Barakot Simalkhet MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
1306 |
Sanction Cost: |
938.94 lakh |
Length:
|
25.000 KM. |
District: |
Champawat |
Block: |
Barakot |
Constituency: |
Lohaghat |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Champawat |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 46
Package Name: 
UDRP/PWD/10/18/RD/046
Tender Date: 19-04-2014
Current Status: Agreement signed
Achieved on Date: 18-12-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/10/18/RD/046
Contractor Name: Parwataiya Constructions
|
Start Date: 25-12-2014
Intended Completion Date: 31-08-2016
Original End Date: 24-03-2016 |
Total Bond Cost: 76722979.51 (767.23 lakh)
Variation Cost: 21842145.84 (218.42 lakh) Hence Total Bond Cost is 98565125.35 (985.65 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.36 KM | 19.59 | 05-02-2015 | 10-01-2016 | 0.36 KM | 0.36 KM | 1.99 | 19.59 | 2. | R/Wall, B/ Wall Type Protection works | 2808.00 m | 271.31 | 08-01-2015 | 15-08-2016 | 2808.00 m | 2808.00 m | 27.53 | 271.31 | 3. | GSB/RBI/G-1 | 1.89 KM | 12.71 | 15-06-2015 | 10-06-2016 | 1.89 KM | 1.89 KM | 1.29 | 12.71 | 4. | G-2 | 3.06 KM | 28.41 | 01-01-2015 | 12-06-2016 | 3.06 KM | 3.06 KM | 2.88 | 28.41 | 5. | G-3 | 6.16 KM | 42.06 | 01-04-2015 | 20-08-2016 | 6.16 KM | 6.16 KM | 4.27 | 42.06 | 6. | PC/CC i/c Prime Coat, Tack Coat | 25.00 KM | 355.04 | 01-02-2015 | 25-08-2016 | 25.00 KM | 25.00 KM | 36.02 | 355.04 | 7. | Cause Way | 17.00 No | 70.90 | 01-04-2015 | 15-08-2016 | 17.00 No | 17.00 No | 7.19 | 70.90 | 8. | Culverts/Scupper | 41.00 No | 81.02 | 01-04-2015 | 15-08-2016 | 41.00 No | 41.00 No | 8.22 | 81.02 | 9. | longitudinal Drain | 23600.00 m | 55.21 | 01-07-2015 | 20-08-2016 | 23600.00 m | 23600.00 m | 5.6 | 55.21 | 10. | Crash Barrier | 0.00 m | 0.00 | 20-06-2016 | 20-06-2016 | 0.00 m | 0.00 m | 0 | 0.00 | 11. | Parapet | 1500.00 No | 36.36 | 21-12-2015 | 20-08-2016 | 1500.00 No | 1500.00 No | 3.69 | 36.36 | 12. | Road Furniture | 359.00 No | 6.58 | 01-02-2016 | 30-08-2016 | 359.00 No | 359.00 No | 0.67 | 6.58 | 13. | Other Allied Works & Finishing Work | 1.00 Job | 6.49 | 31-12-2014 | 31-08-2016 | 1.00 Job | 1.00 Job | 0.66 | 6.49 |
Total Amount: |
985.68 |
|
100 |
985.68 |
|
Remarks:
No Remarks
Work Program Made On:
27-01-2015 } ?>
Updation of work program on:
20-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-March-2015 | 46.11 lakh | 2. | 16-June-2015 | 22.00 lakh | 3. | 20-June-2015 | 46.00 lakh | 4. | 30-June-2015 | 43.00 lakh | 5. | 31-July-2015 | 8.19 lakh | 6. | 05-August-2015 | 37.00 lakh | 7. | 29-September-2015 | 92.55 lakh | 8. | 31-October-2015 | 50.00 lakh | 9. | 06-November-2015 | 26.00 lakh | 10. | 27-November-2015 | 10.00 lakh | 11. | 29-December-2015 | 64.07 lakh | 12. | 31-December-2015 | 33.08 lakh | 13. | 20-January-2016 | 27.19 lakh | 14. | 31-January-2016 | 18.00 lakh | 15. | 29-February-2016 | 28.72 lakh | 16. | 28-March-2016 | 11.10 lakh | 17. | 30-March-2016 | 17.00 lakh | 18. | 19-April-2016 | 7.33 lakh | 19. | 30-April-2016 | 25.00 lakh | 20. | 16-May-2016 | 6.89 lakh | 21. | 31-May-2016 | 62.59 lakh | 22. | 28-June-2016 | 158.24 lakh | 23. | 24-August-2016 | 54.03 lakh | 24. | 30-August-2016 | 12.42 lakh | 25. | 26-October-2016 | 78.32 lakh |
Total |
984.83 lakh |
% Payment |
99.91 % |
|
Advance Amount: 71.00 lakh
Recovered Amount: 71.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 2026 No. of Test Done : 2027 No. of Test Passed : 2021 No. of Test Failed : 6 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 92.64 |
Number of Notice(s) issued: 60 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 944 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 23-09-2016 | 12+550 | Site inspection by DPM Sir.Mansoon damages. | Devki Nandan Sharma | RE | DSC4 R&B WB Champawat | See Pic |
2. | 23-09-2016 | 13+900 | Site inspection by DPMSir | Devki Nandan Sharma | RE | DSC4 R&B WB Champawat | See Pic |
3. | 14-09-2016 | 4+325 | Site inspection by DPM Sir with AE Sir, JE wb pwd champawat , RE sir & contractor | Baldev Arya | Site Supervisor | DSC4 R&B WB Pithoragar | See Pic |
4. | 14-09-2016 | 10+500 | Site inspection by DPM Sir with AE Sir, JE wb pwd champawat, RE Sir & contractor | Baldev Arya | Site Supervisor | DSC4 R&B WB Pithoragar | See Pic |
5. | 14-09-2016 | 12+550 | Site inspection by DPM Sir with AE Sir, JE wb pwd champawat, RE Sir, contractor | Baldev Arya | Site Supervisor | DSC4 R&B WB Pithoragar | See Pic |
6. | 14-09-2016 | 4+325 | Site inspection by DPM sir with AE sir, RE & contractor | Manjeet Saini | JE | UDRP R&B Champawat | See Pic |
7. | 14-09-2016 | 13+900 | Site inspection by DPM sir with AE sir, RE & contractor | Manjeet Saini | JE | UDRP R&B Champawat | See Pic |
8. | 14-09-2016 | 13+900 | Site inspection by DPM Sir with AE Sir, JE wb pwd champawat, RE Sir & contractor | Baldev Arya | Site Supervisor | DSC4 R&B WB Pithoragar | See Pic |
9. | 22-08-2016 | 19+575 | R/Wall with Toe wall & Scupper. | Narendra Kumar Pant | EE | UDRP R&B Champawat | See Pic |
10. | 22-08-2016 | 14+200 | R/Wall with Toe Wall. | Narendra Kumar Pant | EE | UDRP R&B Champawat | See Pic |
11. | 22-08-2016 | 12+000 | KM Stone foundation RCC | Devki Nandan Sharma | RE | DSC4 R&B WB Champawat | See Pic |
12. | 22-08-2016 | 19+575 | Wire crates at toe wall | Devki Nandan Sharma | RE | DSC4 R&B WB Champawat | See Pic |
13. | 22-08-2016 | 19+575 | Slab shuttering for slab culvert | Devki Nandan Sharma | RE | DSC4 R&B WB Champawat | See Pic |
14. | 22-08-2016 | 19+575 | Banded Retaining wall with plum concrete with RR 1:5 masonry toe wall of wire crates | Devki Nandan Sharma | RE | DSC4 R&B WB Champawat | See Pic |
15. | 22-08-2016 | 14+200 | Banded Retaining wall/plum toe wall | Devki Nandan Sharma | RE | DSC4 R&B WB Champawat | See Pic |
16. | 22-08-2016 | 11+200 | Damages on road and retaining / coollie wall due to rain and land slides | Devki Nandan Sharma | RE | DSC4 R&B WB Champawat | See Pic |
17. | 22-08-2016 | 10+850 | Road damaged 100m length aprox.due to heavy rain slips and land slides | Devki Nandan Sharma | RE | DSC4 R&B WB Champawat | See Pic |
18. | 22-08-2016 | 10+100 | Slips damaging road | Devki Nandan Sharma | RE | DSC4 R&B WB Champawat | See Pic |
19. | 07-08-2016 | 14+200 | retaining wall in progress | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
20. | 10-07-2016 | 17+960 | Kc drain in progress | Manjeet Saini | JE | UDRP R&B Champawat | See Pic |
|
|