Ujjwalpur Saim Dharkot Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1278 |
Sanction Cost: |
60.52 lakh |
Length:
|
2.000 KM. |
District: |
Chamoli |
Block: |
Karnaprayag |
Constituency: |
Karanprayag |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Karanprayag |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 116
Package Name: 
UDRP/PWD/02/36/RD/105
Tender Date: 11-09-2015
Current Status: Agreement signed
Achieved on Date: 05-01-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/36/RD/105
Contractor Name: N P Buildwell Pvt. Ltd
|
Start Date: 12-01-2016
Intended Completion Date: 10-06-2019
Original End Date: 11-04-2017 |
Total Bond Cost: 103646807.66 (1036.47 lakh)
Variation Cost: 25046778.29 (250.47 lakh) Hence Total Bond Cost is 128693585.95 (1286.94 lakh)
|
Sub Project Cost: 139.85 lakh
Variation Cost of Sub Project: -8223155.11 (-82.23 lakh)
Total Sub Project Cost:
57.62 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 9120848 for 176 days
LD Analysis for Milestone2: calculated LD is Rs 24615925 for 475 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.25 KM | 1.03 | 01-09-2016 | 25-11-2017 | 0.25 KM | 0.25 KM | 1.67 | 1.03 | 2. | R/Wall, B/ Wall Type Protection works | 120.00 m | 31.37 | 04-09-2016 | 30-10-2018 | 120.00 m | 120.00 m | 50.57 | 31.37 | 3. | G-2 | 0.12 KM | 0.47 | 05-06-2018 | 30-10-2018 | 0.12 KM | 0.12 KM | 0.77 | 0.47 | 4. | G-3 | 0.33 KM | 2.71 | 10-06-2018 | 30-10-2018 | 0.33 KM | 0.33 KM | 4.37 | 2.71 | 5. | PC/CC i/c Prime Coat, Tack Coat | 0.33 KM | 6.18 | 15-06-2018 | 30-10-2018 | 0.33 KM | 0.33 KM | 9.97 | 6.18 | 6. | Cause Way | 1.00 No | 9.09 | 01-09-2016 | 05-04-2018 | 1.00 No | 1.00 No | 14.65 | 9.09 | 7. | Culverts/Scupper | 1.00 No | 2.85 | 15-09-2016 | 20-08-2017 | 1.00 No | 1.00 No | 4.59 | 2.85 | 8. | longitudinal Drain | 2000.00 m | 5.87 | 08-09-2016 | 30-10-2018 | 2000.00 m | 2000.00 m | 9.47 | 5.87 | 9. | Crash Barrier | 0.00 m | 0.00 | 03-01-2017 | 15-03-2017 | 0.00 m | 0.00 m | 0 | 0.00 | 10. | Parapet | 40.00 No | 0.00 | 05-06-2018 | 30-10-2018 | 40.00 No | 40.00 No | 0 | 0.00 | 11. | Road Furniture | 24.00 No | 0.53 | 10-03-2017 | 20-11-2018 | 24.00 No | 24.00 No | 0.85 | 0.53 | 12. | Env. Man & Moni Plan | 1.00 Job | 1.93 | 01-11-2018 | 20-11-2018 | 1.00 Job | 1.00 Job | 3.11 | 1.93 |
Total Amount: |
62.03 |
|
100 |
62.03 |
|
Remarks:
No Remarks
Work Program Made On:
11-02-2016 } ?>
Updation of work program on:
02-08-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 13-October-2017 | 6.67 lakh | 2. | 04-January-2018 | 1.43 lakh | 3. | 28-February-2018 | 1.77 lakh | 4. | 28-March-2018 | 4.60 lakh | 5. | 31-May-2018 | 5.45 lakh | 6. | 23-August-2018 | 0.51 lakh | 7. | 31-October-2018 | 9.46 lakh | 8. | 29-November-2018 | 1.72 lakh | 9. | 16-February-2019 | 20.44 lakh | 10. | 27-February-2019 | 1.20 lakh | 11. | 30-March-2019 | 4.44 lakh | 12. | 22-May-2019 | 0.53 lakh | 13. | 19-June-2019 | 1.19 lakh | 14. | 12-July-2019 | 1.46 lakh | 15. | 15-July-2019 | 1.18 lakh |
Total |
62.05 lakh |
% Payment | 107.69 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1005 No. of Test Done : 1305 No. of Test Passed : 1258 No. of Test Failed : 47 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.50 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 9 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 19-11-2018 | Ch 0.125 | Taking mts of B/W | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
2. | 15-10-2018 | Ch 1+975 | Breaking of WBM G-3 stone aggregates | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
3. | 25-09-2018 | Ch 1+500 to 1+525 | Congratulations of CC road at Dharkot village area | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
4. | 25-09-2018 | Ch 0+225 to 0+250 | Excavation for R/W dressing required. Instruction has given for dressing. | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
5. | 09-02-2018 | Ch 1.950-1975 | Excavation of R/wall under progress dressing required. | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
6. | 09-02-2018 | Ch 0.200-0.225 | Protection work by plum under progress satisfactorily. | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
7. | 25-08-2017 | At Ch 2/00 | Discussions with local public regarding road work progress and provisions | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
8. | 25-08-2017 | At Ch 0/7 | Checking of K. C. drain with AE sir (Base Thickness Found 170 mm) | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
9. | 13-04-2016 | 0.150 | Discussion about road construction with E E sir | Sudhir Kumar | RE | DSC1 R&B WB Chamoli | See Pic |
|
|