Tharali-Junidhar Motor Road Work Completed
Project: UDRP-RB UID: 1275 Sanction Cost: 378.77  lakh Length: 3.600 KM.
District: Chamoli Block: Tharali Constituency: Tharali Circle: Rudraprayag WB Circle
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 108        Package Name:  UDRP/PWD/02/RD/097        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 11-09-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/RD/097      Contractor Name: Sansun Contractors Pvt. Ltd.
Start Date:  18-09-2015      Intended Completion Date:  25-06-2017      Original End Date:  17-12-2016
Total Bond Cost: 74543585.76 (745.44 lakh)        Variation Cost: 18843460.57 (188.43 lakh)    Hence Total Bond Cost is   93387046.33 (933.87 lakh) 
Sub Project Cost: 287.92  lakh        Variation Cost of Sub Project: 12519653.97  (125.2 lakh)       Total Sub Project Cost:   413.12 lakh
LD Analysis for Milestone1: calculated LD is Rs 2459952 for 66 days        LD Analysis for Milestone2: calculated LD is Rs 3689928 for 99 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence3.60 KM15.4810-01-201615-03-20173.60 KM3.60 KM5.4115.48
2.R/Wall, B/ Wall Type Protection works1398.00 m89.6419-01-201615-04-20171398.00 m1398.00 m31.3389.64
3.G-23.60 KM38.8103-12-201620-06-20173.60 KM3.60 KM13.5738.81
4.G-33.60 KM28.0825-01-201728-07-20173.60 KM3.60 KM9.8228.08
5.PC/CC i/c Prime Coat, Tack Coat3.60 KM46.0301-03-201725-10-20173.60 KM3.60 KM16.0946.03
6.Culverts/Scupper 16.00 No45.9410-05-201610-05-201616.00 No16.00 No16.0645.94
7.longitudinal Drain3600.00 m10.7216-07-201612-07-20173600.00 m3600.00 m3.7510.72
8.Crash Barrier225.00 m5.1908-01-201708-08-2017400.00 m400.00 m1.815.19
9.Parapet166.00 No4.8524-05-201720-07-2017166.00 No166.00 No1.74.85
10.Road Furniture121.00 No1.3610-11-201618-09-2017121.00 No121.00 No0.481.36
Total Amount: 286.1 100   286.1
Remarks: No Remarks       Work Program Made On: 25-09-2015        Updation of work program on: 24-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.25-January-20169.20  lakh
2.04-March-201624.50  lakh
3.31-March-20169.79  lakh
4.03-May-201615.93  lakh
5.30-June-201613.36  lakh
6.18-October-201611.05  lakh
7.26-October-201612.50  lakh
8.17-December-201611.24  lakh
9.02-February-201722.34  lakh
10.23-March-201721.41  lakh
11.25-May-201730.18  lakh
12.28-July-201782.60  lakh
13.13-October-201787.25  lakh
14.27-November-201730.79  lakh
15.17-February-201833.91  lakh
16.13-September-20180.48  lakh
Total 416.53  lakh
% Payment100.83 %
Advance Amount:  25.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  25.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 300   No. of Test Done : 301    No. of Test Passed : 255   No. of Test Failed : 46   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 45
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.12-05-2017.050Land slide due to heavy rainVikash SinghJEUDRP R&B Gopeshwar See Pic
2.12-05-20170.150Scupper damage due to heavy rainVikash SinghJEUDRP R&B Gopeshwar See Pic
3.12-05-20170.300Scupper damage due to heavy rainVikash SinghJEUDRP R&B Gopeshwar See Pic
4.12-05-20170.300Land slide due to heavy rainVikash SinghJEUDRP R&B Gopeshwar See Pic
5.12-05-20170.400Settlement of road due heavy rainVikash SinghJEUDRP R&B Gopeshwar See Pic
6.12-05-2017Ch 0.400Settlement due to heavy rainVikash SinghJEUDRP R&B Gopeshwar See Pic
7.12-05-20170.675Wire crate damage due to heavy rainVikash SinghJEUDRP R&B Gopeshwar See Pic
8.12-05-2017Ch0 .875Wbm grading no 2 damage due to heavy rainVikash SinghJEUDRP R&B Gopeshwar See Pic
9.12-05-2017Ch 1100Land slide due to heavy rainVikash SinghJEUDRP R&B Gopeshwar See Pic
10.12-05-20171.150Wbm grading 2 damage due to heavy rainVikash SinghJEUDRP R&B Gopeshwar See Pic
11.12-05-2017Ch.1.250Land slide due to last night heavy rainVikash SinghJEUDRP R&B Gopeshwar See Pic
12.19-07-2016775Slide clear on roadManish VikalContractor Site EngineerUDRP R&B Chamoli See Pic
13.18-07-20161550Lolti KashminagarManish VikalContractor Site EngineerUDRP R&B Chamoli See Pic
14.18-07-20160.720Tharali junidharManish VikalContractor Site EngineerUDRP R&B Chamoli See Pic
15.18-07-20160.740LandslideManish VikalContractor Site EngineerUDRP R&B Chamoli See Pic
16.08-05-20160.000Slide clearence by exvacterVikash SinghJEUDRP R&B Gopeshwar See Pic
17.08-05-20160.00Land slide due to heavy rainVikash SinghJEUDRP R&B Gopeshwar See Pic
18.08-05-20160.000Land slide due to cloud brustVikash SinghJEUDRP R&B Gopeshwar See Pic
19.08-05-20160.00Land slide Due to cloud brustVikash SinghJEUDRP R&B Gopeshwar See Pic
20.07-05-20160.375R/w slope checkingVikash SinghJEUDRP R&B Gopeshwar See Pic