wall with plum concrete with RR 1:5 masonry toe wall of wire cratesDevki Nandan SharmaREDSC4 R&B WB Champawat See Pic
15.22-08-201614+200Banded Retaining wall/plum toe wallDevki Nandan SharmaREDSC4 R&B WB Champawat See Pic
16.22-08-201611+200Damages on road and retaining / coollie wall due to rain and land slidesDevki Nandan SharmaREDSC4 R&B WB Champawat See Pic
17.22-08-201610+850Road damaged 100m length aprox.due to heavy rain slips and land slidesDevki Nandan SharmaREDSC4 R&B WB Champawat See Pic
18.22-08-201610+100Slips damaging roadDevki Nandan SharmaREDSC4 R&B WB Champawat See Pic
19.07-08-201614+200retaining wall in progressSanjeev KumarJEUDRP R&B Champawat See Pic
20.10-07-201617+960Kc drain in progressManjeet SainiJEUDRP R&B Champawat See Pic