Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Sarmola Motor Road Work Completed
Project: UDRP-RB UID: 1273 Sanction Cost: 78.18  lakh Length: 1.400 KM.
District: Chamoli Block: Pokhari Constituency: Badrinath Circle: Rudraprayag WB Circle
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 107        Package Name:  UDPR/PWD/03/RD/096        Tender Date: 23-05-2015        Current Status: Agreement signed        Achieved on Date: 03-09-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDPR/PWD/03/RD/096      Contractor Name: Hindustan Construction
Start Date:  10-09-2015      Intended Completion Date:  15-05-2017      Original End Date:  09-12-2016
Total Bond Cost: 38802100 (388.02 lakh)        Variation Cost: 2853664.64 (28.54 lakh)    Hence Total Bond Cost is   41655764.64 (416.56 lakh) 
Sub Project Cost: 70.72  lakh        Variation Cost of Sub Project: 40945.28  (0.41 lakh)       Total Sub Project Cost:   71.13 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works385.00 m15.4322-09-201515-04-2017385.00 m385.00 m21.2515.43
2.GSB/RBI/G-11.40 KM8.5408-11-201504-02-20171.40 KM1.40 KM11.768.54
3.G-21.40 KM6.3010-02-201620-03-20171.40 KM1.40 KM8.686.30
4.G-31.40 KM8.7129-05-201610-04-20171.40 KM1.40 KM11.998.71
5.PC/CC i/c Prime Coat, Tack Coat1.40 KM16.2211-06-201605-05-20171.40 KM1.40 KM22.3316.22
6.Culverts/Scupper 4.00 No12.5020-10-201515-06-20164.00 No4.00 No17.2112.50
7.longitudinal Drain1400.00 m1.2506-04-201625-05-20171400.00 m1400.00 m1.721.25
8.Parapet110.00 No3.1124-07-201630-12-2016110.00 No110.00 No4.283.11
9.Road Furniture24.00 No0.5717-09-201620-11-201624.00 No24.00 No0.790.57
Total Amount: 72.63 100   72.63
Remarks: No Remarks       Work Program Made On: 26-09-2015        Updation of work program on: 24-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.26-December-20157.88  lakh
2.31-January-20165.84  lakh
3.04-March-20163.51  lakh
4.21-March-20164.47  lakh
5.11-May-20162.73  lakh
6.30-June-20162.43  lakh
7.27-October-20162.58  lakh
8.28-November-201631.23  lakh
9.25-January-20170.97  lakh
10.31-March-20178.31  lakh
11.28-April-20181.05  lakh
Total 71  lakh
% Payment99.82 %
Advance Amount:  38.00  lakh        Recovered Amount:  5.70  lakh        Balance to be Recovered  32.30  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 209   No. of Test Done : 233    No. of Test Passed : 213   No. of Test Failed : 20   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.49
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 67
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.04-05-2017Ch. 0+675Joint inspection with Pwd staff for Road handing overSohanbir SinghJEUDRP R&B Chamoli See Pic
2.25-11-2016Ch 0.675Thickness checking of G3 layerKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
3.22-11-20160.450Parapet work in progressAshwani KumarREDSC4 R&B WB Chamoli See Pic
4.21-11-20160.325Catchpit work in progressAshwani KumarREDSC4 R&B WB Chamoli See Pic
5.02-11-2016Ch 0+850Rolling of Seal coat WorkSohanbir SinghJEUDRP R&B Chamoli See Pic
6.27-10-2016Ch 0+950Dewatering on G-3 SurfeshSohanbir SinghJEUDRP R&B Chamoli See Pic
7.27-10-2016Ch0.900Dewatering on g3 surfacePramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
8.27-10-2016Ch-1.400G3Pramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
9.27-10-2016Ch-0.600Bitumen content test for seal coatPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
10.27-10-2016Ch-1.350Rolling for pcPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
11.27-10-2016Ch-1.350Temperature for pc layingPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
12.27-10-2016Ch1.250Road cleaningPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
13.27-10-2016Ch-0.550Seal coatPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
14.25-10-2016Ch. 0+320Carriageway width Checked by Ex. Er. & RE width is 3.75m at siteSohanbir SinghJEUDRP R&B Chamoli See Pic
15.25-10-2016Ch. 0+320Seal coat work present of Ex. Er. and Re SirSohanbir SinghJEUDRP R&B Chamoli See Pic
16.25-10-2016Thickness checking of PC at ch 0+375PC Thickness checkingSohanbir SinghJEUDRP R&B Chamoli See Pic
17.25-10-2016Ch 0+425Thickness CheckingSohanbir SinghJEUDRP R&B Chamoli See Pic
18.25-10-2016Ch. 0+175PC work in progressSohanbir SinghJEUDRP R&B Chamoli See Pic
19.24-10-20160.175Result of Bitumen content of OGPC sampleAshwani KumarREDSC4 R&B WB Chamoli See Pic
20.24-10-20160.00Bitumen content test for OGPCAshwani KumarREDSC4 R&B WB Chamoli See Pic