Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Kulsari Gairwaram MR Work Completed
Project: UDRP-RB UID: 1299 Sanction Cost: 661.61  lakh Length: 9.000 KM.
District: Chamoli Block: Narain Bagar Constituency: Tharali Circle:
DEA: DEA Karanprayag DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 118        Package Name:  UDRP/PWD/02/38/RD/107        Tender Date: 11-09-2015        Current Status: Agreement signed        Achieved on Date: 05-01-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/38/RD/107      Contractor Name: Chaudhary Sandeep Contractor & Suppliers
Start Date:  12-01-2016      Intended Completion Date:  31-01-2018      Original End Date:  11-04-2017
Total Bond Cost: 51751924.84 (517.52 lakh)        Variation Cost: 11656779.53 (116.57 lakh)    Hence Total Bond Cost is   63408704.37 (634.09 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 2199460 for 85 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence8.70 KM81.3002-02-201620-11-20178.70 KM8.70 KM12.4781.30
2.R/Wall, B/ Wall Type Protection works2375.00 m221.1925-01-201615-01-20182375.00 m2375.00 m33.92221.19
3.GSB/RBI/G-14.20 KM29.1112-06-201620-10-20174.20 KM4.20 KM4.4629.11
4.G-24.40 KM35.4428-12-201625-10-20174.40 KM4.40 KM5.4435.44
5.G-35.20 KM50.9002-01-201705-11-20175.20 KM5.20 KM7.850.90
6.PC/CC i/c Prime Coat, Tack Coat8.30 KM89.3625-04-201710-01-20188.30 KM8.30 KM13.789.36
7.Cause Way5.00 No18.7624-08-201615-12-20175.00 No5.00 No2.8818.76
8.Culverts/Scupper 20.00 No66.7820-04-201625-07-201720.00 No20.00 No10.2466.78
9.longitudinal Drain8500.00 m33.0011-04-201625-12-20178500.00 m8500.00 m5.0633.00
10.Parapet586.00 No17.6201-08-201725-01-2018586.00 No586.00 No2.717.62
11.Road Furniture103.00 No2.2206-03-201630-01-2018103.00 No103.00 No0.342.22
12.Env. Man & Moni Plan1.00 Job6.4901-01-201825-01-20181.00 Job1.00 Job16.49
Total Amount: 652.17 100   652.17
Remarks: No Remarks       Work Program Made On: 28-01-2016        Updation of work program on: 02-08-2019       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-March-201628.64  lakh
2.11-May-201638.42  lakh
3.25-May-201620.31  lakh
4.30-June-201640.07  lakh
5.31-August-201630.69  lakh
6.26-October-201627.97  lakh
7.17-December-201653.11  lakh
8.02-February-201717.11  lakh
9.28-February-201761.45  lakh
10.24-March-201719.23  lakh
11.20-May-201714.33  lakh
12.24-June-201752.46  lakh
13.28-July-201714.45  lakh
14.13-October-201724.44  lakh
15.31-October-201733.52  lakh
16.23-November-201744.13  lakh
17.28-February-201843.37  lakh
18.27-March-201834.76  lakh
19.10-August-201832.47  lakh
20.25-September-20183.15  lakh
21.27-February-201918.08  lakh
Total 652.16  lakh
% Payment 102.85 %
Advance Amount:  20.31  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  20.31  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 322   No. of Test Done : 405    No. of Test Passed : 361   No. of Test Failed : 44   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 85.66
Number of Notice(s) issued: 76

Mobile Pic Upload

Number of Pics Available on Web Repository: 83
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.04-04-2018At KM 9Visit of CE sir and instructions given for rectification of defects and handover to civil division without any further delayRajan NautiyalJEUDRP R&B Chakrata See Pic
2.23-03-2018At ch 3+380Sampling for Third party testing of P. C. workRajan NautiyalJEUDRP R&B Chakrata See Pic
3.23-03-2018At Ch 3+250Core cutting for third party testingRajan NautiyalJEUDRP R&B Chakrata See Pic
4.23-03-2018At Ch 3+000Core cutting for Third party testingRajan NautiyalJEUDRP R&B Chakrata See Pic
5.23-03-2018At Ch 1+650Core cutting for Third party testing of CC work.Rajan NautiyalJEUDRP R&B Chakrata See Pic
6.23-01-2018At Ch 3+225Checking of CC Panel by EE sirRajan NautiyalJEUDRP R&B Chakrata See Pic
7.23-01-2018At KM 3+000Checking of CC and Plum work by EE sirRajan NautiyalJEUDRP R&B Chakrata See Pic
8.23-01-2018At Ch 1+500C C Panel M30 Checking by EE sir and instructions for finishing work has givenRajan NautiyalJEUDRP R&B Chakrata See Pic
9.23-01-2018At Ch 3/25Coolie wall workRajan NautiyalJEUDRP R&B Chakrata See Pic
10.23-01-2018At CH 3+000Dismantling of CC panel (due to poor quality)Rajan NautiyalJEUDRP R&B Chakrata See Pic
11.21-01-2018Ch 0.400-0.425Visit by PPE's expert Mr Arun Tyagi and check the ppe's of labour found okDhwajvir SinghJEUDRP R&B Karnprayag See Pic
12.11-01-2018At Ch 5/21Collie wall work found satisfactoryRajan NautiyalJEUDRP R&B Chakrata See Pic
13.11-01-2018At Ch 3+250Kharinja work rejectedRajan NautiyalJEUDRP R&B Chakrata See Pic
14.11-01-2018At Ch 3+350CC panel rejected due to excess water and not using vibratorRajan NautiyalJEUDRP R&B Chakrata See Pic
15.11-01-2018At Laboratoryconcrete Cube test is in progress of CC road M30Rajan NautiyalJEUDRP R&B Chakrata See Pic
16.12-12-2017At Ch 0+000KM stone, Direction and information board fixed completedRajan NautiyalJEUDRP R&B Chakrata See Pic
17.26-11-2017At Ch 1+640 to 1+660C C road concrete Work done Without surface roughing and neend improvement in camberRajan NautiyalJEUDRP R&B Chakrata See Pic
18.26-11-2017At Ch 1+650Parapet construction in progressRajan NautiyalJEUDRP R&B Chakrata See Pic
19.26-11-2017At Ch 2+700U Drain workRajan NautiyalJEUDRP R&B Chakrata See Pic
20.16-11-2017At Ch 4+830Bridle Way construction for villageRajan NautiyalJEUDRP R&B Chakrata See Pic