Mandal -Anusuiya-Siroli motor road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1296 |
Sanction Cost: |
65.10 lakh |
Length:
|
0.900 KM. |
District: |
Chamoli |
Block: |
Dasholi |
Constituency: |
Badrinath |
Circle: |
|
DEA: |
DEA Gopeshwar |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 88
Package Name: 
UDRP/PWD/02/08/RD/077
Tender Date: 04-07-2015
Current Status: Agreement signed
Achieved on Date: 23-12-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/08/RD/077
Contractor Name: Dream Real Infra
|
Start Date: 30-12-2015
Intended Completion Date: 31-10-2018
Original End Date: 29-03-2017 |
Total Bond Cost: 55686855.62 (556.87 lakh)
Variation Cost: -905472.35 (-9.05 lakh) Hence Total Bond Cost is 54781383.27 (547.81 lakh)
|
Sub Project Cost: 58.14 lakh
Variation Cost of Sub Project: -486057.29 (-4.86 lakh)
Total Sub Project Cost:
53.28 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 4204293 for +151 days
LD Analysis for Milestone2: calculated LD is Rs 13782285 for 495 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.90 KM | 4.98 | 05-02-2016 | 28-03-2017 | 0.90 KM | 0.90 KM | 8.94 | 4.98 | 2. | R/Wall, B/ Wall Type Protection works | 210.00 m | 12.88 | 15-02-2016 | 18-06-2017 | 210.00 m | 210.00 m | 23.12 | 12.88 | 3. | G-2 | 1.80 KM | 9.66 | 01-09-2016 | 25-03-2017 | 1.80 KM | 1.80 KM | 17.34 | 9.66 | 4. | G-3 | 0.90 KM | 6.80 | 20-08-2017 | 13-09-2017 | 0.90 KM | 0.90 KM | 12.21 | 6.80 | 5. | PC/CC i/c Prime Coat, Tack Coat | 0.90 KM | 11.04 | 20-09-2017 | 15-11-2017 | 0.90 KM | 0.90 KM | 19.82 | 11.04 | 6. | Culverts/Scupper | 1.00 No | 3.99 | 01-01-2017 | 10-03-2017 | 1.00 No | 1.00 No | 7.16 | 3.99 | 7. | longitudinal Drain | 900.00 m | 5.81 | 02-09-2016 | 05-11-2017 | 900.00 m | 900.00 m | 10.43 | 5.81 | 8. | Road Furniture | 14.00 No | 0.55 | 10-10-2016 | 21-03-2018 | 14.00 No | 14.00 No | 0.99 | 0.55 |
Total Amount: |
55.71 |
|
100 |
55.71 |
|
Remarks:
No Remarks
Work Program Made On:
06-02-2016 } ?>
Updation of work program on:
21-03-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 03-May-2016 | 5.74 lakh | 2. | 31-March-2017 | 11.89 lakh | 3. | 30-November-2017 | 15.80 lakh | 4. | 19-December-2017 | 0.30 lakh | 5. | 31-March-2018 | 5.43 lakh | 6. | 20-February-2019 | 1.57 lakh |
Total |
40.73 lakh |
% Payment | 76.45 % |
|
Advance Amount: 79.00 lakh
Recovered Amount: 86.50 lakh
Balance to be Recovered -7.50 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 276 No. of Test Done : 255 No. of Test Passed : 243 No. of Test Failed : 12 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 88.17 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 8 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 15-11-2017 | 0.780 | WBM G3 work in progress quality of WBM is satisfactory | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
2. | 31-03-2017 | Ch 0.800 | Rejected G2 | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
3. | 20-04-2016 | 0.200 | Colection of G2 | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
4. | 08-03-2016 | Ch 0.625 | Transit walk | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
5. | 27-02-2016 | 0.600 | Dismentling Rejected R/W | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
6. | 13-02-2016 | 0.800 | B/W | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
7. | 19-08-2015 | CH.900 | Taking GPS coordinate | Jayendra Pundir | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
8. | 18-08-2015 | Ch-.800 | Gas and site visit | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
|
|