Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Raitoli-Nargoli-Kamiyar motor road Work Completed
Project: UDRP-RB UID: 1297 Sanction Cost: 66.45  lakh Length: 1.000 KM.
District: Chamoli Block: Dasholi Constituency: Badrinath Circle:
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 92        Package Name:  UDRP/PWD/02/08/RD/081        Tender Date: 23-05-2015        Current Status: Agreement signed        Achieved on Date: 31-07-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/08/RD/081      Contractor Name: Raina Construction
Start Date:  07-08-2015      Intended Completion Date:  31-03-2018      Original End Date:  06-11-2016
Total Bond Cost: 31526435.26 (315.26 lakh)        Variation Cost: 2442431.62 (24.42 lakh)    Hence Total Bond Cost is   33968866.88 (339.69 lakh) 
Sub Project Cost: 62.60  lakh        Variation Cost of Sub Project: 76545.74  (0.77 lakh)       Total Sub Project Cost:   63.37 lakh
LD Analysis for Milestone1: calculated LD is Rs 2616658 for 166 days        LD Analysis for Milestone2: calculated LD is Rs 4902293 for 311 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.00 KM1.7602-10-201530-08-20171.00 KM1.00 KM3.151.76
2.R/Wall, B/ Wall Type Protection works205.00 m7.8712-10-201522-08-2017205.00 m205.00 m14.077.87
3.G-21.60 KM10.7201-12-201615-02-20181.60 KM1.60 KM19.1610.72
4.G-30.80 KM7.5312-09-201720-02-20180.80 KM0.80 KM13.467.53
5.PC/CC i/c Prime Coat, Tack Coat0.80 KM13.0701-10-201728-02-20180.80 KM0.80 KM23.3613.07
6.Culverts/Scupper 4.00 No8.2721-10-201501-08-20174.00 No4.00 No14.788.27
7.longitudinal Drain1000.00 m4.9702-01-201705-11-20171000.00 m1000.00 m8.884.97
8.Parapet20.00 No0.8930-09-201715-11-201720.00 No20.00 No1.60.89
9.Road Furniture30.00 No0.8706-09-201630-03-201830.00 No30.00 No1.560.87
Total Amount: 55.95 100   55.95
Remarks: No Remarks       Work Program Made On: 28-09-2015        Updation of work program on: 12-04-2018       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.05-December-20154.70  lakh
2.30-June-20160.91  lakh
3.31-December-20162.83  lakh
4.08-March-20171.31  lakh
5.25-May-20176.05  lakh
6.28-July-20176.62  lakh
7.16-October-20177.34  lakh
8.18-December-201716.27  lakh
9.17-February-20187.32  lakh
10.15-May-20181.27  lakh
11.07-June-20180.97  lakh
12.13-September-20180.66  lakh
Total 56.25  lakh
% Payment88.76 %
Advance Amount:  12.00  lakh        Recovered Amount:  12.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 78   No. of Test Done : 85    No. of Test Passed : 75   No. of Test Failed : 10   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
Number of Notice(s) issued: 1

Mobile Pic Upload

Number of Pics Available on Web Repository: 32
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.23-11-20170.640Width checking by EE Gopeshwar width found 3.75mAshwani KumarREDSC4 R&B WB Chamoli See Pic
2.20-11-20170.400Quality of OGPC Work is satisfactoryAshwani KumarREDSC4 R&B WB Chamoli See Pic
3.20-11-20170.300Proposal of tree cutting still pendingAshwani KumarREDSC4 R&B WB Chamoli See Pic
4.08-02-20170.640Stone for WBM G2 rejected due to flakinessAshwani KumarREDSC4 R&B WB Chamoli See Pic
5.07-02-2017Ch 0.530Rejected G2 stoneKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
6.27-12-2016Ch-0.700Hillside cuttingPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
7.13-12-2016Ch-0.050Hillside cuttingPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
8.13-12-2016Ch-0.450Hillside cuttingPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
9.23-09-2016Ch 0.500Hill side cuttingKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
10.23-09-2016Ch 0.280Dismantling of breast wallKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
11.23-09-2016Ch 0.280Road width not properKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
12.23-09-2016Ch 0.300Rejected G2Kirti Vardhan NegiAEDEA WB Gopeshwar See Pic
13.23-09-2016Ch 0.280Rejected breast wallKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
14.12-09-20160.350Hill side cutting in progressAshwani KumarREDSC4 R&B WB Chamoli See Pic
15.28-07-2016Ch- 0.100R/wPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
16.22-07-2016Ch -0.300Hillside cuttingPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
17.22-07-2016Ch- 0.350New R/w damaged havey RainPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
18.09-04-2016Chainage 0.000Information boardKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
19.07-04-20160.300Colection of G2Ashwani KumarREDSC4 R&B WB Chamoli See Pic
20.16-03-2016Ch - 0.050Site.visituPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic