Kanakchouri- Pokhta -Rauta motor road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1298 |
Sanction Cost: |
186.40 lakh |
Length:
|
2.220 KM. |
District: |
Chamoli |
Block: |
Pokhari |
Constituency: |
Badrinath |
Circle: |
|
DEA: |
DEA Gopeshwar |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 88
Package Name: 
UDRP/PWD/02/08/RD/077
Tender Date: 04-07-2015
Current Status: Agreement signed
Achieved on Date: 23-12-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/08/RD/077
Contractor Name: Dream Real Infra
|
Start Date: 30-12-2015
Intended Completion Date: 31-10-2018
Original End Date: 29-03-2017 |
Total Bond Cost: 55686855.62 (556.87 lakh)
Variation Cost: -905472.35 (-9.05 lakh) Hence Total Bond Cost is 54781383.27 (547.81 lakh)
|
Sub Project Cost: 162.62 lakh
Variation Cost of Sub Project: 2111355.43 (21.11 lakh)
Total Sub Project Cost:
183.73 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 4204293 for +151 days
LD Analysis for Milestone2: calculated LD is Rs 13782285 for 495 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 2.22 KM | 4.44 | 15-05-2016 | 30-04-2018 | 2.22 KM | 2.22 KM | 2.68 | 4.44 | 2. | R/Wall, B/ Wall Type Protection works | 517.00 m | 51.07 | 15-05-2016 | 30-04-2018 | 517.00 m | 517.00 m | 30.84 | 51.07 | 3. | G-2 | 2.22 KM | 23.63 | 25-03-2018 | 17-09-2018 | 2.22 KM | 2.22 KM | 14.27 | 23.63 | 4. | G-3 | 2.22 KM | 16.65 | 06-06-2018 | 25-09-2018 | 2.22 KM | 2.22 KM | 10.06 | 16.65 | 5. | PC/CC i/c Prime Coat, Tack Coat | 2.22 KM | 27.29 | 08-06-2018 | 05-10-2018 | 2.22 KM | 2.22 KM | 16.48 | 27.29 | 6. | Culverts/Scupper | 8.00 No | 34.12 | 05-09-2016 | 10-09-2018 | 8.00 No | 8.00 No | 20.6 | 34.12 | 7. | longitudinal Drain | 2220.00 m | 6.16 | 15-09-2016 | 20-09-2018 | 2220.00 m | 2220.00 m | 3.72 | 6.16 | 8. | Parapet | 80.00 No | 1.16 | 15-09-2018 | 30-09-2018 | 80.00 No | 80.00 No | 0.7 | 1.16 | 9. | Road Furniture | 109.00 No | 1.07 | 20-11-2016 | 05-10-2018 | 28.00 No | 28.00 No | 0.65 | 1.07 |
Total Amount: |
165.59 |
|
100 |
165.59 |
|
Remarks:
No Remarks
Work Program Made On:
06-02-2016 } ?>
Updation of work program on:
07-09-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-June-2016 | 16.64 lakh | 2. | 09-September-2016 | 9.42 lakh | 3. | 27-October-2016 | 9.48 lakh | 4. | 12-January-2017 | 11.31 lakh | 5. | 24-March-2017 | 1.43 lakh | 6. | 30-November-2017 | 0.84 lakh | 7. | 31-March-2018 | 6.45 lakh | 8. | 07-June-2018 | 18.69 lakh | 9. | 13-July-2018 | 23.17 lakh | 10. | 18-August-2018 | 7.83 lakh | 11. | 26-November-2018 | 51.35 lakh | 12. | 21-February-2019 | 51.84 lakh |
Total |
208.45 lakh |
% Payment | 113.45 % |
|
Advance Amount: 79.00 lakh
Recovered Amount: 86.50 lakh
Balance to be Recovered -7.50 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 276 No. of Test Done : 255 No. of Test Passed : 243 No. of Test Failed : 12 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 57 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 23-10-2018 | Ch. 1+500 | OGPC rolling work in progress | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
2. | 23-10-2018 | Ch. 1+580 | OGPC rolling work in progress | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
3. | 23-10-2018 | Ch. 1+575 | Seal coat work in progress | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
4. | 23-10-2018 | Ch. 1+530 | OGPC thickness check found 20 mm | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
5. | 22-10-2018 | Ch. 1+325 | OGPC rolling work in progress | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
6. | 22-10-2018 | Ch. 1+325 | PC WORK IN PROGRESS | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
7. | 22-10-2018 | Ch. 1+275 | OGPC WORK IN PROGRESS | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
8. | 05-09-2018 | Chanage 1+900 | Slip clearance work in progress | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
9. | 16-08-2018 | Ch. 1+050 | Schedule information board | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
10. | 07-08-2018 | Ch. 0+525 | Hill side cutting work | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
11. | 07-08-2018 | Ch. 0+325 | Road width checking | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
12. | 16-07-2018 | Ch. 0+525 | Hill side cutting work | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
13. | 14-07-2018 | Ch. 0+325 | Hill side cutting work | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
14. | 07-07-2018 | Ch. 0+150 | Superelevation found 8% | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
15. | 02-07-2018 | Ch. 0+910 | OGPC thickness checking found 23mm | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
16. | 30-06-2018 | Ch. 0+750 | OGPC rolling work in progress | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
17. | 13-06-2018 | Ch.0+150 | Road width checking by Ex. En.sir clear road width found 4.80 m | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
18. | 13-06-2018 | Ch. 0+115 | WBMG-2 first and second layer thickness checking by Ex. En. Sir found 160 mm | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
19. | 13-06-2018 | Chris. 0+040 | WBM G-2 & G-3 Thickness checking by Ex. En. Sir found 225mm | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
20. | 01-06-2018 | Ch.0+350 | WBM G-2 Ist layer thickness checking | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
|
|