Tharali-Junidhar Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1275 |
Sanction Cost: |
378.77 lakh |
Length:
|
3.600 KM. |
District: |
Chamoli |
Block: |
Tharali |
Constituency: |
Tharali |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Gopeshwar |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 108
Package Name: 
UDRP/PWD/02/RD/097
Tender Date: 27-06-2015
Current Status: Agreement signed
Achieved on Date: 11-09-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/RD/097
Contractor Name: Sansun Contractors Pvt. Ltd.
|
Start Date: 18-09-2015
Intended Completion Date: 25-06-2017
Original End Date: 17-12-2016 |
Total Bond Cost: 74543585.76 (745.44 lakh)
Variation Cost: 18843460.57 (188.43 lakh) Hence Total Bond Cost is 93387046.33 (933.87 lakh)
|
Sub Project Cost: 287.92 lakh
Variation Cost of Sub Project: 12519653.97 (125.2 lakh)
Total Sub Project Cost:
413.12 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 2459952 for 66 days
LD Analysis for Milestone2: calculated LD is Rs 3689928 for 99 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 3.60 KM | 15.48 | 10-01-2016 | 15-03-2017 | 3.60 KM | 3.60 KM | 5.41 | 15.48 | 2. | R/Wall, B/ Wall Type Protection works | 1398.00 m | 89.64 | 19-01-2016 | 15-04-2017 | 1398.00 m | 1398.00 m | 31.33 | 89.64 | 3. | G-2 | 3.60 KM | 38.81 | 03-12-2016 | 20-06-2017 | 3.60 KM | 3.60 KM | 13.57 | 38.81 | 4. | G-3 | 3.60 KM | 28.08 | 25-01-2017 | 28-07-2017 | 3.60 KM | 3.60 KM | 9.82 | 28.08 | 5. | PC/CC i/c Prime Coat, Tack Coat | 3.60 KM | 46.03 | 01-03-2017 | 25-10-2017 | 3.60 KM | 3.60 KM | 16.09 | 46.03 | 6. | Culverts/Scupper | 16.00 No | 45.94 | 10-05-2016 | 10-05-2016 | 16.00 No | 16.00 No | 16.06 | 45.94 | 7. | longitudinal Drain | 3600.00 m | 10.72 | 16-07-2016 | 12-07-2017 | 3600.00 m | 3600.00 m | 3.75 | 10.72 | 8. | Crash Barrier | 225.00 m | 5.19 | 08-01-2017 | 08-08-2017 | 400.00 m | 400.00 m | 1.81 | 5.19 | 9. | Parapet | 166.00 No | 4.85 | 24-05-2017 | 20-07-2017 | 166.00 No | 166.00 No | 1.7 | 4.85 | 10. | Road Furniture | 121.00 No | 1.36 | 10-11-2016 | 18-09-2017 | 121.00 No | 121.00 No | 0.48 | 1.36 |
Total Amount: |
286.1 |
|
100 |
286.1 |
|
Remarks:
No Remarks
Work Program Made On:
25-09-2015 } ?>
Updation of work program on:
24-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 25-January-2016 | 9.20 lakh | 2. | 04-March-2016 | 24.50 lakh | 3. | 31-March-2016 | 9.79 lakh | 4. | 03-May-2016 | 15.93 lakh | 5. | 30-June-2016 | 13.36 lakh | 6. | 18-October-2016 | 11.05 lakh | 7. | 26-October-2016 | 12.50 lakh | 8. | 17-December-2016 | 11.24 lakh | 9. | 02-February-2017 | 22.34 lakh | 10. | 23-March-2017 | 21.41 lakh | 11. | 25-May-2017 | 30.18 lakh | 12. | 28-July-2017 | 82.60 lakh | 13. | 13-October-2017 | 87.25 lakh | 14. | 27-November-2017 | 30.79 lakh | 15. | 17-February-2018 | 33.91 lakh | 16. | 13-September-2018 | 0.48 lakh |
Total |
416.53 lakh |
% Payment | 100.83 % |
|
Advance Amount: 25.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 25.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 300 No. of Test Done : 301 No. of Test Passed : 255 No. of Test Failed : 46 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 45 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 12-05-2017 | .050 | Land slide due to heavy rain | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
2. | 12-05-2017 | 0.150 | Scupper damage due to heavy rain | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
3. | 12-05-2017 | 0.300 | Scupper damage due to heavy rain | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
4. | 12-05-2017 | 0.300 | Land slide due to heavy rain | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
5. | 12-05-2017 | 0.400 | Settlement of road due heavy rain | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
6. | 12-05-2017 | Ch 0.400 | Settlement due to heavy rain | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
7. | 12-05-2017 | 0.675 | Wire crate damage due to heavy rain | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
8. | 12-05-2017 | Ch0 .875 | Wbm grading no 2 damage due to heavy rain | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
9. | 12-05-2017 | Ch 1100 | Land slide due to heavy rain | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
10. | 12-05-2017 | 1.150 | Wbm grading 2 damage due to heavy rain | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
11. | 12-05-2017 | Ch.1.250 | Land slide due to last night heavy rain | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
12. | 19-07-2016 | 775 | Slide clear on road | Manish Vikal | Contractor Site Engineer | UDRP R&B Chamoli | See Pic |
13. | 18-07-2016 | 1550 | Lolti Kashminagar | Manish Vikal | Contractor Site Engineer | UDRP R&B Chamoli | See Pic |
14. | 18-07-2016 | 0.720 | Tharali junidhar | Manish Vikal | Contractor Site Engineer | UDRP R&B Chamoli | See Pic |
15. | 18-07-2016 | 0.740 | Landslide | Manish Vikal | Contractor Site Engineer | UDRP R&B Chamoli | See Pic |
16. | 08-05-2016 | 0.000 | Slide clearence by exvacter | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
17. | 08-05-2016 | 0.00 | Land slide due to heavy rain | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
18. | 08-05-2016 | 0.000 | Land slide due to cloud brust | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
19. | 08-05-2016 | 0.00 | Land slide Due to cloud brust | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
20. | 07-05-2016 | 0.375 | R/w slope checking | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
|
|