Kulsari Gairwaram MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
1299 |
Sanction Cost: |
661.61 lakh |
Length:
|
9.000 KM. |
District: |
Chamoli |
Block: |
Narain Bagar |
Constituency: |
Tharali |
Circle: |
|
DEA: |
DEA Karanprayag |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 118
Package Name: 
UDRP/PWD/02/38/RD/107
Tender Date: 11-09-2015
Current Status: Agreement signed
Achieved on Date: 05-01-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/38/RD/107
Contractor Name: Chaudhary Sandeep Contractor & Suppliers
|
Start Date: 12-01-2016
Intended Completion Date: 31-01-2018
Original End Date: 11-04-2017 |
Total Bond Cost: 51751924.84 (517.52 lakh)
Variation Cost: 11656779.53 (116.57 lakh) Hence Total Bond Cost is 63408704.37 (634.09 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 2199460 for 85 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 8.70 KM | 81.30 | 02-02-2016 | 20-11-2017 | 8.70 KM | 8.70 KM | 12.47 | 81.30 | 2. | R/Wall, B/ Wall Type Protection works | 2375.00 m | 221.19 | 25-01-2016 | 15-01-2018 | 2375.00 m | 2375.00 m | 33.92 | 221.19 | 3. | GSB/RBI/G-1 | 4.20 KM | 29.11 | 12-06-2016 | 20-10-2017 | 4.20 KM | 4.20 KM | 4.46 | 29.11 | 4. | G-2 | 4.40 KM | 35.44 | 28-12-2016 | 25-10-2017 | 4.40 KM | 4.40 KM | 5.44 | 35.44 | 5. | G-3 | 5.20 KM | 50.90 | 02-01-2017 | 05-11-2017 | 5.20 KM | 5.20 KM | 7.8 | 50.90 | 6. | PC/CC i/c Prime Coat, Tack Coat | 8.30 KM | 89.36 | 25-04-2017 | 10-01-2018 | 8.30 KM | 8.30 KM | 13.7 | 89.36 | 7. | Cause Way | 5.00 No | 18.76 | 24-08-2016 | 15-12-2017 | 5.00 No | 5.00 No | 2.88 | 18.76 | 8. | Culverts/Scupper | 20.00 No | 66.78 | 20-04-2016 | 25-07-2017 | 20.00 No | 20.00 No | 10.24 | 66.78 | 9. | longitudinal Drain | 8500.00 m | 33.00 | 11-04-2016 | 25-12-2017 | 8500.00 m | 8500.00 m | 5.06 | 33.00 | 10. | Parapet | 586.00 No | 17.62 | 01-08-2017 | 25-01-2018 | 586.00 No | 586.00 No | 2.7 | 17.62 | 11. | Road Furniture | 103.00 No | 2.22 | 06-03-2016 | 30-01-2018 | 103.00 No | 103.00 No | 0.34 | 2.22 | 12. | Env. Man & Moni Plan | 1.00 Job | 6.49 | 01-01-2018 | 25-01-2018 | 1.00 Job | 1.00 Job | 1 | 6.49 |
Total Amount: |
652.17 |
|
100 |
652.17 |
|
Remarks:
No Remarks
Work Program Made On:
28-01-2016 } ?>
Updation of work program on:
02-08-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 28-March-2016 | 28.64 lakh | 2. | 11-May-2016 | 38.42 lakh | 3. | 25-May-2016 | 20.31 lakh | 4. | 30-June-2016 | 40.07 lakh | 5. | 31-August-2016 | 30.69 lakh | 6. | 26-October-2016 | 27.97 lakh | 7. | 17-December-2016 | 53.11 lakh | 8. | 02-February-2017 | 17.11 lakh | 9. | 28-February-2017 | 61.45 lakh | 10. | 24-March-2017 | 19.23 lakh | 11. | 20-May-2017 | 14.33 lakh | 12. | 24-June-2017 | 52.46 lakh | 13. | 28-July-2017 | 14.45 lakh | 14. | 13-October-2017 | 24.44 lakh | 15. | 31-October-2017 | 33.52 lakh | 16. | 23-November-2017 | 44.13 lakh | 17. | 28-February-2018 | 43.37 lakh | 18. | 27-March-2018 | 34.76 lakh | 19. | 10-August-2018 | 32.47 lakh | 20. | 25-September-2018 | 3.15 lakh | 21. | 27-February-2019 | 18.08 lakh |
Total |
652.16 lakh |
% Payment |
102.85 % |
|
Advance Amount: 20.31 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 20.31 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 322 No. of Test Done : 405 No. of Test Passed : 361 No. of Test Failed : 44 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 85.66 |
Number of Notice(s) issued: 76 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 83 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 04-04-2018 | At KM 9 | Visit of CE sir and instructions given for rectification of defects and handover to civil division without any further delay | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
2. | 23-03-2018 | At ch 3+380 | Sampling for Third party testing of P. C. work | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
3. | 23-03-2018 | At Ch 3+250 | Core cutting for third party testing | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
4. | 23-03-2018 | At Ch 3+000 | Core cutting for Third party testing | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
5. | 23-03-2018 | At Ch 1+650 | Core cutting for Third party testing of CC work. | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
6. | 23-01-2018 | At Ch 3+225 | Checking of CC Panel by EE sir | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
7. | 23-01-2018 | At KM 3+000 | Checking of CC and Plum work by EE sir | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
8. | 23-01-2018 | At Ch 1+500 | C C Panel M30 Checking by EE sir and instructions for finishing work has given | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
9. | 23-01-2018 | At Ch 3/25 | Coolie wall work | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
10. | 23-01-2018 | At CH 3+000 | Dismantling of CC panel (due to poor quality) | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
11. | 21-01-2018 | Ch 0.400-0.425 | Visit by PPE's expert Mr Arun Tyagi and check the ppe's of labour found ok | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
12. | 11-01-2018 | At Ch 5/21 | Collie wall work found satisfactory | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
13. | 11-01-2018 | At Ch 3+250 | Kharinja work rejected | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
14. | 11-01-2018 | At Ch 3+350 | CC panel rejected due to excess water and not using vibrator | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
15. | 11-01-2018 | At Laboratory | concrete Cube test is in progress of CC road M30 | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
16. | 12-12-2017 | At Ch 0+000 | KM stone, Direction and information board fixed completed | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
17. | 26-11-2017 | At Ch 1+640 to 1+660 | C C road concrete Work done Without surface roughing and neend improvement in camber | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
18. | 26-11-2017 | At Ch 1+650 | Parapet construction in progress | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
19. | 26-11-2017 | At Ch 2+700 | U Drain work | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
20. | 16-11-2017 | At Ch 4+830 | Bridle Way construction for village | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
|
|