Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Kanakchouri- Pokhta -Rauta motor road Work Completed
Project: UDRP-RB UID: 1298 Sanction Cost: 186.40  lakh Length: 2.220 KM.
District: Chamoli Block: Pokhari Constituency: Badrinath Circle:
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 88        Package Name:  UDRP/PWD/02/08/RD/077        Tender Date: 04-07-2015        Current Status: Agreement signed        Achieved on Date: 23-12-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/08/RD/077      Contractor Name: Dream Real Infra
Start Date:  30-12-2015      Intended Completion Date:  31-10-2018      Original End Date:  29-03-2017
Total Bond Cost: 55686855.62 (556.87 lakh)        Variation Cost: -905472.35 (-9.05 lakh)    Hence Total Bond Cost is   54781383.27 (547.81 lakh) 
Sub Project Cost: 162.62  lakh        Variation Cost of Sub Project: 2111355.43  (21.11 lakh)       Total Sub Project Cost:   183.73 lakh
LD Analysis for Milestone1: calculated LD is Rs 4204293 for +151 days        LD Analysis for Milestone2: calculated LD is Rs 13782285 for 495 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence2.22 KM4.4415-05-201630-04-20182.22 KM2.22 KM2.684.44
2.R/Wall, B/ Wall Type Protection works517.00 m51.0715-05-201630-04-2018517.00 m517.00 m30.8451.07
3.G-22.22 KM23.6325-03-201817-09-20182.22 KM2.22 KM14.2723.63
4.G-32.22 KM16.6506-06-201825-09-20182.22 KM2.22 KM10.0616.65
5.PC/CC i/c Prime Coat, Tack Coat2.22 KM27.2908-06-201805-10-20182.22 KM2.22 KM16.4827.29
6.Culverts/Scupper 8.00 No34.1205-09-201610-09-20188.00 No8.00 No20.634.12
7.longitudinal Drain2220.00 m6.1615-09-201620-09-20182220.00 m2220.00 m3.726.16
8.Parapet80.00 No1.1615-09-201830-09-201880.00 No80.00 No0.71.16
9.Road Furniture109.00 No1.0720-11-201605-10-201828.00 No28.00 No0.651.07
Total Amount: 165.59 100   165.59
Remarks: No Remarks       Work Program Made On: 06-02-2016        Updation of work program on: 07-09-2018       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-June-201616.64  lakh
2.09-September-20169.42  lakh
3.27-October-20169.48  lakh
4.12-January-201711.31  lakh
5.24-March-20171.43  lakh
6.30-November-20170.84  lakh
7.31-March-20186.45  lakh
8.07-June-201818.69  lakh
9.13-July-201823.17  lakh
10.18-August-20187.83  lakh
11.26-November-201851.35  lakh
12.21-February-201951.84  lakh
Total 208.45  lakh
% Payment113.45 %
Advance Amount:  79.00  lakh        Recovered Amount:  86.50  lakh        Balance to be Recovered  -7.50  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 276   No. of Test Done : 255    No. of Test Passed : 243   No. of Test Failed : 12   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 57
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.23-10-2018Ch. 1+500OGPC rolling work in progressSohanbir SinghJEUDRP R&B Gopeshwar See Pic
2.23-10-2018Ch. 1+580OGPC rolling work in progressSohanbir SinghJEUDRP R&B Gopeshwar See Pic
3.23-10-2018Ch. 1+575Seal coat work in progressSohanbir SinghJEUDRP R&B Gopeshwar See Pic
4.23-10-2018Ch. 1+530OGPC thickness check found 20 mmSohanbir SinghJEUDRP R&B Gopeshwar See Pic
5.22-10-2018Ch. 1+325OGPC rolling work in progressSohanbir SinghJEUDRP R&B Gopeshwar See Pic
6.22-10-2018Ch. 1+325PC WORK IN PROGRESSSohanbir SinghJEUDRP R&B Gopeshwar See Pic
7.22-10-2018Ch. 1+275OGPC WORK IN PROGRESSSohanbir SinghJEUDRP R&B Gopeshwar See Pic
8.05-09-2018Chanage 1+900Slip clearance work in progressSohanbir SinghJEUDRP R&B Gopeshwar See Pic
9.16-08-2018Ch. 1+050Schedule information boardSohanbir SinghJEUDRP R&B Gopeshwar See Pic
10.07-08-2018Ch. 0+525Hill side cutting workSohanbir SinghJEUDRP R&B Gopeshwar See Pic
11.07-08-2018Ch. 0+325Road width checkingSohanbir SinghJEUDRP R&B Gopeshwar See Pic
12.16-07-2018Ch. 0+525Hill side cutting workSohanbir SinghJEUDRP R&B Gopeshwar See Pic
13.14-07-2018Ch. 0+325Hill side cutting workSohanbir SinghJEUDRP R&B Gopeshwar See Pic
14.07-07-2018Ch. 0+150Superelevation found 8%Sohanbir SinghJEUDRP R&B Gopeshwar See Pic
15.02-07-2018Ch. 0+910OGPC thickness checking found 23mmSohanbir SinghJEUDRP R&B Gopeshwar See Pic
16.30-06-2018Ch. 0+750OGPC rolling work in progressSohanbir SinghJEUDRP R&B Gopeshwar See Pic
17.13-06-2018Ch.0+150Road width checking by Ex. En.sir clear road width found 4.80 mSohanbir SinghJEUDRP R&B Gopeshwar See Pic
18.13-06-2018Ch. 0+115WBMG-2 first and second layer thickness checking by Ex. En. Sir found 160 mmSohanbir SinghJEUDRP R&B Gopeshwar See Pic
19.13-06-2018Chris. 0+040WBM G-2 & G-3 Thickness checking by Ex. En. Sir found 225mmSohanbir SinghJEUDRP R&B Gopeshwar See Pic
20.01-06-2018Ch.0+350WBM G-2 Ist layer thickness checkingSohanbir SinghJEUDRP R&B Chamoli See Pic