Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Pursari Palethi Sartoli Work Completed
Project: UDRP-RB UID: 1265 Sanction Cost: 164.11  lakh Length: 1.000 KM.
District: Chamoli Block: Dasholi Constituency: Tharali Circle: Rudraprayag WB Circle
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 91        Package Name:  UDRP/PWD/02/08/RD/080        Tender Date: 18-02-2015        Current Status: Agreement signed        Achieved on Date: 05-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/08/RD/080      Contractor Name: Dream Real Infra
Start Date:  12-06-2015      Intended Completion Date:  11-04-2017      Original End Date:  11-09-2016
Total Bond Cost: 10606269.9 (106.06 lakh)        Variation Cost: 4998077.98 (49.98 lakh)    Hence Total Bond Cost is   15604347.88 (156.04 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 111363 for 21 days        LD Analysis for Milestone2: calculated LD is Rs 1309841 for 247 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.50 KM7.8821-06-201501-07-20170.50 KM0.50 KM147.88
2.R/Wall, B/ Wall Type Protection works400.00 m40.5302-07-201515-08-2017400.00 m400.00 m72.0240.53
3.G-20.00 KM0.0014-06-201620-01-20170.00 KM0.00 KM00.00
4.G-30.00 KM0.0001-07-201615-02-20170.00 KM0.00 KM00.00
5.PC/CC i/c Prime Coat, Tack Coat0.00 KM0.0002-10-201631-03-20170.00 KM0.00 KM00.00
6.Culverts/Scupper 4.00 No6.4410-08-201501-05-20164.00 No4.00 No11.456.44
7.longitudinal Drain75.00 m1.2111-02-201615-01-201775.00 m75.00 m2.141.21
8.Parapet0.00 No0.0011-07-201631-03-20170.00 No0.00 No00.00
9.Road Furniture2.00 No0.2208-08-201608-08-20162.00 No2.00 No0.390.22
Total Amount: 56.28 100   56.28
Remarks: No Remarks       Work Program Made On: 14-07-2015        Updation of work program on: 17-11-2018       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-October-201513.66  lakh
2.24-December-201512.80  lakh
3.23-January-20164.38  lakh
4.11-May-20169.54  lakh
5.30-September-20165.46  lakh
6.30-December-20168.50  lakh
7.18-September-20183.95  lakh
Total 58.29  lakh
% Payment 37.35 %
Advance Amount:  12.20  lakh        Recovered Amount:  12.20  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 139   No. of Test Done : 157    No. of Test Passed : 140   No. of Test Failed : 17   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 85.58
Number of Notice(s) issued: 96

Mobile Pic Upload

Number of Pics Available on Web Repository: 54
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.14-04-2017Ch 2.300Bitumen content test of pc found 4 percentKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
2.14-04-2017Ch 0.550Pc layingKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
3.14-04-2017Ch 0.525Pc layingKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
4.14-04-2017C.h 0 .100Checking of thickness of pcKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
5.08-03-2017Ch-0.350Site visitPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
6.31-10-2016Ch0.325W/cPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
7.28-10-20160.325Wire Crates work in progressAshwani KumarREDSC4 R&B WB Chamoli See Pic
8.23-10-20160.000S.E. Sir visit at purshari sitePiyush MishraJEUDRP R&B Gopeshwar See Pic
9.23-10-2016300Site visit by geologist sirPiyush MishraJEUDRP R&B Gopeshwar See Pic
10.19-10-2016750Puccka drainPiyush MishraJEUDRP R&B Gopeshwar See Pic
11.19-10-2016300Shrinking zone at purshari sitePiyush MishraJEUDRP R&B Gopeshwar See Pic
12.19-10-2016+250W/C work at shrinking areaPiyush MishraJEUDRP R&B Gopeshwar See Pic
13.15-10-2016Ch-0.78024/09/16 after complete ID no 23502 we have maintend the slope of wall and the interlocking of stone masonry and bad quality stone removed and good workmanshipPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
14.15-10-2016Ch-0.300Hillside cuttingPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
15.26-09-2016Ch-0.780Retaining wall RR.Dry work in progressPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
16.06-08-2016Ch-0.750Layout for Retaining wallPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
17.04-08-2016Ch-0.650Hillside cuttingPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
18.20-06-2016Ch -0.650Causeway pccPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
19.16-06-2016Ch-0.650Causeway kharanjaPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
20.01-06-20160.100WBM G2 layerAshwani KumarREDSC4 R&B WB Chamoli See Pic