Gauchar Rano Quithi MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
1280 |
Sanction Cost: |
884.92 lakh |
Length:
|
8.500 KM. |
District: |
Chamoli |
Block: |
Pokhari |
Constituency: |
Badrinath |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Karanprayag |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 120
Package Name: 
UDRP/PWD/02/38/RD/109
Tender Date: 27-06-2015
Current Status: Agreement signed
Achieved on Date: 20-11-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/38/RD/109
Contractor Name: Anupam Construction Co.
|
Start Date: 27-11-2015
Intended Completion Date: 15-03-2018
Original End Date: 26-02-2017 |
Total Bond Cost: 78303995.33 (783.04 lakh)
Variation Cost: 4056459.00 (40.56 lakh) Hence Total Bond Cost is 82360454.33 (823.6 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 2858096 for 73 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 8.00 KM | 92.71 | 27-11-2015 | 15-10-2017 | 8.00 KM | 8.00 KM | 11.03 | 92.71 | 2. | R/Wall, B/ Wall Type Protection works | 4200.00 m | 417.58 | 09-12-2015 | 20-01-2018 | 4200.00 m | 4200.00 m | 49.66 | 417.58 | 3. | GSB/RBI/G-1 | 8.50 KM | 31.47 | 15-12-2015 | 15-12-2017 | 8.50 KM | 8.50 KM | 3.74 | 31.47 | 4. | G-2 | 8.50 KM | 35.92 | 21-07-2016 | 20-12-2017 | 8.50 KM | 8.50 KM | 4.27 | 35.92 | 5. | G-3 | 8.50 KM | 49.59 | 12-02-2017 | 25-02-2018 | 8.50 KM | 8.50 KM | 5.9 | 49.59 | 6. | PC/CC i/c Prime Coat, Tack Coat | 8.50 KM | 72.73 | 10-03-2017 | 15-03-2018 | 8.50 KM | 8.50 KM | 8.65 | 72.73 | 7. | Cause Way | 9.00 No | 40.99 | 01-01-2017 | 31-12-2017 | 9.00 No | 9.00 No | 4.88 | 40.99 | 8. | Culverts/Scupper | 19.00 No | 64.43 | 12-01-2016 | 30-11-2017 | 19.00 No | 19.00 No | 7.66 | 64.43 | 9. | longitudinal Drain | 8500.00 m | 16.16 | 14-03-2016 | 20-01-2018 | 8500.00 m | 8500.00 m | 1.92 | 16.16 | 10. | Crash Barrier | 0.00 m | 0.00 | 17-09-2017 | 25-01-2018 | 0.00 m | 0.00 m | 0 | 0.00 | 11. | Parapet | 400.00 No | 10.96 | 11-10-2017 | 25-12-2017 | 400.00 No | 400.00 No | 1.3 | 10.96 | 12. | Road Furniture | 45.00 No | 1.75 | 13-09-2016 | 31-03-2018 | 45.00 No | 45.00 No | 0.21 | 1.75 | 13. | Env. Man & Moni Plan | 1.00 Job | 6.53 | 01-02-2018 | 16-02-2018 | 1.00 Job | 1.00 Job | 0.78 | 6.53 |
Total Amount: |
840.82 |
|
100 |
840.82 |
|
Remarks:
No Remarks
Work Program Made On:
22-12-2015 } ?>
Updation of work program on:
02-08-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 23-December-2015 | 14.62 lakh | 2. | 24-December-2015 | 58.80 lakh | 3. | 25-December-2015 | 19.14 lakh | 4. | 23-January-2016 | 51.33 lakh | 5. | 04-March-2016 | 46.20 lakh | 6. | 21-March-2016 | 31.82 lakh | 7. | 11-May-2016 | 72.36 lakh | 8. | 30-June-2016 | 69.14 lakh | 9. | 30-August-2016 | 17.42 lakh | 10. | 30-December-2016 | 12.15 lakh | 11. | 15-March-2017 | 12.70 lakh | 12. | 16-March-2017 | 16.37 lakh | 13. | 23-March-2017 | 45.93 lakh | 14. | 12-June-2017 | 66.81 lakh | 15. | 28-July-2017 | 23.55 lakh | 16. | 13-October-2017 | 31.56 lakh | 17. | 24-November-2017 | 36.13 lakh | 18. | 30-November-2017 | 25.12 lakh | 19. | 22-December-2017 | 41.23 lakh | 20. | 31-January-2018 | 49.12 lakh | 21. | 28-March-2018 | 27.74 lakh | 22. | 30-June-2018 | 27.06 lakh | 23. | 31-October-2018 | 27.32 lakh | 24. | 27-February-2019 | 17.23 lakh |
Total |
840.85 lakh |
% Payment |
102.11 % |
|
Advance Amount: 19.14 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 19.14 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 408 No. of Test Done : 505 No. of Test Passed : 445 No. of Test Failed : 60 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 86.47 |
Number of Notice(s) issued: 79 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 213 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 11-06-2019 | Ch 11.550 | Causeway in progress | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
2. | 28-03-2019 | Lab | AIV test of G2 | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
3. | 15-10-2018 | Ch 6+350 to 6+400 | Site visit by SE rudraprayag with E E and A E WB Karnprayag | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
4. | 15-02-2018 | Ch 6.400 | Making a base on hard rock by CC and T/W under progress | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
5. | 19-01-2018 | Ch 5.800 | Checking of Causeway R/W and giving a alignment for causeway. | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
6. | 19-01-2018 | 6.800 | R wall work completed | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
7. | 04-01-2018 | CH 5.400 | Giving a layout of causeway | Rajeev Kumar | JE | UDRP R&B Karnprayag | See Pic |
8. | 20-12-2017 | Ch 8.400 | Resolving the local problem
Demand for RWall near village. | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
9. | 20-12-2017 | Ch5.950km | Construction of RWall complete | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
10. | 19-12-2017 | At office WB Karanparyag | Meeting with villager regarding site issues | Rajeev Kumar | JE | UDRP R&B Karnprayag | See Pic |
11. | 16-12-2017 | CH 7.85 km | Second time shuttering damaged and collapsed due to slip. | Rajeev Kumar | JE | UDRP R&B Karnprayag | See Pic |
12. | 29-11-2017 | 2nd km | Construction of causeway | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
13. | 29-11-2017 | Ch.5700 | Banded wall under progress | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
14. | 27-11-2017 | Km 5.600 | Improvement of causeway and haipinband. | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
15. | 16-11-2017 | Km1 | Medical checkup of labourers | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
16. | 16-11-2017 | Ch 7.200 | Top coat under progress | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
17. | 16-11-2017 | Ch3.8 km | Concreting work under progress | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
18. | 10-11-2017 | Km 4 | Reconstruction of damaged Wall which was washed out during last monsoon. | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
19. | 10-11-2017 | Km 4.900 | Prime coat completed and making site ready for pC work. | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
20. | 01-11-2017 | Ch 5.450 | Construction of RWall with plum and banded wall. | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
|
|