Sarmola Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1273 |
Sanction Cost: |
78.18 lakh |
Length:
|
1.400 KM. |
District: |
Chamoli |
Block: |
Pokhari |
Constituency: |
Badrinath |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Gopeshwar |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 107
Package Name: 
UDPR/PWD/03/RD/096
Tender Date: 23-05-2015
Current Status: Agreement signed
Achieved on Date: 03-09-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDPR/PWD/03/RD/096
Contractor Name: Hindustan Construction
|
Start Date: 10-09-2015
Intended Completion Date: 15-05-2017
Original End Date: 09-12-2016 |
Total Bond Cost: 38802100 (388.02 lakh)
Variation Cost: 2853664.64 (28.54 lakh) Hence Total Bond Cost is 41655764.64 (416.56 lakh)
|
Sub Project Cost: 70.72 lakh
Variation Cost of Sub Project: 40945.28 (0.41 lakh)
Total Sub Project Cost:
71.13 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | R/Wall, B/ Wall Type Protection works | 385.00 m | 15.43 | 22-09-2015 | 15-04-2017 | 385.00 m | 385.00 m | 21.25 | 15.43 | 2. | GSB/RBI/G-1 | 1.40 KM | 8.54 | 08-11-2015 | 04-02-2017 | 1.40 KM | 1.40 KM | 11.76 | 8.54 | 3. | G-2 | 1.40 KM | 6.30 | 10-02-2016 | 20-03-2017 | 1.40 KM | 1.40 KM | 8.68 | 6.30 | 4. | G-3 | 1.40 KM | 8.71 | 29-05-2016 | 10-04-2017 | 1.40 KM | 1.40 KM | 11.99 | 8.71 | 5. | PC/CC i/c Prime Coat, Tack Coat | 1.40 KM | 16.22 | 11-06-2016 | 05-05-2017 | 1.40 KM | 1.40 KM | 22.33 | 16.22 | 6. | Culverts/Scupper | 4.00 No | 12.50 | 20-10-2015 | 15-06-2016 | 4.00 No | 4.00 No | 17.21 | 12.50 | 7. | longitudinal Drain | 1400.00 m | 1.25 | 06-04-2016 | 25-05-2017 | 1400.00 m | 1400.00 m | 1.72 | 1.25 | 8. | Parapet | 110.00 No | 3.11 | 24-07-2016 | 30-12-2016 | 110.00 No | 110.00 No | 4.28 | 3.11 | 9. | Road Furniture | 24.00 No | 0.57 | 17-09-2016 | 20-11-2016 | 24.00 No | 24.00 No | 0.79 | 0.57 |
Total Amount: |
72.63 |
|
100 |
72.63 |
|
Remarks:
No Remarks
Work Program Made On:
26-09-2015 } ?>
Updation of work program on:
24-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-December-2015 | 7.88 lakh | 2. | 31-January-2016 | 5.84 lakh | 3. | 04-March-2016 | 3.51 lakh | 4. | 21-March-2016 | 4.47 lakh | 5. | 11-May-2016 | 2.73 lakh | 6. | 30-June-2016 | 2.43 lakh | 7. | 27-October-2016 | 2.58 lakh | 8. | 28-November-2016 | 31.23 lakh | 9. | 25-January-2017 | 0.97 lakh | 10. | 31-March-2017 | 8.31 lakh | 11. | 28-April-2018 | 1.05 lakh |
Total |
71 lakh |
% Payment | 99.82 % |
|
Advance Amount: 38.00 lakh
Recovered Amount: 5.70 lakh
Balance to be Recovered 32.30 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 209 No. of Test Done : 233 No. of Test Passed : 213 No. of Test Failed : 20 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 89.49 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 67 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 04-05-2017 | Ch. 0+675 | Joint inspection with Pwd staff for Road handing over | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
2. | 25-11-2016 | Ch 0.675 | Thickness checking of G3 layer | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
3. | 22-11-2016 | 0.450 | Parapet work in progress | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
4. | 21-11-2016 | 0.325 | Catchpit work in progress | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
5. | 02-11-2016 | Ch 0+850 | Rolling of Seal coat Work | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
6. | 27-10-2016 | Ch 0+950 | Dewatering on G-3 Surfesh | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
7. | 27-10-2016 | Ch0.900 | Dewatering on g3 surface | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
8. | 27-10-2016 | Ch-1.400 | G3 | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
9. | 27-10-2016 | Ch-0.600 | Bitumen content test for seal coat | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
10. | 27-10-2016 | Ch-1.350 | Rolling for pc | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
11. | 27-10-2016 | Ch-1.350 | Temperature for pc laying | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
12. | 27-10-2016 | Ch1.250 | Road cleaning | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
13. | 27-10-2016 | Ch-0.550 | Seal coat | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
14. | 25-10-2016 | Ch. 0+320 | Carriageway width Checked by Ex. Er. & RE width is 3.75m at site | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
15. | 25-10-2016 | Ch. 0+320 | Seal coat work present of Ex. Er. and Re Sir | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
16. | 25-10-2016 | Thickness checking of PC at ch 0+375 | PC Thickness checking | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
17. | 25-10-2016 | Ch 0+425 | Thickness Checking | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
18. | 25-10-2016 | Ch. 0+175 | PC work in progress | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
19. | 24-10-2016 | 0.175 | Result of Bitumen content of OGPC sample | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
20. | 24-10-2016 | 0.00 | Bitumen content test for OGPC | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
|
|