Semi Bend to Siwai Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1269 |
Sanction Cost: |
265.62 lakh |
Length:
|
3.000 KM. |
District: |
Chamoli |
Block: |
Pokhari |
Constituency: |
Badrinath |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Gopeshwar |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 107
Package Name: 
UDPR/PWD/03/RD/096
Tender Date: 23-05-2015
Current Status: Agreement signed
Achieved on Date: 03-09-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDPR/PWD/03/RD/096
Contractor Name: Hindustan Construction
|
Start Date: 10-09-2015
Intended Completion Date: 15-05-2017
Original End Date: 09-12-2016 |
Total Bond Cost: 38802100 (388.02 lakh)
Variation Cost: 2853664.64 (28.54 lakh) Hence Total Bond Cost is 41655764.64 (416.56 lakh)
|
Sub Project Cost: 196.01 lakh
Variation Cost of Sub Project: 4816028.38 (48.16 lakh)
Total Sub Project Cost:
244.17 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 3.00 KM | 16.25 | 15-09-2015 | 02-12-2016 | 3.00 KM | 3.00 KM | 9.05 | 16.25 | 2. | R/Wall, B/ Wall Type Protection works | 895.00 m | 30.96 | 28-09-2015 | 08-12-2016 | 895.00 m | 895.00 m | 17.24 | 30.96 | 3. | GSB/RBI/G-1 | 3.00 KM | 18.30 | 02-11-2015 | 22-12-2016 | 3.00 KM | 3.00 KM | 10.19 | 18.30 | 4. | G-2 | 3.00 KM | 27.01 | 02-02-2016 | 28-01-2017 | 3.00 KM | 3.00 KM | 15.04 | 27.01 | 5. | G-3 | 3.00 KM | 18.67 | 10-01-2017 | 10-02-2017 | 3.00 KM | 3.00 KM | 10.39 | 18.67 | 6. | PC/CC i/c Prime Coat, Tack Coat | 3.00 KM | 34.76 | 01-03-2017 | 24-05-2017 | 3.00 KM | 3.00 KM | 19.36 | 34.76 | 7. | Cause Way | 2.00 No | 3.94 | 06-08-2016 | 08-12-2016 | 5.00 No | 5.00 No | 2.19 | 3.94 | 8. | Culverts/Scupper | 10.00 No | 19.35 | 15-10-2015 | 07-12-2016 | 10.00 No | 10.00 No | 10.77 | 19.35 | 9. | longitudinal Drain | 2815.00 m | 7.39 | 06-01-2016 | 13-05-2017 | 2815.00 m | 2815.00 m | 4.12 | 7.39 | 10. | Crash Barrier | 70.00 m | 1.55 | 02-02-2017 | 03-03-2017 | 80.00 m | 80.00 m | 0.86 | 1.55 | 11. | Parapet | 25.00 No | 0.70 | 02-02-2017 | 13-06-2017 | 65.00 No | 65.00 No | 0.39 | 0.70 | 12. | Road Furniture | 35.00 No | 0.71 | 14-06-2016 | 24-02-2017 | 35.00 No | 35.00 No | 0.4 | 0.71 |
Total Amount: |
179.59 |
|
100 |
179.59 |
|
Remarks:
No Remarks
Work Program Made On:
26-09-2015 } ?>
Updation of work program on:
23-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-October-2015 | 37.47 lakh | 2. | 26-December-2015 | 26.60 lakh | 3. | 31-January-2016 | 7.87 lakh | 4. | 04-March-2016 | 9.92 lakh | 5. | 21-March-2016 | 38.07 lakh | 6. | 11-May-2016 | 2.97 lakh | 7. | 25-January-2017 | 2.73 lakh | 8. | 31-March-2017 | 2.97 lakh | 9. | 20-May-2017 | 59.77 lakh | 10. | 14-July-2017 | 26.01 lakh | 11. | 28-April-2018 | 29.83 lakh |
Total |
244.21 lakh |
% Payment | 100.02 % |
|
Advance Amount: 38.00 lakh
Recovered Amount: 5.70 lakh
Balance to be Recovered 32.30 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 209 No. of Test Done : 233 No. of Test Passed : 213 No. of Test Failed : 20 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 88.78 |
Number of Notice(s) issued: 1 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 175 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 04-07-2017 | Ch.0+050 | Joint inspection for road handing with Pwd pokhari staff | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
2. | 27-05-2017 | Ch.1+950 | SE Sir site visit | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
3. | 16-04-2017 | Ch. 0+075 | OGPC Work in progress | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
4. | 14-04-2017 | Ch 0.075 | Thickness checking of G2 G3 | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
5. | 14-04-2017 | Ch 1.350 | Gradation of G3 | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
6. | 14-04-2017 | Ch 1.350 | AIV test of G3 found 20.91percent. Passed | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
7. | 14-04-2017 | Ch 2.100 | Superelevation at hp band found 10 percent | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
8. | 14-04-2017 | Ch 2.350 | Checking of superelevation | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
9. | 14-04-2017 | Ch 2.800 | Thickness checking of pc found 22 mm | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
10. | 06-04-2017 | Ch.0+075 | AIV Test | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
11. | 06-04-2017 | ch.2+420 | Pc thickness checked by Ex. Er. sir found 23 mm | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
12. | 06-04-2017 | ch. 2+320 | Scupper width ch. by Ex. Er. sir found 8.3 m | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
13. | 06-04-2017 | Ch. 0+050 | Road width measured by Ex. Er. sir | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
14. | 06-04-2017 | Ch. 0+075 | Discussion with contractor regarding the label of Wbm & Rcc Scupper | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
15. | 04-04-2017 | Ch. 2+075 | Seal coat Rolling work | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
16. | 28-03-2017 | Ch.2+225 | Patri filling work | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
17. | 24-03-2017 | Ch. 0+275 | Causeway casting work in progress | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
18. | 14-02-2017 | ch. 1+350 | AIV Test for G-2 stone found 11.62% | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
19. | 18-01-2017 | Change 2+235 | Coolie wall work in progress | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
20. | 09-01-2017 | Ch.2+600 | Dry Retaining Wall work | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
|
|