Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Semi Bend to Siwai Motor Road Work Completed
Project: UDRP-RB UID: 1269 Sanction Cost: 265.62  lakh Length: 3.000 KM.
District: Chamoli Block: Pokhari Constituency: Badrinath Circle: Rudraprayag WB Circle
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 107        Package Name:  UDPR/PWD/03/RD/096        Tender Date: 23-05-2015        Current Status: Agreement signed        Achieved on Date: 03-09-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDPR/PWD/03/RD/096      Contractor Name: Hindustan Construction
Start Date:  10-09-2015      Intended Completion Date:  15-05-2017      Original End Date:  09-12-2016
Total Bond Cost: 38802100 (388.02 lakh)        Variation Cost: 2853664.64 (28.54 lakh)    Hence Total Bond Cost is   41655764.64 (416.56 lakh) 
Sub Project Cost: 196.01  lakh        Variation Cost of Sub Project: 4816028.38  (48.16 lakh)       Total Sub Project Cost:   244.17 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence3.00 KM16.2515-09-201502-12-20163.00 KM3.00 KM9.0516.25
2.R/Wall, B/ Wall Type Protection works895.00 m30.9628-09-201508-12-2016895.00 m895.00 m17.2430.96
3.GSB/RBI/G-13.00 KM18.3002-11-201522-12-20163.00 KM3.00 KM10.1918.30
4.G-23.00 KM27.0102-02-201628-01-20173.00 KM3.00 KM15.0427.01
5.G-33.00 KM18.6710-01-201710-02-20173.00 KM3.00 KM10.3918.67
6.PC/CC i/c Prime Coat, Tack Coat3.00 KM34.7601-03-201724-05-20173.00 KM3.00 KM19.3634.76
7.Cause Way2.00 No3.9406-08-201608-12-20165.00 No5.00 No2.193.94
8.Culverts/Scupper 10.00 No19.3515-10-201507-12-201610.00 No10.00 No10.7719.35
9.longitudinal Drain2815.00 m7.3906-01-201613-05-20172815.00 m2815.00 m4.127.39
10.Crash Barrier70.00 m1.5502-02-201703-03-201780.00 m80.00 m0.861.55
11.Parapet25.00 No0.7002-02-201713-06-201765.00 No65.00 No0.390.70
12.Road Furniture35.00 No0.7114-06-201624-02-201735.00 No35.00 No0.40.71
Total Amount: 179.59 100   179.59
Remarks: No Remarks       Work Program Made On: 26-09-2015        Updation of work program on: 23-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-October-201537.47  lakh
2.26-December-201526.60  lakh
3.31-January-20167.87  lakh
4.04-March-20169.92  lakh
5.21-March-201638.07  lakh
6.11-May-20162.97  lakh
7.25-January-20172.73  lakh
8.31-March-20172.97  lakh
9.20-May-201759.77  lakh
10.14-July-201726.01  lakh
11.28-April-201829.83  lakh
Total 244.21  lakh
% Payment100.02 %
Advance Amount:  38.00  lakh        Recovered Amount:  5.70  lakh        Balance to be Recovered  32.30  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 209   No. of Test Done : 233    No. of Test Passed : 213   No. of Test Failed : 20   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 88.78
Number of Notice(s) issued: 1

Mobile Pic Upload

Number of Pics Available on Web Repository: 175
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.04-07-2017Ch.0+050Joint inspection for road handing with Pwd pokhari staffSohanbir SinghJEUDRP R&B Chamoli See Pic
2.27-05-2017Ch.1+950SE Sir site visitSohanbir SinghJEUDRP R&B Chamoli See Pic
3.16-04-2017Ch. 0+075OGPC Work in progressSohanbir SinghJEUDRP R&B Chamoli See Pic
4.14-04-2017Ch 0.075Thickness checking of G2 G3Kirti Vardhan NegiAEDEA WB Gopeshwar See Pic
5.14-04-2017Ch 1.350Gradation of G3Kirti Vardhan NegiAEDEA WB Gopeshwar See Pic
6.14-04-2017Ch 1.350AIV test of G3 found 20.91percent. PassedKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
7.14-04-2017Ch 2.100Superelevation at hp band found 10 percentKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
8.14-04-2017Ch 2.350Checking of superelevationKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
9.14-04-2017Ch 2.800Thickness checking of pc found 22 mmKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
10.06-04-2017Ch.0+075AIV TestSohanbir SinghJEUDRP R&B Chamoli See Pic
11.06-04-2017ch.2+420Pc thickness checked by Ex. Er. sir found 23 mmSohanbir SinghJEUDRP R&B Chamoli See Pic
12.06-04-2017ch. 2+320Scupper width ch. by Ex. Er. sir found 8.3 mSohanbir SinghJEUDRP R&B Chamoli See Pic
13.06-04-2017Ch. 0+050Road width measured by Ex. Er. sirSohanbir SinghJEUDRP R&B Chamoli See Pic
14.06-04-2017Ch. 0+075Discussion with contractor regarding the label of Wbm & Rcc ScupperSohanbir SinghJEUDRP R&B Chamoli See Pic
15.04-04-2017Ch. 2+075Seal coat Rolling workSohanbir SinghJEUDRP R&B Chamoli See Pic
16.28-03-2017Ch.2+225Patri filling workSohanbir SinghJEUDRP R&B Chamoli See Pic
17.24-03-2017Ch. 0+275Causeway casting work in progressSohanbir SinghJEUDRP R&B Chamoli See Pic
18.14-02-2017ch. 1+350AIV Test for G-2 stone found 11.62%Sohanbir SinghJEUDRP R&B Chamoli See Pic
19.18-01-2017Change 2+235Coolie wall work in progressSohanbir SinghJEUDRP R&B Chamoli See Pic
20.09-01-2017Ch.2+600Dry Retaining Wall workSohanbir SinghJEUDRP R&B Chamoli See Pic