Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Sema Bairaun Motor Road Work Completed
Project: UDRP-RB UID: 1268 Sanction Cost: 1083.32  lakh Length: 10.500 KM.
District: Chamoli Block: Ghat Constituency: Tharali Circle: Rudraprayag WB Circle
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 99        Package Name:  UDRP/PWD/02/36/RD/088        Tender Date: 18-03-2015        Current Status: Agreement signed        Achieved on Date: 05-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/36/RD/088      Contractor Name: Laxman Singh Rawat
Start Date:  12-06-2015      Intended Completion Date:  08-07-2017      Original End Date:  11-09-2016
Total Bond Cost: 76257187.1 (762.57 lakh)        Variation Cost: 24361004.14 (243.61 lakh)    Hence Total Bond Cost is   100618191.24 (1006.18 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 2707159 for 71 days        LD Analysis for Milestone2: calculated LD is Rs 2097095 for 55 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence10.00 KM48.1120-06-201502-12-201610.00 KM10.00 KM5.6448.11
2.R/Wall, B/ Wall Type Protection works4885.00 m288.2101-07-201510-12-20164885.00 m4885.00 m33.8288.21
3.G-210.50 KM113.7522-01-201630-01-201710.50 KM10.50 KM13.34113.75
4.G-310.50 KM82.6001-05-201601-03-201710.50 KM10.50 KM9.6982.60
5.PC/CC i/c Prime Coat, Tack Coat10.50 KM138.6001-03-201730-05-201710.50 KM10.50 KM16.25138.60
6.Cause Way7.00 No15.1922-01-201610-03-20177.00 No7.00 No1.7815.19
7.Culverts/Scupper 45.00 No91.3403-08-201515-02-201745.00 No45.00 No10.7191.34
8.longitudinal Drain10500.00 m60.9102-02-201605-05-201710500.00 m10500.00 m7.1460.91
9.Parapet250.00 No11.4620-01-201730-05-2017250.00 No250.00 No1.3411.46
10.Road Furniture239.00 No2.6302-03-201602-06-2017239.00 No239.00 No0.312.63
Total Amount: 852.8 100   852.8
Remarks: No Remarks       Work Program Made On: 13-07-2015        Updation of work program on: 22-01-2018       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-October-201566.13  lakh
2.30-November-201516.76  lakh
3.24-December-201524.99  lakh
4.25-January-201650.37  lakh
5.29-February-201655.81  lakh
6.30-March-201685.55  lakh
7.02-May-201627.87  lakh
8.31-May-201632.11  lakh
9.30-June-2016109.21  lakh
10.31-August-201632.02  lakh
11.26-October-201636.06  lakh
12.17-December-201616.59  lakh
13.07-March-201757.15  lakh
14.31-March-201770.67  lakh
15.05-May-201735.24  lakh
16.20-May-201746.42  lakh
17.14-July-201779.14  lakh
18.28-July-201725.64  lakh
19.12-October-201748.71  lakh
20.27-November-201759.59  lakh
21.11-December-201726.62  lakh
22.28-August-20183.20  lakh
Total 1005.85  lakh
% Payment 99.96 %
Advance Amount:  222.85  lakh        Recovered Amount:  222.85  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 377   No. of Test Done : 419    No. of Test Passed : 361   No. of Test Failed : 58   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.63
Number of Notice(s) issued: 75

Mobile Pic Upload

Number of Pics Available on Web Repository: 69
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.28-03-2017Ch 1.750Social complianceKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
2.28-03-2017Ch 2.925Sprinkling of water over G3Kirti Vardhan NegiAEDEA WB Gopeshwar See Pic
3.28-03-2017Ch 6.475Gradation of G3Kirti Vardhan NegiAEDEA WB Gopeshwar See Pic
4.28-03-2017Ch 1.780Checking of coarse sand for type B seal coatKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
5.25-03-2017Ch 1.150Grievance by mota villagers for construction of scupperKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
6.25-03-2017Checking superelevation at ch 0.225Checking superelevationKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
7.25-03-2017Ch 0.150Gradation of G2 layerKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
8.08-03-2017Ch-10.500Site visit chief SirPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
9.07-02-2017Ch 3.525Aiv testKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
10.07-02-2017Ch 10.300G2 layer thickness checkingKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
11.07-02-2017Ch 1.800Slope checking of wallKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
12.07-02-2017Ch 1.125Thickness checking of drainKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
13.06-02-2017Ch-1.125C type drain workPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
14.02-02-2017Ch-3.100Slumptest ofcementconcrete inRaftPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
15.02-02-2017Ch-3.1003M spanculvert RR MasonryPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
16.02-02-2017Ch-3.1003M spanculvert span checkingPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
17.02-02-2017Ch-6.900RR.DRYworkin R/wPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
18.01-02-2017Ch-2.600AIV testing G3Pramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
19.13-12-2016Ch-5.850Causeway kharanjaPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
20.18-11-20164.800Mowaja prakranPiyush MishraJEUDRP R&B Gopeshwar See Pic