Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Laiuwapani-Banlekh Motor Road Work Completed
Project: UDRP-RB UID: 1301 Sanction Cost: 393.54  lakh Length: 8.400 KM.
District: Champawat Block: Champawat Constituency: Champawat Circle: Pithoragarh WB Circle
DEA: DEA Champawat DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: ODR
Procurement:
Package No.: 14        Package Name:  UDRP/PWD/10/19/RD/014        Tender Date: 01-02-2014        Current Status: Agreement signed        Achieved on Date: 15-05-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/10/19/RD/014      Contractor Name: Panchghati Constructions
Start Date:  23-05-2014      Intended Completion Date:  01-11-2015      Original End Date:  22-08-2015
Total Bond Cost: 33230845 (332.31 lakh)        Variation Cost: 2293192.78 (22.93 lakh)    Hence Total Bond Cost is   35524037.78 (355.24 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works1700.00 m39.0323-05-201410-01-20151700.00 m1700.00 m10.9939.03
2.G-21.96 KM5.4201-12-201401-05-20151.96 KM1.96 KM1.535.42
3.G-33.40 KM9.5501-08-201430-06-20153.40 KM3.40 KM2.699.55
4.PC/CC i/c Prime Coat, Tack Coat8.40 KM114.0515-02-201510-10-20158.40 KM8.40 KM32.1114.05
5.Cause Way6.00 No21.6301-08-201415-10-20156.00 No6.00 No6.0921.63
6.Culverts/Scupper 49.00 No119.0801-08-201415-02-201549.00 No49.00 No33.52119.08
7.longitudinal Drain8000.00 m19.5601-10-201430-06-20158000.00 m8000.00 m5.5119.56
8.Crash Barrier161.30 m4.2801-10-201530-10-2015161.30 m161.30 m1.24.28
9.Parapet365.00 No14.0601-07-201530-10-2015365.00 No365.00 No3.9614.06
10.Road Furniture124.00 No0.6101-10-201530-10-2015124.00 No124.00 No0.170.61
11.Other Allied Works & Finishing Work 1.00 Job7.9923-05-201401-11-20151.00 Job1.00 Job2.257.99
Total Amount: 355.26 100   355.26
Remarks: Work Completed and Liabilities dues       Work Program Made On: 23-06-2014        Updation of work program on: 20-11-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.01-October-201478.88  lakh
2.31-December-201425.80  lakh
3.31-March-201548.59  lakh
4.16-June-201536.00  lakh
5.30-June-201554.00  lakh
6.31-July-201560.81  lakh
7.29-September-201529.41  lakh
8.31-October-201511.00  lakh
9.29-September-201610.57  lakh
Total 355.06  lakh
% Payment 99.95 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 184   No. of Test Done : 184    No. of Test Passed : 184   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 92.23
Number of Notice(s) issued: 57

Mobile Pic Upload

Number of Pics Available on Web Repository: 136
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.19-05-20162+000World bank mission on site visitSanjeev KumarJEUDRP R&B Champawat See Pic
2.19-05-20168+400World bank mission on site visitSanjeev KumarJEUDRP R&B Champawat See Pic
3.19-05-20162+020World bank mission on site visitSanjeev KumarJEUDRP R&B Champawat See Pic
4.19-05-20162+020World bank mission on site visitSanjeev KumarJEUDRP R&B Champawat See Pic
5.19-05-20160+015World bank mission on site visitSanjeev KumarJEUDRP R&B Champawat See Pic
6.19-05-20160+000World bank mission on site visitSanjeev KumarJEUDRP R&B Champawat See Pic
7.03-02-20168+400Project information BoardDevki Nandan SharmaREDSC4 R&B WB Champawat See Pic
8.03-02-20163+800Plum Concrete breast wallsDevki Nandan SharmaREDSC4 R&B WB Champawat See Pic
9.03-02-20163+800W Metal Beam Crash BarriersDevki Nandan SharmaREDSC4 R&B WB Champawat See Pic
10.03-02-20163+720Parapet wallsDevki Nandan SharmaREDSC4 R&B WB Champawat See Pic
11.03-02-20162+600Hectometer StonesDevki Nandan SharmaREDSC4 R&B WB Champawat See Pic
12.03-02-20162+600Traffic SignageDevki Nandan SharmaREDSC4 R&B WB Champawat See Pic
13.03-02-20161+000BC work above scupperDevki Nandan SharmaREDSC4 R&B WB Champawat See Pic
14.03-02-20161+000KM StonesDevki Nandan SharmaREDSC4 R&B WB Champawat See Pic
15.03-02-20161+000Traffic SignageDevki Nandan SharmaREDSC4 R&B WB Champawat See Pic
16.03-02-2016O+750BC aboveDevki Nandan SharmaREDSC4 R&B WB Champawat See Pic
17.03-02-2016O+750Catch PitDevki Nandan SharmaREDSC4 R&B WB Champawat See Pic
18.03-02-2016O+750Parapet WallsDevki Nandan SharmaREDSC4 R&B WB Champawat See Pic
19.03-02-20160+450BC work above ScupperDevki Nandan SharmaREDSC4 R&B WB Champawat See Pic
20.03-02-20160+500Traffic SignageDevki Nandan SharmaREDSC4 R&B WB Champawat See Pic