Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Gauchar Rano Quithi MR Work Completed
Project: UDRP-RB UID: 1280 Sanction Cost: 884.92  lakh Length: 8.500 KM.
District: Chamoli Block: Pokhari Constituency: Badrinath Circle: Rudraprayag WB Circle
DEA: DEA Karanprayag DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 120        Package Name:  UDRP/PWD/02/38/RD/109        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 20-11-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/38/RD/109      Contractor Name: Anupam Construction Co.
Start Date:  27-11-2015      Intended Completion Date:  15-03-2018      Original End Date:  26-02-2017
Total Bond Cost: 78303995.33 (783.04 lakh)        Variation Cost: 4056459.00 (40.56 lakh)    Hence Total Bond Cost is   82360454.33 (823.6 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 2858096 for 73 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence8.00 KM92.7127-11-201515-10-20178.00 KM8.00 KM11.0392.71
2.R/Wall, B/ Wall Type Protection works4200.00 m417.5809-12-201520-01-20184200.00 m4200.00 m49.66417.58
3.GSB/RBI/G-18.50 KM31.4715-12-201515-12-20178.50 KM8.50 KM3.7431.47
4.G-28.50 KM35.9221-07-201620-12-20178.50 KM8.50 KM4.2735.92
5.G-38.50 KM49.5912-02-201725-02-20188.50 KM8.50 KM5.949.59
6.PC/CC i/c Prime Coat, Tack Coat8.50 KM72.7310-03-201715-03-20188.50 KM8.50 KM8.6572.73
7.Cause Way9.00 No40.9901-01-201731-12-20179.00 No9.00 No4.8840.99
8.Culverts/Scupper 19.00 No64.4312-01-201630-11-201719.00 No19.00 No7.6664.43
9.longitudinal Drain8500.00 m16.1614-03-201620-01-20188500.00 m8500.00 m1.9216.16
10.Crash Barrier0.00 m0.0017-09-201725-01-20180.00 m0.00 m00.00
11.Parapet400.00 No10.9611-10-201725-12-2017400.00 No400.00 No1.310.96
12.Road Furniture45.00 No1.7513-09-201631-03-201845.00 No45.00 No0.211.75
13.Env. Man & Moni Plan1.00 Job6.5301-02-201816-02-20181.00 Job1.00 Job0.786.53
Total Amount: 840.82 100   840.82
Remarks: No Remarks       Work Program Made On: 22-12-2015        Updation of work program on: 02-08-2019       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.23-December-201514.62  lakh
2.24-December-201558.80  lakh
3.25-December-201519.14  lakh
4.23-January-201651.33  lakh
5.04-March-201646.20  lakh
6.21-March-201631.82  lakh
7.11-May-201672.36  lakh
8.30-June-201669.14  lakh
9.30-August-201617.42  lakh
10.30-December-201612.15  lakh
11.15-March-201712.70  lakh
12.16-March-201716.37  lakh
13.23-March-201745.93  lakh
14.12-June-201766.81  lakh
15.28-July-201723.55  lakh
16.13-October-201731.56  lakh
17.24-November-201736.13  lakh
18.30-November-201725.12  lakh
19.22-December-201741.23  lakh
20.31-January-201849.12  lakh
21.28-March-201827.74  lakh
22.30-June-201827.06  lakh
23.31-October-201827.32  lakh
24.27-February-201917.23  lakh
Total 840.85  lakh
% Payment 102.11 %
Advance Amount:  19.14  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  19.14  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 408   No. of Test Done : 505    No. of Test Passed : 445   No. of Test Failed : 60   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 86.47
Number of Notice(s) issued: 79

Mobile Pic Upload

Number of Pics Available on Web Repository: 213
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.11-06-2019Ch 11.550Causeway in progressNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
2.28-03-2019LabAIV test of G2Naveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
3.15-10-2018Ch 6+350 to 6+400Site visit by SE rudraprayag with E E and A E WB KarnprayagDhwajvir SinghJEUDRP R&B Karnprayag See Pic
4.15-02-2018Ch 6.400Making a base on hard rock by CC and T/W under progressDhwajvir SinghJEUDRP R&B Karnprayag See Pic
5.19-01-2018Ch 5.800Checking of Causeway R/W and giving a alignment for causeway.Dhwajvir SinghJEUDRP R&B Karnprayag See Pic
6.19-01-20186.800R wall work completedLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
7.04-01-2018CH 5.400Giving a layout of causewayRajeev KumarJEUDRP R&B Karnprayag See Pic
8.20-12-2017Ch 8.400Resolving the local problem Demand for RWall near village.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
9.20-12-2017Ch5.950kmConstruction of RWall completeLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
10.19-12-2017At office WB KaranparyagMeeting with villager regarding site issuesRajeev KumarJEUDRP R&B Karnprayag See Pic
11.16-12-2017CH 7.85 kmSecond time shuttering damaged and collapsed due to slip.Rajeev KumarJEUDRP R&B Karnprayag See Pic
12.29-11-20172nd kmConstruction of causewayLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
13.29-11-2017Ch.5700Banded wall under progressLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
14.27-11-2017Km 5.600Improvement of causeway and haipinband.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
15.16-11-2017Km1Medical checkup of labourersLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
16.16-11-2017Ch 7.200Top coat under progressLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
17.16-11-2017Ch3.8 kmConcreting work under progressLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
18.10-11-2017Km 4Reconstruction of damaged Wall which was washed out during last monsoon.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
19.10-11-2017Km 4.900Prime coat completed and making site ready for pC work.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
20.01-11-2017Ch 5.450Construction of RWall with plum and banded wall.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic